Safe and civilized construction plan
Civilized construction technical measures
This project is located in --------; the project includes four two-story shops and one five-story (some six-story) commercial office building In the comprehensive building, Buildings 1# and 2# adopt a cast-in-place concrete mixed structure, while Buildings 3#, 4#, and 5# adopt a cast-in-place reinforced concrete frame structure, with an earthquake resistance level of level 4, and a total construction area of ??13,716 square meters. This project was developed by ------, designed by ------ Design Institute, supervised by ---------- Supervision Consulting Co., Ltd. throughout the process, and constructed by ---------- construction.
Civilized construction is an important part of the construction of corporate spiritual civilization. It is an important measure to speed up project progress, reduce project costs, improve project quality and ensure safe production and construction. Our project department will implement the following aspects:
1. Make a good site layout
The construction site will design and prepare a specific and targeted site layout according to the construction progress and construction plan requirements, so that materials can be stacked and construction operations can be smooth and reasonable. ; And consider it from the aspects of safety management, publicity and education. This provides a strong guarantee for the implementation of safety work. This project is located to the west of Zhapu Nanwan Road and south of Zhongshan Road, and the site appearance has good conditions for civilized construction. At the same time, a project that requires higher management goals must not only have a higher starting point. , and it must be comprehensive, so strengthening civilized construction management is becoming more and more prominent and necessary. We will try our best to increase investment to improve facilities.
2. On-site fencing
The construction area is separated from the office area, and the construction site is separated from external roads. 2.5-meter-high fencing walls are set up continuously along the perimeter of the project to ensure solidity and stability. , beautiful, the inside and outside must be painted, and the exterior facade tone is white to visually form a sense of wholeness and stability. The written content includes the construction unit, survey unit, design unit, construction unit, supervision unit, etc.
3. Closed management
1. Set up a gate at the entrance and exit of the construction site with a height of 2.5 meters; the height of the door piers on both sides is 3.2 meters. There is a corporate logo on the gate with the words " The name of the company "Nanqiao Construction"; the color of the gate is white, and the gate is equipped with two inner doors, with a total width of 5 meters. The Nanqiao Construction Company logo is placed in the middle of each door, and the requirement is to ensure that the complete position of the logo is appropriate.
2. There is a guard room next to the gate. The guard should be a full-time security personnel and be on duty 24 hours a day. There should be a guard system in the guard room, a list of security personnel and their responsibilities, and a registration file for personnel entry and exit. When project management and construction personnel enter the construction site, they must abide by various safety systems and wear safety helmets and badges correctly.
4. Construction site
The main road at the entrance of the site and in front of the office shall be hardened to ensure smooth, flat, clean and free of scattered objects. At the same time, a temporary water supply and drainage system in the site should be built along the edge of the hardened floor to ensure smooth drainage and no accumulation of water. A smoking room should be set up on the construction site to prohibit random smoking, and greening should be arranged in open areas.
5. Stacking of materials
Construction materials and turnover materials on the construction site should be stacked according to the general construction plan. Materials should be classified and neatly stacked, and name, variety, and specification signs should be inserted and hung to make it clear at a glance. Set up obvious danger signs in flammable and explosive places such as paint, oxygen, and acetylene bottles. Construction waste is piled up neatly on site, emphasizing that construction workers of all types of work must do a good job in cleaning up their hands every day.
6. On-site fire prevention
The fire prevention responsibility system shall be strictly implemented at the construction site. Fire protection and flammable and explosive materials are managed by dedicated personnel, equipped with a sufficient number of fire-fighting equipment (fire extinguishers, fire-fighting boxes, etc.) that meet the requirements, and the layout is reasonable. Smoking is strictly prohibited in carpentry rooms, warehouses and places where flammable and explosive materials are stored and special safety measures must be taken.
7. Comprehensive Public Security Management
Strengthen safety, civility, and courtesy education for on-site construction personnel, formulate a security and security system, implement responsibilities, and divide them among individuals. Employees should abide by operating procedures, pay attention to the construction of spiritual civilization, set up study and entertainment rooms on the construction site, carry out various cultural and sports activities for employees, strictly prohibit gambling, fighting and other illegal activities, actively cooperate with the comprehensive improvement of social security, and do a good job in various tasks.
It not only relieves employees from worries and improves work efficiency, but also strengthens the construction of spiritual civilization on site.
Set up a school for migrant workers, hang the "Code for Migrant Workers' School Students" and "Management System of Migrant Workers' Schools" signs on the wall, and carry out regular and irregular learning activities.
8. Construction site signs
Five signs and one picture will be set up next to the office area in the construction site. Uniform safety slogans, banners, and various prohibition signs will be hung in the construction site, and publicity boards and reading boards will be set up. Newspaper columns, etc.
9. Living Facilities
Three-format toilets, ceilings, whitewashed walls, ceramic tiles for wall skirts and toilet bowls, floor tiles for the floor, and a simple septic tank connected to the drainage system , cleaned and disinfected by dedicated personnel. Toilets are set up on each floor of the construction site with signs, and dedicated personnel are responsible for cleaning.
10. On-site office and health first aid
1. Set up a temporary room on site as an office, paint the indoor ceiling white, and display progress schedules, construction permits, and positions of various professionals on the walls. Responsibility system, various safety management systems, safety management network diagram, quality system diagram, project manager qualification certificate, barometer, etc., various quality and safety technical materials are organized into categories.
2. The construction site is equipped with a health care medicine box containing various first-aid medicines and equipment, first-aid measures are established and equipped with first-aid equipment and trained first-aid personnel carry out publicity and education on health and disease prevention.
