Classic emergency plan for typhoon season safety prevention
Classic emergency plan for safety prevention in typhoon season (5 general articles)
In study, work or life, it is inevitable that some unexpected events will occur. In order to control the development of accidents, it is usually necessary to prepare an emergency plan in advance. How should we write an emergency plan? The following is a classic emergency plan (5 articles in general) for typhoon season safety prevention compiled by me for your reference only. Welcome to read it.
classic emergency plan for safety prevention in typhoon season 1
in order to do a good job in typhoon prevention in our construction site, reduce disaster losses and ensure personal and property safety, according to the Law of the People's Republic of China on Work Safety and the spirit of relevant documents of the District Construction Bureau, combined with the actual situation of our company, the emergency response plan of this project department is formulated.
first, the basic principles of emergency treatment
(a) this plan is the basic procedures and organizational principles of emergency treatment when my construction site is attacked or affected by a typhoon.
(2) The principle of unified command, individual responsibility, prevention first, saving lives first, quick response and ensuring safety shall be followed in the implementation of emergency treatment.
II. Organizational structure and supervisor's responsibilities
The project department sets up a leading group for typhoon prevention in construction sites
Team leader: Zhu Jiahua, project manager
Deputy team leader: Dai Jinquan, deputy manager of the project department; Zhou Fengping, technical director
Members: Zhang Hua, safety office of the project department, Cai Baobin, builder Zhang Jianhu and other relevant personnel.
main responsibilities:
(1) to be responsible for the formulation and revision of the typhoon emergency response plan for construction projects;
(2) Before the typhoon comes, be responsible for notifying the construction site to do a good job in typhoon prevention, checking the reinforcement of safety facilities on the construction site, and evacuating and transferring workers;
(3) Arrange personnel to be on duty, inspect the construction site, immediately organize rescue and after-treatment work, keep close contact with the higher authorities, and report the emergency treatment at the accident site at any time;
(4) after the typhoon, be responsible for convening relevant personnel to summarize the emergency handling of the accident.
III. Implementation of the plan
(1) Upon receiving the news released by the Meteorological Observatory, it is expected that it may be affected by the typhoon:
1. The project management department of the construction site issued a typhoon prevention notice, and the relevant personnel of the project department paid attention to the meteorological news and paid close attention to the typhoon trend;
2. The project manager department is responsible for notifying the relevant personnel and teams at the site, requiring all personnel to cooperate closely and make all preparations for typhoon prevention.
(2) When the typhoon is approaching our city and will affect our region within 48 hours, when the Meteorological Observatory issues a typhoon warning:
1. The project department should arrange the construction reasonably and stop the working procedures that need continuous construction;
2. The project department should cooperate with the branch company to carry out safety inspection before the typhoon, including whether the construction elevator is firm, whether the scaffolding and other facilities are firm, whether the temporary work shed is safe, etc., and take measures to reinforce and eliminate potential safety hazards.
(3) When a typhoon may attack our area within 24 hours and the Meteorological Observatory issues an emergency warning:
1. The typhoon prevention leading group of the project department is in place and arranged to be on duty;
2. The construction site stops, and the construction personnel are evacuated to safety;
3. The project manager department will organize personnel to inspect the construction site, cooperate with the company's leading group to further check the implementation of various defensive measures, and ensure that the construction site rescue team is in place and is in a state of war;
4. during the typhoon, when there is a safety accident with casualties on the construction site, it shall be implemented according to the company's Emergency Rescue Plan for Major Safety Accidents in Construction Projects.
after the typhoon, when the typhoon warning is released by the meteorological station, the project department should check the damage and report it to the branch company and the head office, reinforce the safety facilities on the site in time, and summarize the typhoon prevention work. Classic emergency plan for safety prevention in typhoon season 2
1. Purpose:
To establish emergency plan for flood control and typhoon prevention, strengthen the ability of flood control and emergency rescue in the management service area through the training and practical training of emergency teams, eliminate dangerous situations more effectively and timely, reduce losses to a minimum, and ensure that flood control and typhoon prevention are foolproof.
