Part I: Report of the First Site Meeting: S324 South Ring Bridge Project of Lianyungang Trunk Highway.
Report materials
(First on-site meeting)
Nanjing Dongfang Road and Bridge Engineering Co., Ltd. South Ring Bridge Project Manager Department of Provincial Highway 324 20 12 1 1 month 22nd
Report materials of the first site meeting
Our department entered the market in early July. Through the efforts of the project department and the concern of leaders at all levels, our department has basically completed the construction of the project department. Now the work of the South Ring Bridge Project of Provincial Highway 324 is reported to the headquarters and the director's office as follows.
I. Overview of the Project
Project name: South Ring Bridge Project of Provincial Highway 324. Project cost:1207,500 yuan.
Project scale: total length1.3km (K57+000-K58+300), in which the bridge length is 826.48m.. Duration: 18 months, 201February to 201March.
The superstructure of the main bridge is a (55+90+55)m prestressed concrete continuous box girder with variable height, with a single box and double room section. Box-shaped chamber bottom width12.5m, cantilever length at both sides 3.0m, total width18.5m. ..
② substructure
The main pier of the main bridge is a solid wall pier, with a wall thickness of 2.5m, a width of 12.5m and a height of 7.563m The cap size is 14.6×9.6×3m, and the chamfer is 3×2m, so as to avoid invading the navigation clearance. 3 rows10 Ф1.6m bored pile group.
2. Upper structure of approach bridge
The approach bridge is 20m partially prestressed hollow slab beam, simply supported structure and continuous bridge deck. 3. Approach bridge substructure
Four-column pier, pier Ф1.1m, Ф1.3m bored pile foundation. I-shaped abutment adopts Ф1.3m bored pile.
Second, the construction deployment
For the convenience of management, according to the actual situation, construction period and engineering quantity of this contract, * * * arranges six construction teams, namely, two pile foundation construction teams, 1 old bridge demolition team, 1 approach bridge construction team, 1 main bridge construction team and 1 road construction team, and each construction team is fully equipped according to the professional type of work. Implement dynamic management, establish the system of survival of the fittest and incentive mechanism, so that the construction team will always maintain high quality and strong combat effectiveness, and ensure the efficient and high-quality completion of the contract project construction. Organization chart of project management department
Third, the overall progress
The whole project is divided into three stages. The first stage is the construction preparation stage:
Main operation contents: advanced equipment input; Land requisition and demolition; Leveling the construction site; Erection of temporary electricity; Construction of production, office and living facilities; Building a central laboratory; Prepare the procurement, inspection and testing of the first batch of raw materials; Complete technical preparation and site retest.
The second stage of the main project construction stage:
Main work contents: bridge foundation, pier and abutment fabrication and installation, precast beam and slab, system transformation and bridge deck system construction; Subgrade, retaining wall, waterproof and drainage construction, culvert construction, etc.
The third stage completion acceptance stage:
Main work contents: Complete self-inspection, repair and submission of subgrade, bridge, culvert, retaining wall and drainage works.
Fourth, the overall goal.
On the basis of fully understanding the requirements of bidding documents, construction contents and construction environment, and according to the construction management ability of our company, the overall construction objectives of this project are determined as follows:
1 duration target
Part II: Report on the regular meeting of construction projects: the new project of Changfeng water pump gate in Yinzhou District, Ningbo City.
(water conservancy)
Remittance information
Preparation: review: approval:
Ningbo Yinzhou Changfeng Water Pump Sluice New Construction Project (Water Conservancy) Projects Department
Zhejiang Weihai Construction Group Zhoushan Co., Ltd. 20 15 years1February 29
catalogue
I. Overview of the project. Overview of hydrometeorology
Three. Complete the visualization progress (crossplot) of major quantities this month. Four. The schedule for next month.
