When will the construction elevator be dismantled?
The overall plan for elevator demolition construction is as follows:
1. Check before dismantling the elevator:
1 Understand the layout of the construction environment and surrounding environment, such as buildings, ditches, pipes, cables, flammable items, etc., and the obstacles on site need to be cleaned.
2 Carefully check the screws, wire rope clamps, clamps, snap rings, rigging and other parts of the trolley, and conduct a comprehensive inspection. If damage or potential hazards are found, they should be replaced or repaired in time.
3. All construction personnel shall operate in accordance with the safety operation procedures of the construction elevator, and report to the person in charge of Party A for solution in time if there is any confusion.
4. Check the bottom pit of the elevator shaft. Whether there are inflammable and explosive articles. Clean it up
Various levels of safety technology
1 Before demolition, make a plan, conduct a comprehensive safety inspection on the construction elevator, and maintain smooth communication between the upper and lower parts.
2. In the process of demolition, a special person shall be assigned to command in a unified way, and a warning zone shall be set on the ground, warning signs shall be erected, and special personnel shall be assigned to command and supervise, and non-operating personnel shall be prohibited from entering or approaching.
Workers must wear safety helmets (fasten safety belts, insulating rubber shoes and gas masks when necessary) before they are allowed to work.
4 When dismantling, notify the other party's construction personnel (computer room construction personnel) to prevent falling, retreat to a safe place after the operation is completed, and the commander can not proceed to the next operation until it is safe.
During the construction period, it is forbidden to play, joke, talk about things unrelated to work, do homework after drinking, and throw objects down.
6 Materials transported to the ground shall be classified and stacked in designated places, and waste gas and harmful substances shall not be discarded at the site. 7 In the process of demolition, it is not allowed to change people in the middle. If you need to change people, you should explain the demolition situation clearly before leaving.
3. Matters needing attention when disassembling the elevator:
1 All connecting bolts must be tightened with lock nuts.
Pulley phenomenon occurs in automobile operation. First, adjust the engine room brakes.
Demolition items piled in the car (parts removed from the elevator) are strictly prohibited from being overweight.
4. Construction personnel must wear safety helmets. (If necessary, seat belts, gas masks, insulating rubber shoes, etc. ).
Security officials are responsible for hanging and removing warning signs. (Please don't go near the elevator for construction)
4. Demolition of the elevator construction procedures:
1. Do a good job in the safety protection inspection of demolition, debug the brakes, check whether the wire rope is aging and whether the screws in key parts are loose.
2. Lift the car to the top floor, cut off the current, and insure the additional pulley.
3. The construction personnel shall stand on the top of the car, and dismantle the main and auxiliary tracks and hall doors of each floor from top to bottom (each hall door must be blocked, and notices and slogans shall be posted. Party A is responsible for the materials).
4 The elevator parts and hall doors removed from each floor are put in boxes (each floor is coordinated by the construction personnel).
Computer room personnel use braking and anti-skid measures to cooperate with the local train.
6. After the shaft is dismantled, safety measures shall be taken with additional wire ropes. Use the pulley principle to slowly lower the counterweight (both counterweight and counterweight are in the pit at this time).
Then, some construction workers took the car and the bottom of the car apart and moved out the counterweight.
8 Dismantle the equipment in the machine room, such as motors, tractors, heavy equipment, etc., for handling.
9. Load the parts to be disassembled. If the hall door needs to be blocked, seal the door and check whether it is firm.
10 Final cleaning. Put all construction tools in order, clean up the garbage, etc. ~ ~ ~ The construction process is completed.
- Related articles
- Gym Advertising SloganGym Advertising Slogan
- What are the specialties in Inner Mongolia?
- Fertilizer Management Measures 2022
- Talk about 3.15 Rights Protection Day
- Weinan City Civilized Behavior Promotion Regulations
- How to tell the authenticity of blueberries?
- A short sentence that can make people burst into tears. A complete sentence that can make people burst into tears.
- The story and brief introduction of Zhang Xiangeng, a national model of teaching and educating people in 2022
- Collect a team slogan at the oil production station: low carbon. . . Green. . . Oil production. . . The number of words in safety and other aspects is preferably within ten words.
- Danger! You can't do it with a truck that can be loaded!