Joke Collection Website - Bulletin headlines - Discussion on ultra-fine standardized construction template?
Discussion on ultra-fine standardized construction template?
1. 1 road hardening thickness: subgrade is smooth, road formwork is straight and firm, and molding quality is guaranteed. Pouring thickness is 15~20cm, vibrating compaction, leveling and lighting.
1.2 ground treatment of processing plant: level the site, with concrete pouring thickness of 5cm. Some yards can be paved with gravel directly.
Road hardening realistic template
Second, the steel processing zone
2. 1. paddock
Erection materials: steel pipe, wood square, small plywood and nails.
Height: 900 mm
Color: 150mm blue paint band from top to bottom, with white paint in the middle.
Real template:
2.2. Processing room
Erection size: 12m×8m×4m(8m×6m×4m) can be erected according to site conditions, and the periphery 1.5m is cantilevered.
Eyebrow height: 600mm, stitched with Xiao Jiu splint.
Rod spacing: 2m (double vertical rods are arranged side by side in the middle, and three vertical rods are arranged at each big corner).
Waterproof practice of the top floor: double-layer protection of the top floor is made into an inclined plane, covered with bamboo picks and covered with colored steel tiles.
Advertising and color: advertising slogans (slogans with white words and yellow edges on a red background) are pasted on the eyebrows, and the vertical bars and horizontal bars are painted in yellow, and the diagonal bars are painted in blue.
Installation of distribution box: distribution box and switch box are centrally arranged at the same elevation and height.
Real template:
Real model of reinforced building
2.3. Raw materials are stacked in frames and areas.
Size: Frame piles are welded by 16 channel steel, with a height of 800mm and a spacing of1000 mm. 。
Color: 400 mm yellow-blue paint is painted on the pile.
Real template:
2.4. Identification mark
Third, the mixing station
3. 1. Erection materials: steel pipe, wood square, bamboo fiber board, color steel tile and bamboo cantilever board.
3.2. Installation dimension: 6m×4m×4m high, single installation.
3.3. Metering platform: pit depth 1.4m×0.9m×0.2m, platform cover size1.35m× 0.85m× 0.15m ... The pit shall be cleaned in each shift.
3.4. Color beautification: the top elevation of the mixing room is painted with 500mm high blue ribbon, and the bottom elevation is painted with 150mm wide blue-yellow twill with an angle of 60. Import and export perimeter 150mm wide, brush 100mm blue and yellow twill.
3.5. Identification plate: The operating instructions and acceptance plate are hung at the inlet, and the "Metering Table" and "XX Mixing Table" are sprayed.
3.6. Real model:
Fourth, safe passage.
4. 1. Lane:
A. Dimensions: the clear height is 5m, the clear width is 5.5m, and steel pipes are erected with 500mm×500mm steel pipe columns with a spacing of 3m.
B, color: vertical bar and cross bar are painted yellow, diagonal bar is painted blue. Eyebrow height 1m, yellow and blue twill.
C notice board: above the entrance, the words "safe passage" and the acceptance sign shall be affixed.
4.2. Pedestrian access:
A. Dimensions: 3.5m in height, 2.4m in clear width and 6m in length (it can also be determined according to the actual situation on site). Cantilevers on both sides are 200mm. Eyebrows are 600mm high. The vertical pole spacing is 1.5m, and the height of the sweeping pole from the ground is 0.5m (nail the skirting board with a height of 0.5m, brush the yellow-blue twill on the inside and blue on the outside). A horizontal pole with a height of 1.8m is arranged above the sweeping pole. Hang a dense mesh safety net.
B, color: vertical bar and cross bar are painted yellow, diagonal bar is painted blue. Eyebrow height 1m, yellow and blue twill.
C. Signs and signs: The "safe passage" is attached to the top of the entrance, and the acceptance card, foot and foot scheme card and building number identification card are hung.
4.3. Construction elevator ground protection passage: 4m high, 6m wide and 6m long (but the length and width can be adjusted according to the actual situation on site).
4.4. Real examples:
Real model of safe passage and cement warehouse (tool room)
5. 1. Erection materials: steel pipe, wood square, bamboo fiber board, color steel tile and bamboo cantilever board.