2. Responsibilities:
The director of the management office is the chief commander of flood prevention and typhoon rescue;
the management office is headed by the deputy commander-in-chief, who is responsible for the overall work of the equipment group;
the safety sponsor is the deputy commander-in-chief, responsible for the overall work of the rescue team;
the environmental organizer is the deputy commander-in-chief, responsible for the overall work of the logistics team;
the control center is responsible for the accurate transmission and coordination of information;
all off-duty personnel in the management office are emergency rescue team members for flood control and typhoon prevention.
III. Division of responsibilities of the team:
3.1 Emergency rescue team: composed of all safety officers who are in charge of safety and those who are not on duty
3.1.1 Take all measures to deal with dangerous situations;
3.1.2 Be responsible for filling, transporting and stacking sandbags for flood control;
3.1.3 use various ways and methods to eliminate dangerous situations in time.
3.1.4 Division of labor
Two off-duty central posts in 3.1.4.1 are responsible for loading sandbags;
two off-duty posts No.2, No.3 and No.4 in 3.1.4.2 are responsible for transporting sandbags;
3.1.4.3's two off-duty No.6 and No.8 are responsible for piling sandbags on site and taking other measures for emergency rescue;
3.1.4.4 Safety Sponsor led the rescue team to take all other effective methods to do all kinds of rescue work.
3.2 equipment group: composed of the manager of the management office and two technicians of the management office
3.2.1 is responsible for starting all kinds of water pumps and power supply equipment;
3.2.2 provide technical guidance to the rescue site;
3.2.3 emergency maintenance of field equipment.
3.3 logistics group: composed of environmental sponsors, domestic servants, lifeguards, front desk attendants, cashiers and club attendants
3.3.1 to ensure the normal supply of all kinds of relief materials;
3.3.2 Be responsible for the rescue of the wounded on site;
3.3.3 Actively assist other groups;
3.3.4 Division of labor
Two off-duty No.5 posts in 3.3.4.1 are responsible for logistics and material support;
The front desk attendants, cashiers and club attendants in 3.3.4.2 are responsible for evacuating people and rescuing the wounded, moving the wounded to a safe place and reporting to the municipal emergency center in time;
Lifeguards and domestic helpers in 3.3.4.3 are responsible for property rescue.
3.4 personnel on duty
4.1.1 The personnel on duty shall notify the center and the shift leader in time after finding the danger;
4.1.2 After receiving the information, the center attendant takes measures such as emergency gathering to call off off-duty personnel to discharge the danger in time;
4.1.3 The attendant of the center shall inform the management office manager, management office supervisor and safety sponsor at the first time;
4.1.4 The attendant in the center shall report the situation to each post on duty;
4.1.5 On-site posts should maintain order and guide personnel and vehicles;
4.1.6 the attendant in the center should pay close attention to the site situation and seek other support when necessary.
4.1.7 before the typhoon comes, all posts in the management office should carefully check the potential safety hazards within the post scope, and eliminate the danger in time, and report to the superior in time if the situation is serious.
Note: All members must obey orders and commands; All members should pay attention to their own safety during emergency rescue. Classic emergency plan for typhoon season safety prevention 3
1. Guiding ideology:
Typhoon and rainstorm prevention is an important work related to the life safety of teachers and students and the safety of national property. In order to effectively protect the safety of teachers and students and property, and improve the handling capacity of kindergarten flood prevention and typhoon prevention, this plan is formulated in line with the principle of "prevention first, safety first".
2. Precautionary steps:
1. List of leading groups and contact telephone numbers
Team leader: director
Team members: logistics team leader
education director
trade union chairman
Kindergarten starts typhoon prevention and flood prevention plan, and implements the system of 24-hour leadership leading shift and 24-hour duty.
