Joke Collection Website - News headlines - How to write a safe and civilized construction plan for a construction site

How to write a safe and civilized construction plan for a construction site

Safe and civilized construction planning of project projects

Overall goals of civilized construction:

Implement the general construction plan zoning management to achieve "facility standards, behavioral norms, and construction in an orderly manner" order, clean environment", create a first-class safe and civilized construction site of XXXXXX power station, and establish a safe and civilized construction brand image project of XXXXXX Construction Corporation.

Safe and civilized construction responsibilities:

Carry out safe and civilized planning, implementation, inspection and assessment of the construction areas, office and living areas under the jurisdiction of our department.

On-site safety and civilization master plan:

See the construction drawings.

Safety and Civilization Model Project Leading Group:

Team leader: XXXXXX (Director of the Project Department)

Members: XXXXXX (Deputy Director of the Project Department)

XXXXXX (Deputy Director of the Project Department)

XXXXXX (Head of the Quality and Safety Section of the Project Department)

XXXXXX (Head of the Engineering Technology Section of the Project Department)

XXXXXX (Chief of the Materials and Equipment Section of the Project Department)

The main responsibilities of the Safety and Civilization Model Project Leading Group: leading, supervising, coordinating, and inspecting various departments to ensure the planning, design, and capital investment of the Safety and Civilization Model Project, and Supervise the implementation of specific implementation units and track the results.

1. Project Overview

The main construction tasks faced by our department this year are XXXXXX excavation and concrete construction, XXXXXX floor slab, upper longitudinal section and slope concrete construction, XXXXXX and above Concrete construction in the dam section and XXXXXX highway construction. Due to the large number of work areas involved and the long distances between them, affected by the topography, the continuous advancement of construction progress and the scope of land acquisition, in order to facilitate construction and ensure safe and civilized sample projects, construction and processing production sites can be arranged in zones and slogans can be arranged centrally. Affected by the local topography and land acquisition scope, most of our camp areas are scattered, but they are concentrated within the scope of XXXXXX, XXXXXX highways, and XXXXXX blasting and excavation operations; some places, such as mixing stations, are both living and working areas. , not relatively independent. Since the construction site is not fully enclosed and on-site materials need to be guarded, there are some temporary work sheds that do not meet the standard requirements of the model construction site.

2. Difficulties in safe and civilized construction:

1. Difficulties in project safety

(1) Safety protection in high slope support construction, that is, It is necessary to ensure the safety of construction personnel and make it conform to the characteristics of water conservancy and hydropower construction sites, reduce unnecessary labor of construction personnel, and speed up the construction progress;

(2) XXXXXX excavation construction and XXXXXX dam section and above The problem of cross-cutting concrete construction work and difficulty in construction in bad weather;

(3) After entering the rainy season, the drainage system and some temporary buildings built on clay backfill foundations operate safely.

(4) Other issues.

2. Key directions of engineering safety

Usually include the following aspects:

(1) Pyrotechnic products, the entire process from receipt to withdrawal Tracking management;

(2) Scaffolding;

(3) Oil depot;

(4) Construction electricity;

(5 ) Other matters that actually exist on site, such as the contradiction between the frequent changes in the construction work surface and the relative fixity of the zigzag ladder requirements.

3. Preliminary planning of civilized construction

1. Set up XXXXXX huge advertisements and introduction to the power station project. The size is 1m*2m, 2m*4m.

2. Set up a huge "Please wear a safety helmet when entering the construction site" sign.

3. Huge construction site safety management regulations, quality leadership group, safety leadership group, construction site ten prohibitions.

4. Each work area shall have project responsibility signs. Including the name of the unit's project, project introduction, project responsible person, safety responsible person, etc.

5. Hazard identification work at the construction site. Such as high slopes: anti-fall, anti-object protection, etc. Transformers and other facilities are equipped with electrical hazards, etc. Working at heights: Please fasten your seat belts. A protective fence is set up on the side of the sky and marked: no climbing, etc.

6. Standardize construction roads and traffic management on construction sites.

Concrete is hardened on the roads entering the camp area and the XXXXXX floor; anti-collision piers are installed on the edge surfaces; road signs are marked with standardized traffic signs; speed limit signs are set up.

7. The toilets installed at the construction site are water-flush type, and the cleaning of the toilets must be done at regular intervals.

8. Set up a rest pavilion on site, equipped with a drinking water insulated bucket and a smoking room.

9. Set up trash cans, mainly at the construction site, to collect some construction site waste materials and various scattered packaging materials.