5.2. Installation dimensions: 8m×4m, elevation height 3.5m, back elevation height 3m, and doorway: 1.5m×2m.
5.3. Roof and floor practice: single slope roof. A. Outside the radius of falling objects at high altitude, the color steel tile can be directly covered, hanging eaves 150mm, and the color steel tile extends out of the eaves by 50 mm; B. Within the radius of falling objects, cover colored steel tiles first, and then spread bamboo protection, with an eyebrow height of 300 mm.
5.4. Color: 300mm high blue paint for eyebrows and skirting lines, and blue paint for door frames 120mm wide. The rest is painted white.
5.5. Tool house construction: The material, color (door painted yellow) and roof are the same as those of cement house. The erection size shall be determined according to the site conditions.
5.6. Real examples
Six, power distribution facilities
6. 1. Protection of main power supply lines: A. Buried cables (buried depth not less than 600mm) shall be hard protected along the surface of the wire laying direction, and warning signs shall be set along the way. B, Ming cable directly using wood square and 200mm wide nine plywood nail box protection.
6.2. Outdoor first-class distribution box protective shed: A 1.5m high steel fence can be directly set and locked outside the coverage of tower crane. Set up a double-layer protective shed within the coverage of the crane, which is fully enclosed and locked.
6.2. 1. Erection height and size: fence height 1.8m, protective shed height 2.5m, circumference 300mm wide. The bottom of the protective shed is paved with wood squares, and then nine splints are nailed. Length, width and size shall be determined according to site conditions.
6.2.2. Color: the eyebrow is 300mm wide, and all parts are painted with yellow and blue paint.
6.2.3. Safety signs: operating procedures, beware of electric shock and pay attention to safety. Set fire extinguishers.
6.2.4. Installation and identification of distribution boxes at all levels: The first-level distribution box is equipped with an installation platform with a height of 200mm, and the operation part is equipped with an insulating platform with a height of 100mm and a width of 500mm. The installation height of movable secondary distribution box is 600mm, and the installation height of fixed secondary distribution box and switch box is1.3m.
Logo in the box: the control switch is marked with the line direction, and the "Wiring System Diagram" and "Daily Inspection Record Form" are posted on the door of the box.
6.2.5. Installation of cables in operation area: During foundation construction, all power lines are temporarily overhead in different parts, and decorative floor lines are overhead along the wall.
6.3. Real model:
Real model of distribution box
Seven, crane foundation
7. 1. Perimeter enclosure and color: the perimeter of the foundation is closed with wooden squares and nine plywood, and the height is1m. Paint the upper and lower parts with blue paint, with the width of 150mm, and paint the rest with white paint.
7.2. Handling of anchor screws: butter and cover with plastic bottles for protection.
7.3. Identification cards: operating rules, ten don't hang, and acceptance cards.
7.4. Real model:
8. Site partition and material stacking 8. 1. Division of processing sites for each team:
8.2. Material stacking principle: centralized stacking according to varieties and specifications. A face, a line and a head. There are partition columns and signs.
8.3. Materials used in the decoration stage: foam bricks or hollow bricks (concentrated as far as possible) shall be used for masonry, with a height of 900mm, and the length and width shall be determined according to the site.
8.4. Blocking and separating small pieces of material: make a block frame with small pieces of steel pipe, wood square and nine plywood, with the height of 1m and the length and width determined according to the site (the inside is not painted).
For more information about project/service/procurement bidding, and to improve the winning rate, please click on the bottom of official website Customer Service for free consultation:/#/? source=bdzd
- Previous article:A Summary of Chinese Teaching, Teaching and Scientific Research
- Next article:Why does milk tea turn sour?
- Related articles
- A rabbit sleeps under a tree and writes four sentences in English.
- Introduction of Beidahuang Group in Beidahuang Grain Electronic Trading Market
- How to send a friend to the rescue car in the middle of the night?
- The third season of Chinese Restaurant ended perfectly. What are the hardcore changes compared with the previous two seasons?
- The latest txt complete works of eschatological evolution and invasion
- How to say rainbow in English?
- Can the concrete mixing station use bagged cement?
- World Environment Day environmental protection slogans
- 10.8 summary of national hypertension day activities
- Types of POP advertisements _ What are the five types of pop advertisements?