Verb (abbreviation of verb) is the input of main equipment, personnel and materials. Summary of engineering quality inspection. Safe and civilized construction
I. Overview of the Project
This project is a new project of Changfeng Pump Gate in Yinzhou District, Ningbo City. The design gate has a total clear width of 4m, * *1hole, and the pump house has ***2 holes, with a single clear width of 3.5m and a pump station flow of 6.6m/s; The total construction area of pump lock room, installation room, duty room, power distribution room and control room is 498 meters. The newly-built planned river course upstream is160m long and 20m wide, and the greening bandwidth on both sides is 20m. Located between Zhangbei Road (Planning Road) and Guangde Hubei Road, it dredges the river under Guangde Hubei Road Bridge. The design grade of Changfeng pump gate is Grade II, and the design grade of upstream channel is Grade IV.
Term of the contract: commencement date, year month day ~ year month day. Construction unit, survey unit, design unit, supervision unit, construction unit, quality supervision unit and project management objectives:
Quality management goal: civilized construction goal: civilized project.
Safety management goal: put an end to major safety accidents and minor injuries.
Second, complete the image progress of major quantities
Third, the schedule for next month.
3. Strive for the completion acceptance before April 1 and 20 16.
Four. Input of major equipment, personnel and materials
1 investment in machinery and equipment
Article 3: Report materials for handover acceptance of the fourth bid section of Fuzhou Expressway pavement.
One. Project overview
Fuyang-Zhou Ji Expressway starts from Liu, Lixin County, Bozhou City, passes through Yingquan District, yingdong district, Yingzhou District, Funan District and Yingshang County of Fuyang City, and finally ends at G 105, Fengjing Town, Huoqiu County, Lu 'an City.
Our company won the bid to build the fourth contract section, with the starting and ending pile numbers of K62+3 14 ~ K83+570, including Zhou Ji Interchange (K82+460 ~ K83+570), with a total length of 2 1.256 km. There are different degrees of lime improving soil, drainage, protection and structural construction unfinished along the subgrade. The main structural forms of pavement are as follows: the subbase adopts 20cm thick low-dose cement stabilized macadam; The base adopts 38 cm thick cement stabilized macadam; The asphalt surface course adopts SBS modified AC- 13+6cm thick SBS modified AC-20+8cm thick AC-25. The main projects include: subgrade earthwork construction, low-dose cement stabilized macadam subbase, cement stabilized macadam subbase and interlayer spreading cement slurry, common emulsified asphalt seal coat construction, common asphalt concrete lower layer, (SBS) modified asphalt concrete middle and upper layer, and modified asphalt spreading interlayer bonding oil; And related ancillary works: median, shoulder hardening, slope protection, drainage, defect maintenance, road reconstruction and ditch reconstruction, fence construction, etc.
Second, the completion of the winning contract
Main quantities completed
Subgrade filling earthwork is 267202m3, precast C20 trapezoidal longitudinal drainage ditch is 2 1450m, M7.5 mortar rubble is 2094 1 m3, precast C20 concrete is 96 1 m3, 20cm low-dose water-stabilized macadam subbase is 295,332m2, 18cm cement stabilized. 19cm cement stabilized macadam base is 533536m2, prime coat is 344375m2, seal coat is 345725m2, bonding layer is 876386m2, bottom layer of coarse-grained asphalt concrete with 8 cm thickness is 335659m2, middle layer of modified asphalt concrete with 6 cm is 541209m2, and C25,4cm modified asphalt.
Shoulder C20 concrete 298 1m3, C30 concrete cast-in-place structural slab 1746m3 steel handrail 9799m, reworked steel handrail 6099m. (ii) Completion of the contract
Our bidding start date is April 2009 1 day, the completion date stipulated in the contract is May 3, 20654381day, and the contract duration is 14 months. The actual completion date of this project is March1year in May, and the actual construction period is 14 months.
During the construction process, the project department carefully organizes the decomposition according to the overall plan, formulates the annual plan and decomposes it into quarters, months, ten days, weeks and days. At the same time, according to the actual construction situation, the plan is adjusted, with safety and quality as the core and progress as the goal, and the construction climax has been set off since September 2009. In particular, with the guidance and strong support of leaders at all levels of the project office, the director office, the supervision team and the local government, various problems and local interference have been overcome and the construction task has been completed as scheduled.