10. Standardize material identification. Standardize placement and unify signage. Indicate the material name, origin, entry date, specifications, model, status, etc.

11. Standardize electricity management. The electrician, safety person in charge, and contact number should be marked on the distribution box to standardize and solve the current situation of scattered power lines.

12. All staff members wear camouflage uniforms and sign up for work. The helmets are all blue. Full-time staff (duties, quality inspectors, safety officers, etc.) should wear corresponding red armbands.

Giant advertising slogans, etc. can be considered to be placed above the 999 horse road. The clay covering layer is still being excavated here. After the excavation is completed, a relatively stable platform will be formed. Some processing plants, PARKING LOT.

IV. Implementation Details

1. Adhere to the people-oriented concept, promote safe and civilized construction standardization, and strive to: institutionalize safety management, standardize safety facilities, organize site layout, Equipment and materials are fixed, work behavior is standardized, environmental impact is minimized, and a good atmosphere of safe and civilized construction is created.

2. The Quality and Safety Department of the Project Department is the main body for the safe and civilized implementation of engineering projects. It is responsible for the entire process management of safe and civilized construction. The office, other departments, construction bureaus, and collaboration teams fully cooperate and cooperate.

(1) Establish and improve various rules, regulations, operating procedures and related accounts for safe and civilized construction.

(2) Ensure the investment of funds required for safe and civilized construction.

(3) Prepare targeted safety technical measures (plans) according to safety technical specifications, and conduct briefings with all employees to ensure the effective implementation of the plan.

(4) Equip qualified full-time (part-time) safety management personnel in accordance with regulations and improve the safety management network.

(5) Regularly organize safe and civilized construction inspections.

(6) Strengthen safety education and training for construction managers and operators, and inform them in writing of the operating procedures for hazardous positions and the hazards of illegal operations. Carry out risk point analysis and formulate targeted prevention and control measures.

(7) Provide construction workers with qualified labor protection and safety protection supplies (appliances) and supervise their correct use.

(8) Strict safety management in the project contract and keep files on file for all workers.

(9) Comply with laws and regulations related to environmental protection, advocate green construction, and reduce the harm and pollution caused to the environment by construction.

(10) Supervise and inspect the cooperation team to apply for accident insurance for personnel engaged in dangerous operations at the construction site.

(11) Carry out safety, health and environmental assessment of engineering projects.

3. The project department shall coordinate the layout according to the safe and civilized construction plan, carefully carry out the specific design of safe and civilized construction of the construction site, and be responsible for the implementation.

4. Layout requirements for the office area and living area of ??the project department:

(1) For Class I and II buildings such as electrical equipment, office and living temporary facilities, the walls should be painted Use white or white prefabricated house building materials to unify the main color of the temporary facilities and coordinate with the on-site environment.

(2) Project department office area layout and office facilities:

1) The project department name plate should be set up at the entrance of the project department camp area. In the conference room of the project department, the safe and civilized construction organization chart, safe and civilized construction environment management goals and policies, safe and civilized construction job responsibility system, and project construction progress bar chart are set up on the wall.

2) Offices and conference rooms should be equipped with air conditioning, projection and other equipment.

(3) The living facilities of the project agency and the construction bureau are all equipped with various hardware facilities according to the requirements of the demonstration site:

1) The canteen is equipped with stainless steel kitchenware, freezers, disinfection cabinets and other facilities , clean and tidy, meeting health and epidemic prevention requirements.

2) The staff dormitories have good living conditions, are kept ventilated, clean and hygienic, have a suitable room temperature, and comply with special management measures.

3) Showers and washing facilities are provided for employees, and bathrooms are cleaned by dedicated personnel without obvious odor.

4) Provide necessary cultural and entertainment facilities for employees. We carry out various cultural and entertainment activities such as billiards, table tennis, and basketball, and regularly show movies to employees. Increase the internal LAN and broadband of the Facilities and Engineering Bureau to meet the needs of employees for network health information.

5) Inspect, supervise, and implement the living and sanitary conditions and labor protection conditions for accommodation, catering, etc. of the outsourcing team.

6) Waste collection devices should be set up in the construction area, and trash cans with labeled classification collection functions should be set up in the living area.