3. Emergency measures:
1. Strengthen information communication, so that the information can be released and the information can be reported.
when a major flood occurs, all the leaders are in their posts and the leading group for flood control and typhoon prevention begins to operate; The leaders in charge shall report the flood to the leading group for flood control and typhoon prevention; Fully deploy anti-Taiwan flood control work.
2. Give priority to prevention:
Clear corridors. Before the typhoon landed, the sundries and flowerpots on the balcony and corridor should be cleaned to prevent people from being blown off by the wind when the typhoon landed.
close the doors and windows. When typhoon and rainstorm come, the wind and rainfall are heavy, so doors and windows should be closed to prevent the wind and rain from damaging doors and windows, furniture and causing casualties.
The janitor has fully dredged the sewers and main collecting wells in the school.
Dredge the gutters and downpipes on the buildings of the school, and trim and strengthen the trees of the school.
conduct a comprehensive safety inspection of the lightning protection facilities and outdoor wires in the buildings of the whole school.
conduct a comprehensive safety inspection of outdoor antenna, outdoor unit of air conditioner and external suspension.
conduct a comprehensive inspection of indoor power supplies, sockets, doors and windows of all departments.
If the circuit and wires are interrupted due to typhoon, turn off the power switch in time and turn on the emergency lights, flashlights or candles for lighting.
IV. Safeguard measures:
After the plan is started, kindergartens should make early warning and record information. Hold an emergency meeting, in the shortest possible time, deploy the work of flood control and typhoon prevention in kindergartens by telephone, inform the dynamics of typhoon flood, and arrange the requirements and tasks of flood control and typhoon prevention, emergency rescue and disaster relief.
keep close contact with the higher authorities and units at any time, strengthen information communication, and ensure that the upper information is issued and the lower information is reported. Classic Emergency Plan for Safety Prevention in Typhoon Season 4
In order to do a good job in typhoon prevention, the Emergency Plan for Typhoon Prevention in Hotel is revised and issued, and all hotels are requested to follow it.
I. Organization and responsibilities
The hotel has set up a emergency headquarters for flood control and typhoon prevention. When the typhoon comes, all members of the headquarters must immediately do a good job in flood control and typhoon prevention and on duty in the hotel. The organization is as follows:
Chief Commander: Executive General Manager of the hotel
Deputy Chief Commander: General Assistant in charge of safety work of the hotel
Member units: Housekeeping Department, Catering Department, Front Office Department, Engineering Department, Security Department and Finance Department
II. Typhoon Procedures
(1) Self-inspection preparation before typhoon
1. Front Office Department: Collection Gate. Put a typhoon information bulletin board in the lobby or elevator entrance, and prepare a typhoon reminder card and hand it to the housekeeping department for allocation into the room; Prepare umbrellas and rain gear. Every employee in the front office should know the typhoon information, answer the guests' inquiries in time, and prepare the emergency lighting at the front desk. The assistant lobby should set up a post in the lobby, do a good job of customer inquiries and pay attention to the situation at the door and lobby and report it in time to ensure the normal business order in the front office.
2. Housekeeping Department, Catering Department and Finance Department: Check and close the doors and windows of all rooms, boxes, walkways and corridors; Do a good job of typhoon prevention for guests and inform the housekeeping department that typhoon warning cards should be allocated to the room; Prepare emergency lighting;
3. Operator: responsible for understanding the typhoon situation and reporting it to the hotel leaders and relevant department heads in time; Prepare emergency lighting and walkie-talkies, and check whether the backup power supply of the switchboard is working normally, and provide emergency service for power failure under the guidance of the department manager, and do a good job in guest inquiry service.
4. Each department should prepare the reported loss linen one day in advance for emergency use.
5. The engineering department will conduct a comprehensive inspection of the hotel periphery, platforms, neon lights, billboards, satellite receivers, doors and windows of various business departments and tenants, reinforce them with iron wires, ropes, wooden stakes, etc., and temporarily dismantle the unstable hanging objects. Check the important parts such as the computer room of the underground electricity room, reinforce the hotel door, and cut off the circuit that may cause fire due to short circuit. The pool should be filled with water to ensure the normal supply of water, electricity and gas in the hotel, and prepare enough sandbags.
