Joke Collection Website - Cold jokes - How to draw after the project is completed?
How to draw after the project is completed?
1. Obtain the electronic version of the design drawings.
2. Collect all design changes.
3. Modify the original design drawings according to the design changes.
4. focus ~! Must indicate the unconstructed part ~! ! For example, the post-pouring zone of the factory, or the part that is planned to postpone construction. This is very important, otherwise there will be jokes.
(This is the corresponding sentence "Draw what has been done", and the parts that have not been done must be clearly marked)
Don't change anything else, because in theory, it is constructed according to the drawings, and what you made is what you originally painted, so there should be no difference.
4. Water and electricity drawing is a matter of water and electricity specialty, and you can't do it unless your leader is 290.
5. Check the drawings carefully. The actual drawing won't take long. The key is to be careful.
Wish you success ~!
Theoretically, as-built drawings should be drawn at the time of completion. In practice, the owner's handover requirements are met, that is, when the completion acceptance is ready, the as-built drawing must be drawn-the as-built drawing is a project of the completion acceptance.
In addition, as-built drawings and construction drawings are divided into construction, construction and water application.
Question 2: What should I pay attention to when drawing as-built drawings? First, the basic requirements for the preparation of as-built drawings
1. As-built drawings shall use new or clean construction drawings, and shall be stamped and signed as required.
2. Where the construction is carried out according to the drawing and there is no change, the sign of "as-built drawing" can be stamped on the original construction drawing.
3. If the general design changes can be modified or supplemented on the original construction drawing, the construction unit shall indicate the modified contents and basis on the original construction drawing (which must be a new blueprint) as the as-built drawing.
4. The structural form, technology, plane layout, engineering, etc. Major changes have taken place and the map change area exceeds 35%, and the as-built map must be redrawn. Re-draw according to the original number, and add the word "Jun" at the end. The icon of the new drawing should be marked as "completed"
Stage ".
5. As-built drawings shall be accurate, clear, complete, standardized and revised in place, and truly reflect the actual situation at the time of completion acceptance. Ensure the quality of drawings, make them uniform in specifications, neat and readable, and do not use ballpoint pens or other useful ones.
Painted in faded ink.
6. After the completion of the as-built drawings, the supervision unit shall urge and assist the design and construction units to inspect the as-built drawings.
If it is found to be inaccurate or insufficient, it should be revised and supplemented in time.
7. As-built drawings shall be related to construction drawing design, design changes, material changes, actual construction conditions and quality inspection records.
Meet.
8. Prepare the general description of as-built drawings and the compilation instructions of various disciplines, and explain the compilation principles of as-built drawings, the catalogue and compilation of various disciplines.
System situation.
9. As-built drawings are folded into A4 paper (2 10mm×297mm) according to the folding method of technical drawings.
The icon is exposed.
Question 3: How to draw the as-built drawing of architectural decoration? 1 If the construction is carried out in strict accordance with the design, the original drawing shall be stamped with the completion stamp and regarded as the completion drawing.
Where there are general changes, but the original construction drawing can be modified and supplemented to reflect the actual completion situation, it is not necessary to redraw the as-built drawing, and the construction unit shall make supplementary modifications in accordance with the method specified in the change document, and affix the seal of completion, which shall be regarded as the as-built drawing.
3 If the structural form, process change, plane layout change, engineering change and other major changes or changes exceed the drawing 1/3, the as-built drawing shall be redrawn.
Question 4: Who should draw the as-built drawings? As-built drawings are drawn by the constructor, and it is clear that this is not the service scope of the designer.
If the construction party does not have the ability and needs you to draw the as-built drawing, you should ask it to provide relevant information such as construction drawing changes and charge it a certain fee. The expenses shall be negotiated by both parties. As-built drawings should be stamped with the completion seal of the construction unit, not the seal of the design unit.
Question 5: What's the difference between construction drawing and as-built drawing? The construction drawing is the drawing before construction.
As-built drawings are drawings after construction.
If there is no change, the as-built drawing is equal to the construction drawing. But sometimes, due to the need of site construction or other reasons, some changes will be made on the construction drawing as the as-built drawing. Generally, minor problems will be approved by the design unit (major problems will have design changes).