5. Standard requirements for the overall layout of safe and civilized construction on site:

(1) Visual image: mainly through the general layout of the construction and temporary buildings, installation facilities, safety facilities, and signs , signage and other styles and standards, coupled with visual image design (on-site safety visual identification system) to achieve an overall effect of a unified, clean, eye-catching and beautiful on-site visual image.

(2) Modular management: The general floor plan of the on-site construction should be divided into functional modules according to actual functions, including office area, living area, construction area, and equipment and material storage area. Each module area is mainly connected by on-site circular concrete roads or water-stabilized pavement, and separated by simple iron wires or steel pipes painted red and white.

(3) Regional management of construction: Implement regional management of safe and civilized construction responsibilities at the construction site. According to the work content or construction area, the work site shall be enclosed, isolated and closed by plastic steel mesh panels, steel pipe railings, safety fences or scaffolding pipe fences (red and white color codes), and safety signs and signs shall be set up to clarify safety responsibilities. . Temporary fences can also use prefabricated pole colored flag fences (red and white color code).

(4) Fixed-location management: planning and drawing construction floor plans, and stacking equipment and materials to achieve fixed-location.

(5) Fences: Fences such as transformers should be painted white, locked, and affixed with electricity signs.

(6) Construction site:

1) Arrange the process reasonably and the construction site should be kept flat from beginning to end. The earth excavated from foundation pits and trenches should be cleared and transported in a timely manner (it can be leveled on the spot if conditions permit), and should be prevented from being spilled during transportation.

2) The floors of concrete mixing stations, gravel storage yards, warehouses, material processing yards, and parking lots should all be hardened.

3) The equipment and material storage site should be solid, flat, and free of water on the ground.

(7) Roads:

1) Temporary roads built according to construction needs can be made of mud and stone hardened pavement, and drainage slopes should be formed on both sides of the road.

2) After the road concrete surface layer is poured, the finished product or semi-finished product must be effectively protected: it is strictly prohibited to mix mortar (concrete) or stack various materials on the road surface, and it is strictly prohibited to directly support the crane on the road surface. When welding operations are performed on the road surface, it is strictly forbidden for oil-spill vehicles or crawler cranes to drive on the finished road surface. Carry out regular cleaning and sprinkling of water on the road surface to keep it clean and tidy, ensuring that there is no mud on rainy days and no dust on sunny days.

3) Cables used to temporarily cross the road must pass through steel pipes painted with red and white color codes.

(8) Road signs: National standard road signs, traffic signs, speed limit signs and regional police signs should be set up on both sides of the main road. Construction area indication signs should be set up on roads within the construction site.

(9) Drainage ditches: Drainage ditches should be built in advance on both sides of the road and maintained regularly to ensure that the drainage systems in campsites, mixing stations and other places must remain smooth.

(10) Buildings: Only the following temporary buildings are allowed:

1) Construction team tool rooms, warehouses, etc. are light steel keel mobile rooms or masonry rooms, Container house.

2) Temporary work sheds and equipment rainproof sheds should be of prefabricated structure and covered with blue corrugated boards.

Asbestos tiles, scaffolding boards, templates, colored strips of cloth, linoleum felt, bamboo fence and other materials are prohibited from building work sheds at the construction site.

(11) Installation facilities:

1) Publicity notices: including publicity boards, slogans, colorful flags, etc.

2) Road traffic: including road posts, warning signs, speed bumps, prohibited signs, etc.

3) Area enclosure: including safety fences, plastic steel mesh panels, etc.

4) Waste and garbage recycling category: including various types of waste and garbage classification and recycling facilities.

5) Signage category: including equipment, materials, items, site signs, procedures, specifications, responsibility charts, etc. Its production and layout requirements:

a All signboards on site, Signs, promotional boards, etc. can be made beautiful and standardized, and can be painted with color inkjet printing.

b The embedding, hanging and display of signs must be safe, reliable, standardized and beautiful.

c Signs, sign frames, columns, and supports should use steel structures or stainless steel structures; signs should be made of aluminum plates.

(12) Large signs: The project department should set up "five signs and one picture" (project name sign, project management target sign, project construction management responsibility sign, safety sign, etc.) in the office area or construction area. Civilized construction discipline sign, general construction layout plan), an introduction to our XXXXXX Construction Corporation, a bird's-eye view of the project, etc. can also be added.

(13) Gate: The gate of the project department is required to be simple and clear. The gate generally consists of a light box, a double iron door, a side door for personnel passage, a guard room, etc.