6. The head office is responsible for conveying typhoon information to all employees of all departments and arranging the heads of all departments to stay in the store for duty.
7. The security department informs the dormitory security guards to be diligent, and cooperates with the engineering department to check whether the sewers and gutters in key parts such as the periphery and roof of the hotel are unobstructed, and prepare lighting appliances, rain boots and raincoats, helmets, flashlights and emergency lights.
(2) Re-inspection: The heads of the General Office, the Engineering Department and the Security Department will re-inspect the preparations of all departments according to the above provisions.
(3) When the wind is strong, emergency procedures should be started:
1. The heads of the security department and the engineering department should stay at the hotel at any time to deal with sudden dangers and ensure sufficient manpower and material resources to do emergency repair and remedial work.
2. If there is water seepage in the guest room, box, linen, drinks and food warehouse, the subordinate department shall immediately move the contents of the room to a safe place, and the engineering department shall do a good job in plugging and drainage.
3. The rainwater at the front door may flow backward into the lobby, and the security department and the engineering department will pile sandbags at the door to prevent the inflow. PA class is responsible for sending additional personnel to clear the accumulated water.
4. Rain from the back door may flow backward into the employee elevator. The security department and the engineering department will pile sandbags at the back door to prevent the inflow. The security guard at the back door post is responsible for removing the accumulated water. If the rain has flowed backward into the elevator, the engineering department should immediately control the elevator to the floor above 1F, and it is forbidden to let the elevator run to-1f-2f.
5. When the wind is very strong, the front door and the back door should be reinforced with wooden plugs and boards to prevent the glass doors from being destroyed by the wind. During the reinforcement, some glass doors should be properly left open to reduce the resistance of the wind to the glass doors, and the front door glass should be taken care of by the bellboy and the foreman of the security department. The back door glass is taken care of by the security guard at the back door post.
6. When the wind is very strong, the porter of the security guard at the gate post should pay attention to falling objects and guide the guests' vehicles to park in the underground garage. If necessary, they should wear safety helmets. The front office department should put away the desk lamps and flower pots placed on the countertop to avoid being blown down.
7. If there is water in the elevator, the engineering department should immediately start the drainage system to remove the accumulated water. In order to avoid the passenger elevator from running due to strong wind, the dining room screen should be pushed to the elevator entrance for shielding.
8. in case of power failure, the engineering department immediately contacts the property office to generate electricity and restore lighting. The security department maintains the hotel security order in case of power failure. In case of power failure, the restaurant manager is responsible for taking care of the cashier in place, and the cashier at the main desk is taken care of by Qianmen Gang and 2 or 1 of the security department. The assistant manager of the lobby, 1 and 2 should provide elevator service, inquire whether there are any guests who have been shut down, and do a good job of comforting the guests who have been shut down. Floor workers and management personnel of various departments should be dispersed to various floors and restaurants to explain and appease the guests.
9. When the gutter is blocked, the Engineering Department and the Security Department * * * will send people to dredge it. The dredging personnel should pay attention to their own safety. They must wear safety helmets and wear safety ropes when necessary, and they will be connected by two people in tandem.
- Related articles
- Caring for newborn hygiene and cleaning essentials for various parts of the body
- The name of the fairy tale studio is the name of the fairy tale studio.
- Greetings, surprises, happiness and concern for the health of friends.
- The story of Kaixian county public village
- "What are the characteristics and advantages of Huizhou lawn guardrails?
- The interesting poisonous chicken soup that has become very popular in the circle of friends recently
- The safety inspection results of a certain project are as follows: 1. Safety management: the guaranteed project scored 44 points, and the general project scored 34 points; 2. Civilized construction: t