(iii) Execution of the contract
According to the requirements of the contract, some parts of the project will be put into mechanical equipment, equipped with test instruments, and the construction progress plan and material procurement plan will be formulated, and the construction will be carried out after a series of construction organizations are completed. We have always strictly implemented the terms of the contract with the owner. In the process of construction, we strictly abide by the general terms and special terms of the contract and establish a perfect quality assurance system. The project acceptance results meet the requirements of the contract technical specifications. In accordance with the requirements of the contract, strengthen the quality awareness management and safety education of employees, and formulate corresponding quality management systems and safety management systems. There are no quality accidents and safety accidents on the construction site.
Third, the construction organization and management
(a) Project organization and staffing
In order to ensure the normal work of the project, the project department consists of seven functional departments: engineering department, laboratory, dispatching room, machinery department, ministry of materials and equipment, finance department and comprehensive office.
The management department and laboratory are located on the right side of K82+600 route, about 1 km away from the subgrade, and rented in Fengjing Town. The centralized mixing station is located on the right side of K82+000 route.
200 meters; The prefabrication yard is located on the left side of K78+200 subgrade. In order to ensure the smooth progress of the construction task, 1 water-stabilized mixing station, 1 asphalt mixing station, 30 transport vehicles, 5 auxiliary engineering construction teams, 3 earthwork teams and 1 water-stabilized asphalt construction teams are set up in the whole line, and the project department will organize, coordinate and direct the construction of the whole line.
② Material organization
The limestone for the water-stabilized base in my bid section is crushed stone produced by Nantong Road and Bridge and Anhui Hefei Shi Lei Stone Co., Ltd., and the limestone for the asphalt surface is produced by Anhui Hefei Shi Lei Stone Co., Ltd., and the stone factory processes 6,000 tons of crushed limestone every day, which can meet the construction needs. The basalt used in the upper layer is crushed stone produced by Shucheng Tongda quarry, and its adhesion to asphalt reaches Grade 5. All kinds of materials are stored in different grades and categories, and the raw materials are not confused, which ensures that the raw materials do not change.
Machine-made sand: The limestone machine-made sand used for asphalt pavement is made of limestone aggregate produced by Anhui Hefei Shi Lei Stone Co., Ltd., and the particle size of the crushed stone used for processing the machine-made sand is fixed from beginning to end, and the mud content of the crushed stone is not more than 65,438 0%, which eliminates the quality hidden danger caused by the machine-made sand and can meet the production needs.
Mineral powder: Asphalt surface filler is mineral powder obtained by grinding strongly alkaline limestone. Gravel used for processing mineral powder has a silt content of less than 65,438+0%, a fixed particle size and is stored indoors in the rain. The treated ore powder is dry, clean and stable in particle size range, and can freely flow out of the ore powder bin. Limestone powder produced by Hefei Shi Lei Stone Co., Ltd. is selected.
Anti-spalling agent: calcium hydroxide powder (hydrated lime) is used, and hydrated lime produced by Anhui Chizhou Hengsheng is selected. The test results of raw materials meet the requirements.
Cement: Conch brand compound silicate P. C 32.5 retarded cement produced by Changfeng Conch Co., Ltd. is adopted. The initial setting time of cement exceeds 4 hours, and the final setting time exceeds 6 hours.
Asphalt: The lower layer adopts Grade A 70# heavy traffic petroleum asphalt provided by Zhongwu Zhenhua Trading Co., Ltd. designated by the owner, the middle layer adopts SBS I-D modified asphalt produced by Anhui Yuhuan Highway Asphalt Co., Ltd. and Hefei Baoying Materials Co., Ltd., and the upper layer adopts Hefei Bao.
In order to eliminate all hidden dangers, SBS I-D modified asphalt produced by Surplus Materials Co., Ltd. is responsible to the owner. According to relevant laws and regulations, our contract section samples and tests each car's asphalt and keeps samples for inspection.