(14) Machinery and tool rooms:

1) Mechanical equipment, tools, tool rooms, scaffolding pipes, etc. that enter the site should be renovated, painted, and uniformly color coded Make sure the logo is intact and beautiful.

2) The signs of safety operating procedures for machinery and equipment should be displayed in a conspicuous and standardized manner.

3) Medium and small machines should be kept clean, with the surface paint intact, and eye-catching and standardized operating procedures signs hung.

4) When small and medium-sized machines are used in the open air on site, they should have strong, beautiful and suitable rainproof facilities.

5) Tool rooms and containers are placed together in a neat and beautiful manner.

(15) Construction electricity facilities: The electricity used in the construction of the transformer station shall be strictly in accordance with national standards and adopt the three-phase five system (TNS system). The power supply setting should use a combined transformer (van type transformer), and the lines can be Overhead and directly buried cables are used. When the distribution lines in the station are laid with directly buried cables, the burial depth should not be less than 0.2-0.7 meters. At intersections with roads, they should be laid in strong protective tubes and obvious signs should be set on the ground; 1. 2 , Level 3 distribution board cabinets and portable power panels must meet electrical safety and related technical requirements. Distribution boxes should be equipped with leakage protectors, and the signs should be standardized and eye-catching.

(16) Lighting facilities: Centralized lighting is used in the construction area, and mobile pole-type metal lamp stands are used for local lighting. The use of simple iodine tungsten lamps is reduced or eliminated as much as possible.

(17) Fire-fighting facilities: Equip fire extinguishers, sandboxes, fire buckets and other fire-fighting equipment as required, and use fire-fighting equipment racks and boxes.

(18) Greening: Green belts should be set up in office areas, living areas, mixing stations, partially protected ballast yards, etc., with flowers, plants and trees planted, and dedicated personnel responsible for management.

(19) Drinking water points: Set up shed-style drinking points at suitable locations to keep the indoor clean and the drinking water clean and hygienic.

(20) Smoking room: Set up a box-type shed-style smoking room in a suitable area on site, and mobile smoking is prohibited in the construction area.

(21) Portable cable reel: used for small tools and temporary lighting power supply at construction sites.

(22) Water-flush toilets: Water-flush toilets should be installed at office, living, and construction sites and should be cleaned by dedicated personnel.

(23) The temporary oil depot is equipped with facilities such as lightning protection, fire-fighting sand, fire extinguishers, and rainproof sheds. There is a three-dimensional intersection problem between the XXXXXX concrete construction and the excavation above the Youfei 1002 platform. A slag retaining wall is set up above the 9999 platform to prevent problems such as rocks falling from the slope caused by blasting and excavation operations in the rainy season.

6. During project construction, national environmental protection laws and regulations should be strictly abided by, green construction should be advocated, and the impact on the environment should be reduced as much as possible.

(1) Sand, gravel, cement and other construction materials should be paved, and construction remnants should be cleaned up in time.

(2) Construction and domestic wastewater shall not be discharged at will; construction and domestic waste shall be classified and recycled and shall not be dumped at will.

7. Each project project must strengthen the quality management of the construction process, reasonably arrange the construction period, reasonably arrange the processes, and continuously improve the technological level of each process. Corresponding protective measures must be taken for finished products and semi-finished products. The work surface that is handed over from one process to the next must be clean, tidy, and meet the process requirements.

5. The safety and civility model project will be implemented by everyone and on time

According to the owner's requirements, except for the temporary oil depot which will be completed on April 10, all model projects will be implemented by the end of March.

According to the content of the model project, the following division of responsibilities has been made:

XXXXXX - all responsible for the implementation of the model project and the implementation of key and difficult contents: the renovation of the oil depot and all work sheds.

XXXXXX——Responsible for the implementation of the sample project content for high slope operations;

XXXXXX——Responsible for the implementation of the sample project content related to blasting operations;

XXXXXX ——Responsible for the implementation of the sample project content of the open channel floor;

XXXXXX——Responsible for the maintenance of roads in all work areas;

XXXXXX——Responsible for the implementation of the model project content of the upper vertical section;< /p>

XXXXXX——Responsible for the implementation of the model project content of XXXXXX Highway;

XXXXXX——Responsible for the implementation of the model project content of XXXXXX;

XXXXXX——Responsible for road watering and dust removal ;

XXXXXX——Responsible for the implementation and maintenance of all signage.

XXXXXX Construction Corporation

XXXXXX Power Station Project Department

XXXX Year XXXX Month XX Day