Joke Collection Website - News headlines - Design plan for PVC floor construction
Design plan for PVC floor construction
1. Basis for preparation
1. Construction drawings provided by Party A;
2. Actual conditions at the construction site;
3. Ground engineering construction quality acceptance specifications (GB50209-2002);
4. Construction site boundary noise limits (GB12523-90);
5. Party A’s bidding documents and related technologies Require.
2. Preparation work before construction
1. According to the requirements of the ground construction quality acceptance specification (GB50209-2002), the floor surface should be smooth, hard, dry, dense, clean, There should be no grease and other impurities, and there should be no defects such as pitting, sanding, cracks, etc. The flatness should be 2M and the error should not exceed 2MM. According to the above requirements, Party A is requested to supervise the inspection and acceptance. After passing the inspection, follow-up construction will be carried out.
2. The decoration of the PVC plastic floor laying area and adjacent areas is basically completed. The floor must be dry, solid, and free of debris. The decoration personnel have basically left the site, and there are no idle personnel. No other personnel are allowed to cross during our construction.
3. According to the construction requirements of PVC plastic flooring, Party A should provide necessary support, seal the construction area, provide lighting for the construction area, and provide water and power supply for the construction area.
4. Floor inspection:
1) Use a temperature and humidity meter to detect the temperature and humidity. The indoor temperature and surface temperature should be 15°C, and should not be below 5°C or 30°C. above construction. The relative air humidity suitable for construction should be between 20% and 75%;
2) Use a moisture content tester to detect the moisture content of the base layer. The moisture content of the base layer should be less than 4.5%;
3) The strength of the base layer should not be lower than the requirement of concrete strength C-20, otherwise suitable self-leveling should be used to enhance the strength;
4) The test result of the base layer should be using a hardness tester. The surface hardness is not less than 1.2 MPa;
5) For the construction of rubber flooring, the unevenness of the base layer should be less than 2 mm within a 2-meter ruler. Otherwise, use a suitable self-leveling Perform leveling.
5. Party A must provide a safe and effective material storage warehouse and construction tools and equipment storage area that is protected from rain, moisture, and direct sunlight.
3. Material procurement and supply guarantee
1. Materials
Our company has tens of thousands of square meters in stock all year round. If you select non-stock products, we will Delivery time is 30-45 days.
2. On-site unloading management
Our company will arrange very sufficient labor and equipment at the construction site in advance. Once the goods arrive, they will be handled as quickly as possible under on-site supervision. The cargo is unloaded. At the same time, in order to avoid the influence of natural factors such as rain, prepare rain-proof items to ensure that the quality of the items is not affected.
3. Owners
During the entire process, our company will report relevant information to the owners in a timely manner, communicate and coordinate with the owners, supervisors, and general contractors, and listen carefully. , Earnestly fulfill the requirements or suggestions put forward by the owner, and complete the related work of this project as quickly as possible and with the best quality.
IV. Construction process
1. Construction sequence
Treat the base layer - apply primer - make self-leveling cement floor - maintenance 24 - 48 hours - divided elastic line - trial laying of floor - scraping glue - laying floor - exhaust and compaction - cleaning and maintenance - finished product protection.
2. Construction method
1) Floor pretreatment:
① Floor requirements: clean, dry, no grease, no sand, cracks, etc. Phenomenon, the surface finish is not rough to the touch;
② Use a floor grinder with a power of more than 1000 watts and appropriate grinding discs to polish the floor as a whole to remove paint, glue and other residues, bumps and Loose plots and plots with hollows must also be removed;
③ Use an industrial vacuum cleaner of no less than 2000 watts to vacuum and clean the floor;
④ For the floor Cracks on the floor can be repaired by using stainless steel reinforcing bars and polyurethane waterproof adhesive to spread quartz sand on the surface;
⑤ Basements or relatively humid floors must be equipped with appropriate waterproofing treatments during civil construction. Before paving, check whether the floor is completely dry.
2) Self-leveling construction:
① Primer:
a. Absorbent base layers such as concrete and cement mortar should be leveled first with multi-purpose Dilute the interface treatment agent with water at a ratio of 1:1 and then perform sealing and priming;
b. For non-absorbent base layers such as ceramic tiles, terrazzo, marble, etc., it is recommended to use a dense interface treatment agent for priming; < /p>
c. If the moisture content of the base layer is too high (>3%) and construction needs to be carried out immediately, an epoxy interface treatment agent can be used for primer treatment, but the premise is that the moisture content of the base layer should not be greater than 8%;
p>d. The interface treatment agent should be applied evenly without obvious liquid accumulation. After the surface of the interface treatment agent is dry, the next step of self-leveling construction can be carried out.
② Stirring:
a. Pour a bag of self-leveling into a mixing bucket filled with clean water according to the specified water-cement ratio, and stir while pouring;
b. In order to ensure uniform self-leveling, a high-power, low-speed electric drill with a special mixer must be used for stirring;
c. Stir until a uniform slurry without agglomerates, and let it stand for maturation. About 3 minutes, stir briefly again;
e. The amount of water added should strictly follow the water-cement ratio. Too little water will affect fluidity, while too much water will reduce the strength after curing.