(3) mechanical equipment
In order to ensure the smooth progress of the project, our company invested a set of WCZ-600 water-stable mixing equipment with an output of 600 tons/hour in this contract. A set of Estek -4000 asphalt mixture mixing equipment with an output of 400 tons/hour is used to centrally mix the mixture. The equipment can be automatically controlled in the whole process, and has an accurate disk-by-disk data acquisition and printing system. The excellent performance and function of mixing machinery provide a strong guarantee for the smooth completion of our contract section.
Chapter IV: Report materials for regular meetings of construction projects: Report materials for the 2009 conference on attracting investment.
One. Work progress and completion in 2009
In 2009, focusing on the central work of the district committee and district government, the Investment Promotion Bureau of * * District, while thoroughly implementing the Scientific Outlook on Development, constantly innovated investment ideas, improved investment methods, broadened investment fields, and worked with the Municipal Investment Promotion Office and various departments at all levels to continuously improve and optimize the investment environment, providing high-quality and efficient services for foreign-invested enterprises and individuals, and achieved new results in investment promotion in the whole region.
In order to achieve the goal of "planning and packaging not less than 30 high-quality projects and not less than 20 imported projects throughout the year, and striving to introduce 800 million yuan" put forward in the 2009 work report of the district government, we have mainly done three aspects of work in project promotion and construction: First, together with various departments at all levels, we will speed up the investment and construction of existing approved projects through supervision, coordination and service; Second, in conjunction with various departments at all levels, through supervision, coordination and service, we will promote the contracted projects to improve procedures and processes and implement them as soon as possible. Third, by planning packaging projects and increasing the publicity of the projects, we will further introduce new projects. Introducing new projects is the goal and direction of our work. In 2009, we strengthened the establishment and publicity of the project library. After careful screening, key planning and packaging, the original projects reported by towns, offices and departments will be made into DVD discs, which will be taken to Guangzhou, Shenzhen, Hangzhou, Wenzhou and other places together with cities and counties to carry out extensive promotion activities. In Lijiang, we also constantly promote it through the website. Compared with overseas investment, Lijiang, a place with special tourism environment advantages, has more advantages than other places. Many entrepreneurs will take the initiative to come to Lijiang, or to travel or play golf. In addition to publicity through the website, we will also introduce various projects to entrepreneurs in Lijiang through organizations such as chambers of commerce and entrepreneurs' associations. We think this is a good way, because going abroad to attract investment not only costs money, but sometimes it doesn't have to be in place at once. And through the association to organize entrepreneurs' project promotion meeting, it should be said that it can also achieve certain results in publicity. However, under the influence of the financial crisis to a certain extent, the input of foreign funds has obviously weakened compared with last year. In 2009, the jurisdiction implemented 22 foreign-funded projects, namely Oman Hotel; Dino Cafe Lijiang; Shuhe's Bar Street, Shuhe Shopping Mall, Xiyu Valley Hotel and Shuhe Hongshan Development Project; "Tianyu Sunshine Characteristic Dwellings" Construction Project and "Theme Pavilion" Project. Jinmao Group's World Heritage Reconstruction and Expansion Hotel Project; Shui Mu Tsinghua Garden Project; Banyan Tree Hotel Phase II Construction Project; Snow Mountain Century Garden, Xinhua Cultural Square, etc. The investment attraction project actually reached 490 million yuan. It accounts for 6 1% of the annual 800 million target tasks.
In 2009, the newly signed investment projects in the jurisdiction include: in February, an intention agreement for the development of wind energy resources was signed with the preparation office of Yangmeishan project in Lvliang, Yunnan Province; In March, it signed a cooperative operation agreement with Anman Hotel in Lijiang, and in April, it signed an intention agreement with Hainan West Coast Country Manor Club Co., Ltd. for Lijiang Provence Holiday Project; In May, he signed an agreement with Mr. Xiang Bing, cheung kong graduate school of business, on the project of Hongshan Jian Yong Academy in Shuhe, Lijiang River; In June, 1 1 signed an agreement with Shenzhen Sangxia Technology Co., Ltd. on the project of Lijiang Hi-Tech Software R&D Base.
