1) Measures for site management . Made of 5 thick iron sheets welded.

(2) Use 2m high-pressure steel plates (0.6-0.8 thick) around the construction site. Surround the stalls and paint posters or slogans.

(3) Set up a "Seven Signs and One Picture" construction sign at the gate:

Project Introduction

List of Project Responsible Personnel

Six Disciplines of Safety Production

Safety Production Counting Sign

Ten Safety Technical Measures Sign

Fire Prevention Instructions

Hygiene Instructions Sign

p>

General layout of the construction site

(4) The construction area and the dormitory area are strictly separated, the site appearance is neat and orderly, the material area is neatly stacked, and there are guards on duty. Set up eye-catching safety signs and set up eye-catching safety warning signs in construction areas and dangerous areas.

(5) Establish a civilized construction responsibility system, divide areas, clarify management personnel, implement a tagging system, and ensure that the site is clean and tidy.

(6) The ground at the construction site shall be all hardened, and the road material storage site shall be marked with 10 cm of yellow paint. A wide yellow line will be used to divide the area, and greening elements such as flowers and plants should be placed at appropriate locations to beautify the environment.

(7) Build a sedimentation tank for on-site drainage pipes to prevent sewage from overflowing.

(8) Set up publicity slogans and blackboards based on the conditions at the construction site, and change the content appropriately, which can indeed play a role in boosting morale and praising the advanced.

2) Dressing image of construction personnel

All employees should establish the idea of ??abiding by rules and disciplines, adopt a sign-up system, and use unified safety helmets and work clothes. Safety personnel on duty wear different color markings. The construction site leader wears an armband with red characters on a yellow background, and the team safety officer wears an armband with yellow characters on a red background.

(1) Safety helmets

a. Construction management personnel and various operators wear safety helmets of different colors to show distinction:

Department managers, management personnel and external inspectors wear red hard hats; general construction management personnel wear white hard hats; operating workers wear yellow hard hats; mechanical operators wear blue hard hats; mechanical crane conductors wear red safety pads.

b. Paste or print the unit logo in the center of the front of the helmet. Logo size is 2X2 cm.

(2) Clothing: All operators wear uniform clothing, beige jacket with blue pants.

③Basket: The size is 9cmX5.5cm with blue and black characters, uniform number, and a one-inch color photo of the person.

3) Measures for on-site mechanical management

(1) The mechanical equipment used on site must be stored at fixed points on dry surfaces, comply with mechanical safety regulations, and always keep the fuselage, etc. Cleanliness of surrounding environment. The machinery is clearly marked and numbered, and the safety device is reliable.

(2) The sewage discharged by machinery must be discharged and shall not flow anywhere.

(3) Rebar cutting machines, butt welding machines and other machines that require the erection of protective sheds must be strong and beautiful when erecting them, and meet the requirements of the construction layout.

(4) The styles and standards of various electrical boxes for various temporary facilities should be unified, and their placement should be reasonable to facilitate construction and maintenance. 4) Measures for on-site life and hygiene management

(1) Construction site The office should have various charts, plates, and signs. The indoors are civilized and sanitary, the windows are clear and clean, and the order is in order. Green potted flowers are placed indoors and outdoors to beautify the environment.

(2) The construction site offices, warehouses, and staff (including migrant workers) dormitories have full-time health management personnel and cleaning personnel, formulate health management systems, and set up necessary health facilities.

(3) The on-site toilets and surrounding buildings must be kept clean, free of maggots and smelly, and well ventilated. There should be dedicated personnel responsible for cleaning and cleaning. There should be no open urination and toilets should be flushed with water in a timely manner.

(4) Resident family members are strictly prohibited at the construction site, and residents’ family members and children are strictly prohibited from walking or playing at the construction site.

(5) Dormitory management is based on unified management and detailed dormitory management regulations are formulated. Each dormitory is required to draw up a duty list and clean it every day to ensure the neatness of the dormitory. Private wiring and electrical appliances are not allowed in the dormitory.

The dormitory must be sturdy, the installation must meet the standards, the bedding must be neatly placed, the clothes must be clean and hung neatly.

(6) Food management is in compliance with the "Food Guard Law", there are preventive measures to isolate flies and mice, there are covered containers for leftovers, and the internal and external environment is clean and hygienic.

(7) Tea buckets are set up on site. Each bucket is clearly marked and stamped. Special personnel are assigned to refill tea and manage drinking water facilities.

(8) Set up a sedimentation well at the end of the on-site drainage ditch, and clean the sediments in the sedimentation sheet regularly. Canteen sewers and toilet septic tanks must be cleaned and disinfected regularly to prevent the spread of harmful bacteria.

5) Civilized construction measures at the construction site

(1) Set up temporary toilets: Due to the large number of people at the construction site and the long length of the structure, one should be set up every 80 meters on each floor. The urinals are cleaned by someone after get off work every day.

(2) Floor cleaning: After the production team completes its work tasks every day, it is required that the remaining materials must be cleaned up and stacked in specified locations. Individual materials must be stacked randomly on the floor to keep the floor tidy.

(3) Control of construction water: During construction, water consumption is large and water is used in many parts, which can easily cause cross-flow or accumulation of sewage on construction floors and construction sites, contaminate construction products, affect people's walking, and cause uncivilized phenomenon. Take the following measures:

a. Each water supply faucet (energy-saving type) is protected with a homemade wooden box, locked, and has a dedicated person to guard it. Strictly prevent others from opening or destroying it at will.

b. During the construction of the main structure, it is necessary to wash away the dust on the formwork and steel surface before pouring concrete, moisten the formwork, etc., and maintain it after pouring. Place 60mm bricks around the edges of floors, elevator shafts or reserved openings, and plaster the inside with cement mortar to form a closed water retaining line.

c. During the renovation period, the dry bricks must be watered and moistened on the bottom floor before being raised to the floor surface. Watering is not allowed on the floor.

The masonry mortar should be stirred centrally on the bottom layer, and water should not be re-mixed on the working surface.

d. Set up drainage ditches around the site to keep drainage smooth, and set up pools to use rainwater to save water.