Joke Collection Website - News headlines - How is the South-to-North Water Transfer Project progressing now?

How is the South-to-North Water Transfer Project progressing now?

20 1 1, the Henan section of the Middle Route of South-to-North Water Transfer Project entered the peak period of the whole line. In order to achieve the goal of "connecting the north of the Yellow River and developing the south of the Yellow River", the pressure of construction period and various contradictions are intertwined. How to implement the spirit of the Fifth Plenary Session of the Construction Committee and the South-to-North Water Diversion Work Conference in 20 1 1, and how to grasp the key points and solve problems are very important for the smooth completion of the whole year. On March 25th, our reporter interviewed Wang Shushan, director of the South-to-North Water Diversion Office and director of the provincial government immigration office, on how to speed up the construction of the project.

Reporter: At present, what is the progress of the South-to-North Water Transfer Project in Henan?

Wang Shushan: The Henan Provincial Party Committee and the provincial government attach great importance to the construction of the South-to-North Water Diversion Project, and always regard the construction of the South-to-North Water Diversion Project as an important political task entrusted to Henan by the CPC Central Committee and the State Council, as an important livelihood project, and mobilize Qi Xin at all levels and departments to work together to fight the tough battle of the South-to-North Water Diversion Project. Since last year, the project construction has been accelerated in an all-round way, the resettlement has progressed smoothly, the water source protection has been solidly promoted, and all the work has achieved remarkable results. * * * The annual investment was 23.083 billion yuan. The year of 20 10 has become the most arduous year since the construction of the South-to-North Water Transfer Project in our province started in 2005, and it is also the year with the most investment and the greatest effect.

As far as engineering construction is concerned, in the first five years, our province started construction of 280 kilometers. After fighting day and night last year, the trunk line project with a total length of 73 1 km entered the construction stage of the whole line. At present, some canal sections of the 249.7 km trunk line project north of the Yellow River have begun to take shape, and various sections of the 48 1.3 km trunk line project south of the Yellow River have been started one after another. The construction goal of "developing the north of the Yellow River and connecting the south of the Yellow River" set by the State Administration of Regulation and Control in 20 10 was successfully realized. At the same time, quality and safety are always under control, and no safety accidents have occurred.

Reporter: 20 1 1 This year is a crucial and decisive year for the construction of the South-to-North Water Transfer Project in Henan Province. What is our overall goal?

Wang Shushan: In 20 1 1 year, our province plans to complete the construction of South-to-North Water Transfer Project and invest 20 billion yuan in resettlement, and strive to break through 22 billion yuan. Its main objectives are: to speed up the construction of Henan section of the middle route of South-to-North Water Transfer Project and ensure the realization of the construction goal of "connecting the Yellow River to the North and prospering the Yellow River and Henan"; Complete the relocation task of the second batch of 86 1 10,000 immigrants in Danjiangkou reservoir area on schedule to ensure the realization of the goal of "four-year task, two-year completion"; Continue to do a good job in the relocation and closing work of the South-to-North Water Transfer Project, and further create and optimize the construction environment; Do a good job in the water quality protection of Danjiangkou reservoir water source area and water source protection areas on both sides of the main canal to ensure the realization of the goal of "one pool of clear water is put into storage and one pool of clear water is sent to the north"; Start the construction of supporting projects as soon as possible to ensure the simultaneous completion and realization with the main project.

Reporter: At present, the South-to-North Water Transfer Project faces many difficulties, especially the practical problems of speeding up the construction progress and ensuring quality and safety. How to balance these two aspects to meet the needs of engineering construction in peak and critical periods?

