Small and high-rise project engineering coordination meeting system?

What are the coordination systems for small and high-rise projects?

1) the purpose and task of the project coordination meeting: to ensure the smooth progress of construction production, further refine the weekly plan, implement the tasks to people and check in place.

2) Participants: engineering, technology and materials departments, team leaders of construction teams (subcontractors), technicians and safety officers.

3) Meeting time: 3 pm every day.

4) Participants should prepare the following contents:

(1) Simple report on the completion of tasks within the scope of responsibilities (whether or not completed, how, not completed, why? How to remedy it?

(2) Simple report on the work arrangement the next day, especially to solve problems with other departments (specialties) or project management departments.

(3) Half an hour ago, the relevant personnel checked the task completion of the day, and after the meeting, it was carried out in time according to the spirit of the meeting.

5) Meeting discipline:

(1) held on time every day, no further notice;

(2) If you don't attend the meeting, you should ask for leave in time to ensure that your work will not be affected.

For more information about project/service/procurement bidding, and to improve the winning rate, please click on the bottom of official website Customer Service for free consultation:/#/? source=bdzd