11. Community Services
The construction site shall take effective control measures for construction machinery that produces noise and vibration, and take measures to prevent powder and dust. Formulate on-site non-disturbing measures, set reasonable safe working and resting hours, adjust the equipment and use of labor and machinery, and report to the Municipal Environmental Protection Bureau for approval of continuous construction under special circumstances, put up notices to protect the people, and do a good job of explaining to surrounding residents.
12. Technical measures for fire prevention at the construction site
1. When preparing the construction organization design, the general layout plan, construction methods and construction technology of the construction site shall comply with fire safety requirements, and fire protection facilities This should be reflected in the general floor plan.
2. Fire operations should be clearly divided at the construction site, and areas such as flammable and combustible material yards, warehouses, flammable waste collection stations, and living areas should be separated.
3. The construction site should be equipped with sufficient fire-fighting equipment, and designated personnel should be maintained, managed, and regularly updated to ensure completeness and usability. Buildings over 30 meters in length should have fire-fighting water sources and pressurized pumps installed at each floor. There is a fire water source interface on each floor.
4. Smoking is strictly prohibited at the construction site, or a smoking room should be set up as required.
5. The distance between welding and cutting operation points and dangerous goods such as oxygen bottles and acetylene bottles shall not be less than 10 meters, and the distance from flammable and explosive materials shall not be less than 30 meters.
6. The storage distance between acetylene bottles and oxygen bottles shall not be less than 2 meters; the distance between them when in use shall not be less than 5 meters.
7. Valves, meters and other accessories on welding and cutting equipment such as acetylene bottles and oxygen bottles must be complete and valid, otherwise they are not allowed to be used.
8. Welding and cutting operations at the construction site must comply with fire protection requirements and strictly implement the "ten no burning" regulations.
9. If open fire operations are carried out in large areas or in special environments at the construction site, the fire approval procedures and guardianship should be completed.
10. When using electricity at construction sites, the "Technical Specifications for Temporary Electricity Safety at Construction Sites" should be strictly implemented, and power management should be strengthened to prevent fires.
11. Temporary carpentry rooms, paint rooms, woodworking machine tool rooms, etc., should be equipped with one fire extinguisher of the appropriate type for every 25 square meters; oil depots and dangerous goods warehouses should be equipped with a sufficient number and type of fire extinguishers.
12. It is strictly prohibited to use an open flame to melt asphalt on the roof.
13. If a fire alarm or fire is discovered, the police should be called quickly and efforts should be actively organized to put out the fire.
14. Regularly provide fire safety education and popularize fire protection knowledge to employees, and improve employees’ fire safety capabilities and fire prevention vigilance.
15. The full-time safety officer of the project department is responsible for monthly fire safety inspections at the construction site. The inspections must have records and corrective measures and implementation status.
16. Necessary punishments will be imposed on relevant personnel who violate fire safety regulations and cause fires, and those in serious cases will be held accountable in accordance with the law.
13. Approval system for open flame operations
1. The use of electrical equipment and chemical hazardous materials must comply with technical specifications and operating procedures, strictly implement fire prevention measures to ensure construction safety, and violations are prohibited Operation.
2. The use of fire in construction operations must be reviewed and approved by the project department before operation. The license is only valid at the designated location and time.
3. The use of open flames is prohibited in places with fire hazards. When it is really necessary to use open flames, approval procedures must be obtained from the project in advance, and strict fire-fighting measures must be taken. Dedicated personnel are assigned to monitor at designated locations to ensure safety.
4. Electric welding must be carried out by professionals and must hold a certificate.
14. Fire Prevention Inspection System
In order to improve the safety and fire prevention work at this construction site, protect property and personal safety, and ensure the normal construction progress of the project, the following system is specially formulated:
p>
1. Members of the fire prevention leading group, in addition to daily fire prevention inspections, are led by the team leader during the monthly inspections organized by the project department. Check the fire prevention situation of the construction site carefully, discover hidden dangers in time, and eliminate them in time to nip the fire in the bud.
2. The fire prevention inspection content, in addition to the fire prevention inspection system formulated by the company, should be timely inspected at the wood mold stacking point, carpentry room and other places based on the actual situation of the construction site. If problems are found, corrective measures should be proposed in a timely manner. Carry out rectification and review.
3. Never let go of any spark of fire. Those who cause fires will be dealt with differently according to the severity of the case and must also be given certain financial penalties.
4. Inspectors must be serious and responsible, and must not take it lightly or carelessly. In addition to educating irresponsible employees, they should be dealt with seriously when necessary.
15. Storage and management system for flammable and explosive materials
1. The storage and storage of construction materials should comply with fire safety requirements, and flammable and explosive materials should be stored in special warehouses and classified , stacked separately and kept ventilated. Electricity usage complies with fire protection regulations.
2. Chemical flammable items and compressed or flammable gas containers should be stored in special warehouses according to their properties.
3. The interior of the construction project is not allowed to be used as a warehouse, and flammable and combustible materials are not allowed to be accumulated.
4. When using flammable and explosive items, fire prevention measures must be strictly implemented, a person in charge of fire prevention must be designated, and fire extinguishing equipment must be equipped to ensure construction safety.
5. In terms of collection: Warehouse custodians must carry out registration work and conduct inspections when the work is completed and put into the warehouse to ensure that they are well aware of the next collection.
- Related articles
- The Black Tiger General who walked out of the mountains
- A Complete Collection of Vegetable Varieties in Northeast China. What are the special vegetables in Northeast China?
- 50-word circle of friends Yangmei propaganda language copy?
- What are the attractions in Maoming Lady Xian’s Hometown Cultural Tourism Scenic Area?
- How about the Kunlun series of Tianwang?
- What does Uncle Gemini Orchard like?
- What is the subway branch of the Public Security Bureau?
- Why do Balenciaga short sleeves have trapezoidal marks?
- What are the children's songs about fire safety?
- How to deal with the law without hitting yourself?