How does Party A determine the cost of Party B's safe and civilized construction?

1. The cost of civilized construction on site is fixed rate, and this money is earmarked. However, if Party A has high requirements on site, and Party B thinks that such a high standard exceeds the standard of fixed rate, Party A needs to increase the expenditure according to the actual expenditure. If Party B loses money, it has the right to complain

2. The expenses for safe and civilized construction shall be paid by the construction unit for safe production and civilized construction on the construction site. At present, the general practice is that the construction unit pays the construction unit in batches according to the progress of the project. In some places, this part of the cost is paid to a third-party account and then paid to the construction unit according to the needs of the construction site.

1 the purchase of safety construction signs and the setting of publicity columns (including the purchase of newspapers and periodicals, promotional books and slogans)

2 the safety protection facilities of protective sheds and fences

3 the hardening of the site, the car wash tank

4 mud, sewage treatment, garbage and demolition waste and the control of dust removal

5

Extended reading:

1. The charging standards are: 12 yuan/m2 for safety production measures, 8 yuan/m2 for civilized construction measures and 1 yuan/m2 for environmental protection measures. This expense is mainly used to set up a closed enclosure around the demolition site and equip the construction site with sprinkler equipment, etc., which is earmarked for special purposes and finally included in the total cost of demolition.