Two. 20 10 work plan
First, it is necessary to establish key investment projects, increase investment promotion efforts, strengthen project reserves, screen a number of major projects related to the economic development of the whole region, especially non-land acquisition projects such as agriculture, forestry, animal husbandry and water, increase investment attraction, especially concentrate on the 5 square kilometers planning area of the new group, focus on introducing large enterprises and groups with core competitiveness, combine the best resources with the most powerful enterprises, and strive to achieve new breakthroughs in the total amount, scale and grade of investment attraction.
Second, we should strengthen the follow-up service of attracting investment, further improve the target responsibility management system of attracting investment around the economic development strategy determined by the district party Committee and the district government, and do a good job in landing the proposed investment projects. Further strengthen the tracking and coordination of major investment projects. Solve the difficulties and problems in the project progress in time.
Third, vigorously promote new ways of attracting investment, such as national investment, resource investment, intermediary investment, cultural investment, window investment and media investment, and truly form a new pattern of all-round investment, and strive to complete the task of attracting investment.
Three. Specific project plan of report 20 10:
Ye Ding's current construction projects include: Shuhe Celebrity Bar Street Construction Project, Shuhe Tenth Hospital Construction Project, Western Region Ancient Hotel Construction Project and Tianyu Sunshine Construction Project.
I. Shuhe Celebrity Bar Street Project
1. Start date: April 2007
2. Total planned investment: 1.20 billion yuan.
3. Accumulated investment since construction: 94 million yuan.
4.20 10 is scheduled to be completed in March, with a planned total investment of1200,000 yuan.
Second, Shuhe Tenth Hospital Construction Project
1. Start date: April 2009
2. Total planned investment: 50 million yuan.
3. Accumulated investment since construction: 3 million yuan.
4.20 10 June 30th.
Chapter V: Report materials for regular meetings of construction projects: Since the beginning of this year, Mianyang Municipal Bureau of Statistics has actively promoted the theme activity of "Deepening Year of Statistical Quality Service" in accordance with the "three accelerations" work requirements of the municipal party committee and the municipal government and the overall requirements of statistical work in the province, providing statistical guarantee for promoting the "two accelerations".
In the first half of the year, the city's economy showed a trend of recovery and accelerated development, the agricultural economy achieved recovery growth, industrial production stopped slipping and rebounded, investment growth was strong, the consumer goods market was gradually active, the growth rate of fiscal and tax revenue rebounded, the credit growth rate was relatively high, the income of urban and rural residents maintained rapid growth, and market prices continued to fall.
The city achieved a regional GDP of 38.86 billion yuan, an increase of 13.7%, ranking 15 in the whole province, up two places from the first quarter and three places from last year. Among them, the added value of the primary industry reached 6.69 billion yuan, up 4.6% year-on-year; The added value of the secondary industry reached 65.438+08.46 billion yuan, a year-on-year increase of 654.38+08.2%; The added value of the tertiary industry was 137. 1 100 million yuan, up 12.5% year-on-year, ranking second in the province. The industrial structure ratio of the primary, secondary and tertiary industries is 17.2: 47.5: 35.3, and the industrial added value accounts for 4 1.7% of gdp.
First, focus on the center, highlight key points and vigorously promote various statistical monitoring work.
Focusing on the "three accelerations", the Municipal Bureau of Statistics has overcome difficulties, reformed and tapped potential, adjusted working ideas, added work measures and strengthened special monitoring. First, further establish and improve the statistical rapid response mechanism, and focus on monitoring and statistical analysis of post-disaster reconstruction, expanding domestic demand, strengthening the city by industry, "planning project investment breakthrough year", transportation hub construction and economic target completion every month, and make early warning and forecast. Through regular data review and evaluation meetings and "joint departmental statistics meetings", a joint evaluation mechanism will be established to improve the quality of key monitoring data. Second, around the central work of the Party Committee and the government and the hot and difficult issues in society, we will carry out in-depth surveys on the people's livelihood, such as investment in fixed assets, energy saving and consumption reduction of industrial enterprises, pig prices and production, which are concerned by leaders and society, and strive to form a number of in-depth and influential statistical special survey reports to provide scientific basis for the decision-making of the Party Committee and the government. The third is to further strengthen the management of matrix system and enhance its execution. Divide the tasks into leaders, responsible departments and responsible persons, strictly implement the schedule and time limit requirements, form a good situation of grasping the first level and being responsible at all levels, and ensure the successful completion of all objectives and tasks. In addition, according to the requirements of the Provincial Bureau of Statistics and the needs of the Municipal Party Committee and the Municipal Government to speed up post-disaster reconstruction and economic development, the post-disaster recovery and reconstruction, energy saving and consumption reduction and statistical monitoring of the service industry have been fully completed.