③ Laying:
a. Pour the mixed self-leveling slurry onto the construction floor. It will flow by itself and level the ground. If the design thickness is ≤ 4 mm, Then you need to use a special tooth scraper to scrape a little;
b. Then the construction workers should put on special spike shoes, enter the construction ground, and use a special self-leveling deflation roller to gently apply the pressure on the self-leveling surface. Roll gently to release the air mixed in the mixing to avoid bubbles, pockmarks and interface height differences;
c. Please close the site immediately after the construction is completed. Walking is prohibited within 5 hours and avoid heavy objects impact within 10 hours. , the floor glue can be laid after 24 hours;
d. For winter construction, the floor laying should be carried out 48 hours after the self-flow construction;
④ Ground grinding:
After the self-leveling is fully dry, grind, polish and clean the self-leveling floor.
5) PVC plastic floor construction
① Pre-laying and cutting:
a. Whether it is roll material or block material, it should be placed on site for 24 hours For more than 1 hour, use material memory restoration, and the temperature should be consistent with the construction site;
b. Use a special trimmer to cut and clean the burrs of the coiled material;
c. Coiled material When laying, the overlap between two pieces of material should be cut with overlap, generally requiring an overlap of 2 cm. Pay attention to cutting with a single knife;
d. When laying blocks, the two pieces of material should be close to each other and there should be no seams.
② Pasting:
a. Select the corresponding glue and squeegee according to the floor with different properties;
b. When laying the roll material, put the roll Fold one end of the material. Clean the floor and the back of the roll first, then scrape the glue on the floor;
c. When paving the blocks, turn the blocks up from the middle to both sides, and clean the ground and the back of the floor as well. Then apply glue and stick;
d. Different adhesives will have different requirements during construction. Please refer to the corresponding product instructions for construction.
③ Exhaust and rolling:
a. After the floor is pasted, first use a cork block to push the floor surface to flatten and squeeze out the air;
b , then use a 50 or 75 kg steel pressure roller to roll the floor evenly and promptly repair the warping of the joints;
c. Excessive glue on the floor surface should be wiped off in time;
< p>d. After 24 hours, perform grooving and welding.④ Grooving:
a. Grooving must be done after the glue is completely solidified. Use a special slotter to slot along the joints. In order to make the welding firm, the slots should not be through the bottom. It is recommended that the slotting depth is 2/3 of the floor thickness;
b. Use the slotter For the end parts that cannot be opened, please use a manual seam opener to open seams with the same depth and width;
c. Before welding, the dust and debris remaining in the groove must be removed.
⑤ Welding:
a. You can use a manual welding gun or automatic welding equipment for welding;
b. The temperature of the welding gun should be set at 350~400 About the degree;
c. Use an appropriate welding speed (to ensure the melting of the welding rod), and squeeze the welding rod into the opened groove at a uniform speed;
d. When the welding rod is semi-cooled , use a welding rod trimmer or a moon-shaped cutter to cut off the remaining convex part of the welding rod, usually scraping twice, so that the joints between PVC flooring materials will be more completely smooth.
⑥ Construction of PVC plastic flooring for stairs
a. According to the plan provided by Party A, the design requires self-leveling construction of the tread platform of the stairs.
b. Self-leveling, polishing and cleaning.
c. Make PVC plastic floor laying lines according to the size of the stairs.
d. Use special PVC plastic floor glue to scrape and pave the stair steps.
e. When paving, use a rubber hammer to tap the entire surface.
⑦ Protection of finished products: Clean and clean the site 24-48 hours after the completion of construction. Please accept the inspection by the supervisor and Party A and then deliver the finished products to Party A for protection.
V. Overall layout and management of the construction site
1. Set up a cordon in the opening area and have dedicated personnel to guard it to prevent idlers from entering and exiting.
2. Construction workers shall wear uniform work ID cards. Those without ID cards will be prevented from entering.
3. Equip fire-fighting equipment at the construction site and warehouse, and provide fire-fighting training to all construction workers.
4. Water and electricity used for construction shall be provided by Party A. It is required that the power supply, distribution box and other facilities in the construction area are complete, and the temporary arrangement of water and electricity must comply with the requirements of safety production technical regulations.
5. The on-site material stacking and self-leveling mixing areas shall be divided by the construction personnel according to reasonable and safe principles.
6. Project management and coordination
1. Construction site quality management and technical support
1) Strictly follow the construction conditions and technical specifications of PVC plastic flooring Quality management, pursuing the principle of quality first.
2) Establish a three-level technical quality supervision and management mechanism to ensure construction quality:
① Technical representatives from flooring, self-leveling, glue, etc. manufacturers regularly or irregularly go to the site to conduct technical work Quality inspection and guidance;
② The company sends professional and technical personnel for quality supervision and management;
③ Supervision and management by the construction team's special and dedicated technical quality responsible person.
2. Safety assurance measures
The policy of “safety first, prevention first” must be implemented, safe construction technical measures must be implemented in strict accordance with relevant regulations, and the construction responsibility system must be improved.