Wang Shushan: The main construction task of the Middle Route Project was completed at the end of 20 13, less than three years ago. However, the bidding task of the 335-kilometer trunk line project in our province was completed at the end of last year, and construction teams entered the site one after another, especially some key canal sections and buildings south of the Yellow River that control the water supply target. The construction period is even more urgent. There are many projects under construction, and the remaining time is short. Coupled with the influence of winter and rainy season, it will bring great pressure to the project construction. A slight mistake may affect the timely realization of the water supply target. At the same time, there are many high-fill canals in trunk projects in our province, and the special geological conditions such as expansive soil (rock) canals, high underground canals and coal mine goaf are complex, and the design standards and construction technology are strict. In addition, the layout of a large number of cross buildings makes it impossible for the whole channel to be continuously constructed, which makes it difficult to control the quality and safety, with high risks, and is prone to quality and safety hazards. Under the grim situation that all construction units are scrambling to catch up with the construction period, the risk of quality and safety control is further increased. In particular, the expansive soil (rock) canal section in our province is 340 kilometers long, accounting for 46% of the length of domestic trunk lines; The highest fill in Jiaozuo city section is 8 to 10 meters above the ground; The design flow of Taocha canal head in Nanyang is 350 cubic meters per second, and the design flow of Zhanghe outlet in Anyang is 235 cubic meters per second. The bottom of the canal is high and the flow is large. If major technical problems are not solved well, once there is a water leakage accident, the consequences will be unimaginable.

In the face of the contradiction between schedule and quality and safety, we always adhere to the unity of project schedule and quality, speed up the project construction on the premise of ensuring quality, and achieve high quality and high price, high quality and fast speed, good and fast. This year, we will make great efforts to grasp the project construction progress, and take the project construction progress as the top priority with a strong sense of urgency of "can't sit still, can't wait, and can't slow down". Taking the objectives and tasks determined by the fifth meeting of the State Council South-to-North Water Diversion Project Construction Committee as hard indicators, we will further refine the plan, reverse the construction period, and take all necessary measures to ensure the successful completion of the annual construction tasks. Sign the responsibility book of the project construction progress target with the construction management unit and each construction unit, implement rewards and punishments, strictly supervise the contract, and urge the construction unit to perform the contract. Intensify unannounced visits and urge them regularly. Actively coordinate the governments along the line to continue to maintain the project construction environment, and coordinate relevant departments to timely implement the relocation of special facilities.

At the same time, we will pay close attention to quality and safety. First, strictly implement the system of quality rewards and punishments and accountability for quality accidents, and always maintain the high-pressure situation of quality accountability. The second is to strengthen site management, requiring all parties to strengthen the monitoring of project quality. The third is to strengthen government quality supervision and special inspection, and build a multi-level supervision and inspection system. The fourth is to strengthen safety responsibility, increase the investigation and punishment of safety accidents and hidden dangers, and prevent accidents. Through the joint efforts of all levels and departments, the quality and safety of the project are ensured without accidents. The qualified rate of unit project quality reached 100%, and the excellent rate remained above 90%.

Reporter: the requisition and relocation of trunk lines is also one of the restrictive factors of engineering construction. What's the progress so far? What's the plan for the next step?

Wang Shushan: On the basis of the transfer of1069,000 mu of construction land in the first five years, we completed the transfer of 239.7 million mu of construction land (permanent land/kloc-0.05 million mu, temporary land1347,000 mu) south of the Yellow River in seven months last year. At present, all the construction passages of the middle route project in our province have been connected, and 362,700 mu of construction land (permanent land of 6,543.8+059,300 mu, temporary land of 203,400 mu) has been handed over. Besides the temporary land of 6,543.8+0.6100 mu north of the Yellow River, it needs to be requisitioned in time according to the construction progress, at the same time, power facilities, communication, radio and television will be relocated. The whole process realized the harmonious and civilized relocation.

In the next step, we will actively communicate with relevant special units, track the progress of relocation and speed up the pace of relocation. For the special facilities newly transferred to temporary land, we should pay close attention to the relocation to meet the needs of engineering construction.

Reporter: The resettlement task of Danjiangkou reservoir area in Henan Province is very heavy. What's the progress of resettlement at present, especially this year? It is necessary not only to complete the last batch of large-scale resettlement tasks, but also to increase support for the relocated people in the later period. What are our work arrangements in this regard?

