Road construction traffic control plan

1. Project Overview:

The Suining-Ziyang section of the Sui-Zi-Mei Expressway starts from the west side of Suining City, and is connected to the existing Sui-Chongqing Expressway by a Xining hub interchange. It passes through Anju District of Suining City, Lezhi and Yanjiang Districts of Ziyang City, and connects with the proposed Suizimei Expressway at Laopeng Bay on the border of Ziyang. There are 11 interchanges across the entire line in Xining, Meishan, Baima, Baoshi, Sanxing, Lezhibei, Tongjia, Zhongtian, Zhonghe, Baotai, Yingying and other places. The entire line is constructed according to two-way four-lane highway standards, with a design speed of 80 kilometers per hour and a road bed width of 24.5 meters.

The starting point of the Ziyang section of the Suizhi-Mei Expressway is K41+800, and the ending point is K124+026.825. The total length is 82.174647km, including Sanxing, Lezhibei, Tongjia, Zhongtian, Zhonghe, Baotai, Yingying 7 interchanges, Lezhibei service area, Longtanhe parking area, and Ziyang service area.

The pavement project of the LM2 contract section of Suizi Road, undertaken by our project department, will soon begin large-area road asphalt construction. As the water stabilization construction progresses, roads are formed and traffic conditions improve, the number of vehicles traveling within the construction red line will increase and the driving speed will become faster and faster. At the same time, some local social vehicles and local villagers along the construction line will also enter the construction red line. Driving or staying inside will seriously interfere with and affect the road construction along the line, and pose major traffic safety hazards. Mainly manifested in:

As the road traffic conditions in the red line area are getting better and better, construction units such as roadbeds and bridges are undergoing the final intensive construction, and the construction access roads have not yet been closed. The construction red lines and access roads along the way are There are many intersections, and some local villagers and motor vehicles (including motorcycles and agricultural tractors) will enter the construction red line area through the construction access road, which poses serious traffic safety hazards and brings difficulties to the normal construction and safety management of our department. Great impact.

In order to create a safe environment and ensure safe construction, this plan is specially formulated with reference to the relevant documents of Sichuan Province and the owner

.

2. Traffic Control Plan

1. Organizational Structure

(1) Project Department Traffic Control Safety Leading Group

Leader: Chen Degang

Team members: Wang Yi, Ye Lin, Yin Yun, Chen Shuai, Liu Bin, Wang Wei

Duty phone: 0286741816

(2) Safety The leading group is responsible for the implementation and arrangement of the traffic control plan for the project's road construction.

2. Specific contents of the plan

(1) Set up obvious traffic safety warning signs and signboards at the entrances and exits of our construction site;

(2 ), set up a duty room at the entrance where our vehicles must pass through in the construction section, and assign dedicated personnel to be on duty 24 hours a day;

(3) Strengthen inspections of the entire construction line;

( 4). Conduct a comprehensive safety status and vehicle technical condition inspection of our department’s construction vehicles;

(5) Strengthen safety education for transportation vehicle drivers of our department’s cooperating units;

< p> (6). Send a written report to the local government along the construction line, requesting assistance in providing safety education to local villagers, prohibiting public vehicles and local pedestrians from entering the construction red line, and issuing leaflets to the people along the line to vigorously promote Suizi Road Expressway The highway is closed for construction, and non-construction vehicles and pedestrians are prohibited from entering the construction red line to ensure the safe progress of our construction; we have strengthened contact with the local traffic police department and requested help.

(7) In order to eliminate interference from local villagers who block work and ensure the smooth progress of the road construction on the LM2 section of Suizi Road, our ministry will set up a road protection team to patrol 24 hours a day to promptly dissuade and prohibit those who block work. occurs to ensure the smooth progress of construction.