3. Arrange full-time quality management personnel to follow the work, strictly control the quality, personally inspect every construction link, and strictly follow the quality acceptance standards. Only after passing the inspection can the following construction procedures be carried out.
4. The on-site project manager ensures to be on-site around the clock to arrange and guide operations.
5. Actively cooperate with the owners and supervisors in our management, and actively and proactively rectify the problems raised by the owners and supervisors.
6. Actively cooperate with the construction unit and take good care of the completed products.
7. Strictly implement and implement various rules and regulations proposed by the owner and supervisor to the construction unit.
8. For details on the specific management organization, please see the management network diagram.
7. Construction deployment and management
1. The construction site is delivered and construction is carried out in different areas when the construction conditions are met.
2. Arrange construction personnel reasonably and divide labor reasonably. Please see the staffing table for details.
8. On-site safe and civilized construction measures
1. Safety measures
1) Establish professional safety management personnel for the project and clarify the responsibilities and powers of the safety personnel.
2) The construction site is under closed management, and safety personnel are responsible for supervising the entry and exit of personnel and materials.
3) Construction workers must wear uniform work ID cards. If they do not have a ID card, security personnel have the right to prevent them from entering.
4) All construction workers entering the site must wear special labor protection equipment for their type of work.
5) Construction water, power distribution, lighting, etc. shall be supervised by professionals in accordance with relevant regulations, and measures for protection and use shall be taken.
6) Set up a temporary material warehouse at the construction site to store flammable materials and items in categories, such as paint and glue, and set up special warehouses and manage them by dedicated personnel. Warehouses and construction sites are equipped with fire extinguishing equipment.
7) During the construction period, in order to prevent accidental accidents, a fire prevention team for construction workers was set up, with safety personnel responsible for conducting safety and fire prevention education for each construction worker, posting fire prevention notices in obvious places on the construction site, and regularly inspecting fire prevention measures. .
2. Appearance of the construction site
Five signs and one picture are hung at the construction site, namely, project overview sign, safety discipline sign, safety placard, safety record sign, and civilized construction system sign. and construction plans. Five cards and one picture are complete and beautiful.
3. Civilized atmosphere at the site
Post promotional slogans in the temporary construction site, use blackboards or newspaper columns, and the content is often updated; hang promotional slogans and banners at the entrance to the construction site.
All construction workers wear work ID cards with their names, positions, identities and numbers marked on them, and all machinery and equipment are marked with our company name.
4. Life and hygiene
Develop a life and hygiene management system, improve the hygiene of staff dormitories and food hygiene in canteens; install flush toilets, and do a good job in cleaning toilets ; Do not dump domestic garbage randomly, and domestic garbage will be centralized and included in the urban garbage disposal system; fighting, stealing, gambling and other illegal and disciplinary behaviors on the construction site are strictly prohibited.
9. Environmental protection plan
1. Noise control
Comply with the noise limits at the construction site (GB12523-90), control the noise well, and avoid damaging the environment. It will cause adverse effects to surrounding units and residents and prevent the occurrence of disturbing incidents.
2. Sewage discharge
All wastewater and sewage shall be treated according to approved methods and then discharged into the sewage system, which will never pollute the environment; all construction waste shall be transported to specified locations according to approved methods. For treatment, domestic waste should be concentrated every day according to city regulations and incorporated into the city's waste treatment system.
3. Environmental hygiene
Smoking and urination and defecation are prohibited at the construction site. Construction channels should be kept clear. Construction workers should ensure their own personal hygiene and surrounding environmental hygiene.
4. Cultural relics
During the construction process, take protective measures for affected cultural relics and ancient trees, propose monitoring and protection plans for cultural relics that need protection, and report to the cultural relics protection unit.
10. Construction machinery and materials plan
1. Construction machinery, equipment and tools
According to the performance characteristics of PVC plastic flooring, the following equipment and special tools are equipped:< /p>
※ German original WOLFF dust-proof floor grinder and various supporting grinding blocks and grinding discs
※ Powerful vacuum cleaner
※ Self-leveling special tools
※ Special edge trimmer
※ Wall marking device
※ WOLFF65KG roller and edge roller
※ Deflation roller p>
※ Ground detector
※ Various other professional tools and measuring tools
2. Material plan
Reasonable optimization based on the total area and construction plan , reduce losses.
3. Please refer to the construction equipment and tool drawings for details
- Previous article:Folk music makes the countryside more beautiful and farmers richer
- Next article:Is it illegal to put rat poison in your property?
- Related articles
- Shop name suitable for hotpot chicken
- How to advocate civilized tourism for tourists? Ninth grade English composition
- Slogan of building safety
- How much is the agency fee for buying a second-hand house in Ma'anshan?
- Teaching plan for small cleaners in large classes
- What is the content of the campus legal propaganda and moral education textbook? Do you have this book?
- Although the head was not holed and the arms were not broken, the mental pain was the most severe. I will remember for the rest of my life that my hair was pulled in the hands of the young female Chin
- Self-evaluation of comprehensive quality is about 300 words (selected 10)
- Tourism slogans around Xinjiang
- Birthday wishes for people in their 80s.