Wang Shushan: Since June 5438+065438+ 10, 2008, the overall progress of resettlement in the reservoir area of our province has been relatively smooth. In August 2009,1.65,438+0.00 was successfully relocated in the first battle. In September 2065, the first batch of 64,900 immigrants fought a beautiful battle, coordinating more than 70,000 relocation service personnel (times) and using vehicles1.65,438+0.00. At the same time, on June 2, 20 10, 18, the construction of the new village with the second batch of immigrants of 86 10/0,000 people and the resettlement site of15 started. At present, the main construction of immigrant housing has been basically completed, and follow-up work such as the construction of new villages and the formulation of immigrant relocation plans is being carried out in various places. By the end of August, the relocation goal of "four-year task and two-year completion" for 0/62,000 immigrants in the reservoir area will be realized.

In the next step, we will strive for time and speed according to the requirements of the time node, and fully promote the construction of the second batch of immigrant new villages to create conditions for starting the relocation on time. The centralized relocation of the second batch of immigrants was completed from May 1 day to August 3 1 day. Around this plan, all localities are in full swing to carry out various preparatory work before relocation.

For the 76,000 people who have moved, through the joint efforts of all levels and departments in the previous stage, the follow-up assistance for immigrants has achieved remarkable results, the production and life of immigrants have been properly resettled, and the immigrant masses have been generally stable. In the next step, we will continue to strengthen the training of immigrants' production skills and improve their employment and entrepreneurial ability; Strengthen communication and coordination, formulate preferential policies, actively transfer labor force and expand employment opportunities for immigrants; As soon as possible, we will implement the plan for the use of construction land and production development funds for aquaculture parks, help guide immigrant villages to formulate production development plans, and develop tertiary industry projects such as characteristic planting, forestry and fruit industry, aquaculture and agricultural product processing industry according to local conditions, so as to provide conditions for immigrants to become rich.

Reporter: How to do a good job in immigration stability?

Wang Shushan: At present, the immigrants in the reservoir area of our province are generally stable. However, due to the large number of immigrants, complicated situation, wide coverage and slight negligence, unstable factors may occur. Therefore, we ask all levels and departments to keep a clear head, always regard the maintenance of stability as the key work in engineering construction and immigration work, strengthen legal education and policy propaganda for the immigrant masses while adhering to rigid policies and family operations, seriously solve outstanding problems that the immigrant masses have strongly reflected, and sincerely solve problems for the people; Insist on going deep into the grass roots, go deep into the reality, really think about what the masses think, be anxious about what the masses are in a hurry, meet their needs, truly grasp the matters concerning the vital interests of the people who emigrate and relocate in the reservoir area, and let the masses become the beneficiaries of the construction of the South-to-North Water Transfer Project; Formulate and improve the emergency plan for emergencies, promptly investigate and resolve contradictions and disputes that affect social stability, solve problems at the grassroots level, eliminate contradictions in the bud, realize harmonious immigration, harmonious immigration and harmonious construction, and make positive contributions to ensuring the overall social stability of the province.

Background link:

Main project: The total length of trunk line project in Henan is 73 1 km, which flows through 8 provincial cities and 2 1 county (city), requiring 603,000 mu of land acquisition and 21.7,000 immigrants.

Immigrants in the reservoir area: Danjiangkou reservoir area involves rural immigrants from Henan province1620,000 people, which is divided into three stages: pilot immigration, the first batch and the second batch. The overall requirement is "four-year task, two-year completion", and the difficulty and intensity of resettlement are unprecedented. Especially this year, it is necessary to complete the 86 100 rural migration task and continue to do a good job in the follow-up assistance of the 76,000 relocated population.

Water source protection: The water source of the Middle Route Project * * involves six counties (cities) of Nanyang, Luoyang and Sanmenxia in Henan Province, namely Xichuan, Xixia, Neixiang, Dengzhou, Luanchuan and Lushi, with a total population of 1, 326,5438+0,400.

Source: Report of South-to-North Water Diversion Project in China.