Question 6: How to draw the as-built drawing is very simple: First of all, understand a truth: As-built drawing is to draw what the construction unit has done.
1. Obtain the electronic version of the design drawings.
2. Collect all design changes.
3. Modify the original design drawings according to the design changes.
4. focus ~! Must indicate the unconstructed part ~! ! For example, it is a post-pouring belt, or a part that is planned to postpone construction. This is very important, otherwise there will be jokes.
(This is the corresponding sentence "Draw what has been done", and the parts that have not been done must be clearly marked)
Don't change anything else, because in theory, it is constructed according to the drawings, and what you made is what you originally painted, so there should be no difference.
4. Water and electricity drawing is a matter of water and electricity specialty, and you can't do it unless your leader is 290.
5. Check the drawings carefully. The actual drawing won't take long. The key is to be careful.
Question 7: How to draw the project completion drawing as a CAD drawing and modify the contents of design changes on the computer? Or draw on the picture with a pen. It's simple.
Sun it into a blueprint and stamp it as completed. Fold it into A4 size. Okay.
Question 8: How to draw the project completion map? What pictures do you draw? The project completion drawing is the original of the construction drawing. Change it, according to the actual construction drawing! Including a lot, the most important thing is water and electricity, that is, line nail trend diagram, water pipe distribution diagram, system diagram (mainly indicating where the water valve is and how to control the switch of the electric box), because water and electricity are the most needed parts, so Party A will pay special attention. Nothing else is important. If the contact list changes, change it directly!
Question 9: How to draw the completed decoration drawings? If there are changed drawings in the design changes, the as-built drawing company will find someone to make a budget, which is definitely linked to the company's profits. After completion, submit it to Party A for review, and Party A will settle the project payment for you after review.
Therefore, the as-built drawing must be the size of the field engineering quantity. You'd better redraw a finished drawing according to the original design drawing, change the drawing, and don't change the dimensions on the design drawing. Because budget personnel usually use orders to calculate the engineering quantity on CAD software drawings, if you only change the size without actually changing the specific size of the drawings, the error is very large, and Party A estimates that it is difficult to get the project payment. If you are familiar with CAD, the as-built drawing can be drawn soon, and you don't have to worry about doing the project.
Question 10: How to draw the building completion drawing is also simple: First of all, understand a truth: the completion drawing is to draw what the construction unit has done.
1. Obtain the electronic version of the design drawings.
2. Collect all design changes.
3. Modify the original design drawings according to the design changes.
4. focus ~! Must indicate the unconstructed part ~! ! For example, the post-pouring zone of the factory, or the part that is planned to postpone construction. This is very important, otherwise there will be jokes.
(This is the corresponding sentence "Draw what has been done", and the parts that have not been done must be clearly marked)
Don't change anything else, because in theory, it is constructed according to the drawings, and what you made is what you originally painted, so there should be no difference.
4. Water and electricity drawing is a matter of water and electricity specialty, and you can't do it unless your leader is 290.
5. Check the drawings carefully. The actual drawing won't take long. The key is to be careful.
Wish you success ~!
Theoretically, as-built drawings should be drawn at the time of completion. In practice, the owner's handover requirements are met, that is, when the completion acceptance is ready, the as-built drawing must be drawn-the as-built drawing is a project of the completion acceptance.
In addition, as-built drawings and construction drawings are divided into construction, construction and water application.
- Previous article:Joke science
- Next article:I haven't cared about basketball for a long time. I want to ask you what's going on now.
- Related articles
- Diary of Mid-Autumn Festival
- Football jingle
- My classmate "The King of Jokes" _ A 200-word composition by a second-grade writer.
- Children’s poems describing the four seasons
- A sharp joke
- Why is Zhou Xun included in the credits of "Charlotte Troubles"?
- The Russian-Ukrainian war played a joke.
- The Cultural Characteristics of Russia and Its Causes
- I dreamed that there were many little red dot on my head.
- Zen Master Yicheng: Heart disease is the root of all problems.