Detailed explanation of construction scheme of construction waste transportation
First of all, the dominant idea:
In order to ensure the social environment and environmental protection, under the guidance of the national standards for the creation of civilized cities, with the focus on controlling the dust on the construction site and the pollution of urban roads by transport vehicles, the responsible institutions are set up on the construction site, the tasks are decomposed, the standards are clarified, and the long-term mechanism for the management of dust and transport vehicles on the construction site is established and improved, and effective control and treatment are carried out. My project department has formulated this special plan according to the actual situation on site.
Second, the organization establishment and responsibility system assessment:
This project establishes a management network led by the construction unit, supervised by the supervision unit and worked by the construction unit, and is responsible for the planning, organization and implementation of dust pollution and spill control on the construction site, and makes strategic deployment from the aspects of financial resources, material resources and manpower, so as to bring the dust and spill control in the construction of this project into the overall management.
The responsibility of controlling dust and scattering on the construction site lies with the leadership, the management lies with the post and the key lies with the team. Therefore, on the basis of establishing and perfecting various dust control rules and regulations, the project department must carry out management responsibilities layer by layer, closely link construction dust control with safety production and civilized construction management, make it run through the whole construction management process, become a supplementary element of environmental factors in the safety production guarantee system, and implement the whole process and all-round control.
1, the project manager is responsible for the construction dust pollution control, and takes full responsibility for the construction site dust pollution control.
2. Management personnel's control of construction dust should be included in the whole process of construction management, and management should be strengthened according to their respective responsibilities.
3. Team leader is the first person responsible for dust pollution control in construction, mainly responsible for dust pollution control in construction site.
4. The superior company and the competent department of industry further promote the orderly development of dust prevention work of this project.
5, the project manager and relevant personnel signed a management responsibility, according to the safety production responsibility assessment form for assessment.
6, the project department and the construction team operators to carry out the construction dust, easy to spill control responsibility, formulate reward and punishment system, in order to promote the process of construction dust pollution control.
Four, the project dust prevention and control management system and management system:
Dust prevention and control management system:
1, dust control management objectives, and implement the whole process of dust control management. Ensure that dust pollution accidents do not occur during construction. Abide by the national laws, regulations and relevant documents on environmental protection, and meet the requirements of dust control in environmental protection in the Regulations on Safety and Civilized Management of Construction in Fujian Province.
2. Dust prevention management plan. The Project Management Department formulates the dust control management plan of this project according to the Company's Special Plan for Controlling Construction Dust and Pollution of Urban Roads by Transport Vehicles, and determines the dust control management objectives, dust control management of foreign labor teams, operation management of construction machinery and equipment, use of energy and resources, dust control and overflow prevention, emergency preparation, dust control monitoring and correction, and unqualified prevention. The factors related to dust control in construction are all included and effectively controlled.
3, management system, the establishment of dust control management team, headed by the project manager personally, responsible for the overall coordination, the site security department is responsible for the implementation, and then submitted to the company for approval and filing. The management department sends people to organize and supervise the implementation and implementation of the dust control targets and indicators of this unit every month, as well as the special control scheme to control the construction dust and the pollution of urban roads by transport vehicles.
4. Determine the dust control, protection and management of this project.
The specific dust control factors for dust control and protection of the project are: fencing the material stacking place, cleaning the construction garbage in time, cleaning the tires of vehicles on site, cleaning the construction work surface, and cleaning the domestic sewage and domestic garbage on site.
In addition to the long-term and continuous management of the above construction dust control factors, it is also necessary to formulate relevant plans for key projects, determine specific management indicators and measures, improve the inspection system, and clarify relevant responsibilities.