1-In June, the Municipal Bureau of Statistics compiled and distributed 25 statistical analysis and special investigation reports and 3 statistical briefings, providing 72 pieces of statistical government information, which were adopted by the general office of the provincial government, 5 by the National Bureau of Statistics and 46 by the Provincial Bureau of Statistics. Innovatively compiled and printed special products such as Mianyang Economic Development and Prospect, Mianyang Economic and Social Development for 60 Years, Mianyang Statistical Analysis 20 10. Complete high-quality social, people's feelings and feelings investigation reports such as Survey Report on the Impact of the Global Financial Crisis on the Production and Operation of Mianyang Industrial Enterprises, Quarterly Survey on the Prices of Agricultural Products and Agricultural Means of Production, Special Survey Report on Mianyang Automobile Market, and Survey Report on the First Anniversary of Reconstruction after the "5. 12" Earthquake in Mianyang, and deliver important index data to the main leaders of the municipal party committee and municipal government and relevant departments at the first time.
Two, in-depth study and practice of Scientific Outlook on Development, to further deepen the work of statistical quality service.
The study and practice activities of the Municipal Bureau of Statistics have achieved many prescribed actions, and the self-selected actions strive for innovation. The satisfaction rate of the analysis and inspection report of the leading group of the Bureau of Statistics has reached 100%. By carrying out the 20 10 "year of deepening statistical quality service", we adhere to the concept of "deepening statistical service with learning and practice as the carrier"; Focus on upgrading service products and improve the level of statistical services; Focus on strengthening investigation and research, and give play to the role of statisticians; Innovating service mechanism and optimizing statistical service function; With matrix management as the guarantee, strengthen the responsibility of statistical service, realize the change of service concept to compound, service focus to multi-field and service function to diversification, focus on building an open statistical pattern, and strive to realize the change of Mianyang statistics from popularity to reputation.
First, based on the "scientific development" of statistical services, establish the concept of "great service" integrating statistics and scientific development. The second is to focus on "grasping service demand, optimizing service products, innovating service mechanism and broadening service fields". The key point is to expand statistical services mainly providing economic statistical products, including social statistics, people's livelihood statistics, resources and environment statistics, etc. The third is to increase the information content of statistical service products. In addition to the main macro information, the focus is shifted to statistical products including micro information, factor guarantee and progress information to improve the reference value and practicability of statistical data. Fourth, grasp the development theme, keep up with social hotspots, actively carry out various special surveys and popular surveys, improve the quality of special survey reports, and improve the overall level and quality of Mianyang statistics.
The third is to attach importance to the investigation of major national conditions and national strength, and the economic census has achieved phased results.
Conscientiously implement the "Regulations on National Economic Census", closely focus on the requirements of the "Implementation Plan for the Second Economic Census of Sichuan Province", and complete various technical work such as unit inventory, household registration, data review, data processing and reporting of the city's10.8 million households and more than 270,000 self-employed households. Make full use of census data, establish a basic unit directory database application system with unified standards, timely updates and * * * resources, start the second basic unit geographic information system construction, and build a socio-economic geographic information system with intuitive reading and convenient query. The economic census has achieved remarkable results, successfully passed the provincial inspection and acceptance, and was unanimously praised in the inter-provincial inspection in the province.
Fourth, strict statistical work norms, data quality has been improved as a whole.
