Aolin Toy Factory arranges Workshop A and Workshop B to process 1000 Olympic mascots of the same model respectively, and each worker processes the same number of mascots every day.

( 1)A;

(2) Analytical formula of straight line OB: y=50x.

A (2 2,0), c( 18960), let the analytical formula of straight line AC be: y=kx+b, then 0 = 2k+b960 =18k+b.

Solution: k=60, b=- 120.

Analytical formula of linear AC: y=60x- 120.

Meanwhile: y = 50xy = 60x? 120,

Solution: x = 12y = 600.

A: After processing 12 days in Workshop A, the number of mascots processed in both workshops is the same.

(3) Let the resolution function of BC be y=kx+b, b (20,1000) c (18,960).

20k+b = 1000 18k+b = 960,

Solution: k = 20b = 600.

∴y=20x+600, when y= 1000, x = 20.

20-2= 18 (days).

Therefore, it takes 18 days for Workshop B and Workshop A to complete production tasks at the same time.