5, dust control management system
The project manager department is responsible for training the employees of this project department and the professional construction team present on the requirements and knowledge of dust prevention, so as to improve the employees' awareness of environmental protection. The project department should establish and improve the reward and punishment system for dust control and protection, with clear rewards and punishments, and directly link the dust control work with the economic interests of the construction party. Establish an inspection system for dust control and protection, control various dust control factors in each construction process, and link dust control and protection with the construction quality inspection of key construction procedures. Take the one-vote veto system for dust control and dust protection. If the dust control is unqualified, it will not be rectified, and it is not allowed to be accepted and handed over to the next process. And make plans for emergency treatment measures. For dust control and protection projects that do not meet the requirements, timely determine the rectification measures, implement the responsible person for rectification, limit the rectification period, and strengthen the inspection of results.
6, dust control management measures
(1) According to the actual situation of the construction site, enclosure shall be adopted in the construction area, and closed construction shall be adopted as far as possible. (2) The construction waste shall be cleaned up and transported in time, and appropriate amount of water shall be sprayed to reduce pollution.
(3) cement and other flying objects and fine-grained materials should be stored or covered in the warehouse, and measures should be taken to prevent omission, flying during transportation and stacking during unloading, so as to reduce pollution.
(4) All the yards in the yard are on the concrete floor, and the construction site and roads are often cleaned with water to prevent dust.
(5) Strengthen the management of transport vehicles to prevent spillage. It is required that all transport vehicles must be equipped with movable baffles to prevent spillage, and they must be cleaned before they can appear. (6) In order to prevent vehicles from getting muddy on the road, intercepting ditch, grit chamber, water pipe, water gun and other equipment will be set at the gate of the construction site, and a washing platform will be set at the entrance, and special personnel will be assigned to wash the vehicles before they leave the site.
(7) In order to prevent dust pollution in the construction process, scaffolding dense mesh safety net is adopted to effectively control dust in the construction process and effectively avoid environmental pollution. (8) The stacking of engineering materials shall be effectively laid according to the general construction plane, so as to reduce the dust generated in the process of transshipment and environmental pollution. In addition, the construction waste and slag are piled up at fixed points, and it is forbidden to throw loose slag and abandoned building powder at high altitude on the construction site.
Verb (abbreviation of verb) Specific prevention and control measures
1, the construction site is closed with a brick or colored board fence, and the height of the fence is not less than 2.5m..2. Assign a special person to sprinkle water on the road twice a day to reduce dust and control dust pollution.
3, construction waste removal in the building structure, the erection of closed temporary special garbage way transportation or container lifting or bagging, it is strictly prohibited to volley scatters at will. Cover the surface of the garbage pit with a dense mesh safety net, remove the construction garbage in time, and spray an appropriate amount of water to reduce the air pollution caused by dust.
4, cement and other easy to float in the sky, fine-grained granular materials, arranged in the warehouse or tightly covered, to prevent scattering and flying in the process of transportation, take measures to reduce pollution when unloading.
5. All traffic pavements and material storage yards on site are paved and hardened with concrete. All earthwork construction uses dense mesh safety net to cover loess.
6. In the structural construction stage, ready-mixed commercial concrete shall be used for concrete, and the management of ready-mixed concrete transport vehicles shall be strengthened to prevent spillage. It is required that all transport vehicles must be ridged and equipped with movable baffles to prevent spillage, and the concrete must be cleaned before leaving the site.
7. Set up a car wash pool and sedimentation tank at the gate. Vehicles leave the site after cleaning and covering, so as to prevent vehicles from leaving the site with dirt and sand, causing road pollution.
8, the construction area every day to send a cleaning class to clean regularly, timely watering, to ensure that the road is clean, daily vehicle feeding, vehicles must be washed, to ensure that dust is not out of the site.
- Previous article:Are there any sports that use the slogan of queuing?
- Next article:How about soy sauce cake?
- Related articles
- Brief Introduction of Huaqiao Central Primary School in Kunshan City
- What is the mission and vision of Yishiwuyou?
- It is best to give detailed instructions on how to change the words on the led display screen. thank you
- What do you mean by turning the headlights?
- What is the principle of subway braking?
- How to write the title of the news report?
- What are the motivational slogans for struggle?
- Gym safety precautions sign
- He Bin rd school education
- What is the separation of Lu Tian and Lu Zhai?