The Municipal Bureau of Statistics always insists on improving the quality of statistical data as the center, conscientiously implements standardized management measures for statistical work, and strictly controls the quality of statistical data. The first is to improve the statistical data quality grading system. The establishment of city, county, township (street offices) three linkage data quality responsibility system, responsible for layers, strict data collection, summary and audit. The second is to strengthen coordination and cooperation among majors, strengthen communication and convergence with relevant departments and superior statistical departments, master first-hand information, and ensure that statistical survey data are well-founded. The third is to improve the evaluation mechanism. Further improve the quality evaluation mechanism of major statistical data, actively explore the establishment of a third-party evaluation mechanism of statistical data, and ensure that the main indicators of the city are accurate and all economic indicators objectively reflect the economic operation of the city. Five, grassroots infrastructure construction has been continuously strengthened, and actively build a "big statistics" work system.
First, actively promote the "statistical agency system" and strengthen the "three-in-one" enterprise statistical work. The work of "statistical agency system" explored by Mianyang was reported on the front page of China Information Daily, which was highly valued by the National Bureau of Statistics and the Provincial Bureau of Statistics, and has been extended to the whole province this year. Second, new breakthroughs have been made in the reform of statistical methods and systems. This year, a new monitoring index system for post-disaster reconstruction was established, a statistical system for the service industry was established and improved, and statistical investigation methods were further improved. Third, the level of software and hardware construction of grassroots statistics has been continuously improved. In the first half of the year, 276 towns and villages in the city were equipped with "special computers and printers for statistics", and the business training of grass-roots newspaper units was intensified, further improving the statistical ability of grass-roots units. Fourth, new progress has been made in the construction of statistical informatization. This year, we will invest 300,000 yuan to transform the local area network, build a new video conference room, and configure video conference facilities and equipment to build a unified and compatible statistical data platform in the city. Fifth, conscientiously implement the spirit of the instructions of Director Ma Jiantang of the National Bureau of Statistics, actively promote the establishment of the "fifth-level statistical organization" (township statistical station) in jiangyou city, and strive to consolidate the foundation of township statistics.
In the second half of 20 10, we will mainly focus on the following aspects:
First, innovative measures should be taken to establish a statistical monitoring index system of "one master, three modernizations and three upgrades", unify the thinking with the development path of "one master, three modernizations and three upgrades" and the leading strategy of "strengthening the city through industry", and strengthen special statistical monitoring.
The second is to strengthen statistical law enforcement. Intensify the publicity and implementation of the newly revised Statistics Law and the newly promulgated Provisions on Punishment of Statistical Violations and Disciplinary Actions, and strengthen the awareness of statistical laws and regulations of all subjects. At the same time, do a good job in the special law enforcement inspection of statistical qualifications.
The third is to speed up the statistical reform and deepen the statistical quality service. Further expand the scope of statistical services, strengthen statistical monitoring and analysis, forecast and early warning, and provide decision-making staff from the long-term development strategy. Carry out a series of special surveys such as Mianyang Industrial Park (industrial concentrated development zone) survey and Mianyang 12 energy consumption survey of key energy-consuming enterprises.
Fourth, comprehensively promote the "statistical agency system", further strengthen the park's statistical work, strengthen the "fifth-level statistical institutions" pilot, explore the establishment of "township accounting centers", and improve the quality of statistical source data.
Fifth, actively do a good job in the preparations for the sixth national census.
- Previous article:What famous wines are there in Anhui?
- Next article:Emergency plans for fire safety in villages and communities
- Related articles
- "Love growth, love charity" accompanies charity activities for children with cerebral palsy.
- What's the name of the pancake shop?
- Travel safety tips in snowy days
- Practice, how to make chicken pieces in casserole, and the home-made practice of chicken pieces in casserole
- How about Fuzhou Yucheng Printing Co., Ltd.?
- How far is it from Gongtan Town to Longxi Town?
- Make sentences with piggyback (about 30)
- How to write a humorous advertisement recommendation for the wedding team?
- Why do I feel dizzy and chest tight after soaking in hot springs for a long time?
- What is the moral of Ferrero chocolate? Ferriero's advertising words are only for those who love them the most.