Joke Collection Website - News headlines - How to write the construction manager's plan

How to write the construction manager's plan

Engineering construction is a special accounting subject for construction and installation enterprises to collect and calculate the project cost, and it is an activity to build, expand and rebuild construction projects according to the requirements of construction project design documents. Engineering construction consists of four details: labor cost, material cost, machinery cost and other direct costs. The following is "How to write a good construction manager plan" for your reference.

Tisch

At the arrival of the new year, I analyze and evaluate my work, sum up experience and lessons, and improve my methods, so as to learn lessons and make up for deficiencies in my future work, which will be the basis for improving my working methods in the future.

The manager of the project department pays attention to controlling the construction quality of the project, and pays close attention to saving the project cost with the management of the supervision team, the safety management of the security department and the material management.

1, project quality management

Due to the particularity of Wang Hucheng project, the project quality requires high standards and a high starting point. In the early stage of construction, we should pay attention to the technical disclosure of the team, so as to lay the foundation for the team members to meet the quality, progress and safety requirements of the project technically and lay the foundation for the later construction.

Like the second floor, the four single structures need carpenters, steel workers and masons to construct according to the drawings, and video materials (photos, etc.) are reserved. ) Let their individual team members watch their opinions and ask their individual 4# to build. This move also brought the supervision, acceptance, construction and praise of individual units in the later quality management to the later construction quality.

2, four single building management

3. Team management

(1) The most basic managers in the construction administrator's office are not only commanders and combatants, but also feedback on grassroots issues. They should also establish their own image. At work, colleagues set an example. Emotionally, colleagues trust their partners and ask them to work overtime to meet high quality standards. I have participated in the whole process of every concealed project, paying attention to process control and controlling the quality defects in the bud.

(2) Colleagues: When colleagues have something to do, they help to cover for the class and organize the whole class to sympathize with the big family atmosphere.

(3) Pay attention to the training of four single building numbers. I will try my best to make every comrade dominate every meeting, make every comrade independent with his own experience, and make the whole team technically integrated.

4, safety management work

In the course of work, the safety management and education of the construction personnel of the Ministry of Security have achieved excellent results in many construction inspections, and the safety management demonstration monomer of this project has been included in the quarterly safety inspection.

5, and construction, supervision

When the construction manager watched the start of the Lake City project, I paid attention to the construction and supervision work and took the lead in construction and supervision.

extreme

The expansion project of xx Psychiatric Hospital is a project for me to display my talents and learn new knowledge. I will cherish this opportunity and plan from the following aspects in order to finish the work better.

A, the blue prints.the design and engineering technical disclosure

Check the drawings when they are received, and check the contents of the drawings and various systems in time, so as to solve them in time when the blue prints.the design. According to the approved construction organization design, construction scheme and quality acceptance specification, make quality and technical disclosure to the construction team.

Second, the construction safety

According to the production policy of safety first and prevention first, the temporary water and electricity use in the construction site and living quarters will be inspected irregularly, and potential safety hazards will be handled in time. According to the approved safety construction plan, make safety disclosure for workers in special parts.

Third, the construction quality

In order to avoid quality defects, patrol the construction site irregularly and correct the mistakes in time, and put forward preventive measures to the team leader for the places prone to quality defects. In case of conflict with the civil works, consult with the civil works in time to avoid delaying the construction progress, and notify the construction team for rectification in time for the projects that need hidden acceptance. Strictly check all hydropower materials entering the construction site to prevent unqualified materials from being applied to the construction site.

Fourth, the construction progress

Speed up the construction progress under the condition of ensuring safety and quality, and cooperate closely with the civil construction party to ensure the smooth progress of the construction. Due to various reasons, the construction progress is slow. When necessary, ask the construction team to increase workers and work overtime. In order to better cooperate with the overall construction schedule, the working procedures that affect the overall construction schedule of this major will be solved in time.

Verb (abbreviation of verb) building materials

Without changing the design intention, the route and pipeline of hydropower construction drawing are redesigned to save materials and costs. In order to avoid the waste or loss of engineering raw materials, explain the reasonable use and cleaning of the team. Avoid the theft of raw materials and set up a special warehouse.

Tisso

In 20xx, xx Square Station in our work area has successively completed many processes, such as continuous wall, crown beam, supporting beam, cushion system, end reinforcement, and multiple traffic diversion reconstruction. In the new year of 20xx, new technologies such as foundation pit excavation, steel support erection, comprehensive grounding, main structure construction, temporary deck demolition and ancillary structure construction will be ushered in. No matter for the field of work or individuals, they will face new pressures and challenges! In this regard, I made a 20xx personal work plan to make greater progress and achievements in the new year.

I. Process management

1. Personnel arrangement: due to the start and increase of new processes, it is necessary to strengthen technical personnel to ensure the safe and efficient management of all kinds of work in the whole work area (including librarians, electricians, general workers and other staff).

2.20xx During the foundation pit excavation from February to May in XX, the personnel, mechanical equipment and emergency supplies were basically in place at the initial stage of foundation pit excavation, and the construction was proceeding in an orderly manner according to the foundation pit excavation plan. This stage is very important. The position and direction of excavation in the early stage determine the subsequent construction. Our work area strictly follows the plan and reports to the leaders all kinds of situations at the scene in time.

Next, in the stage of foundation pit excavation, several excavators cooperate with each other to ensure the safe and rapid progress of each excavation face, and set up steel-supported continuous wall, bulging treatment and line invasion in time. After the excavation of the foundation pit has bottomed out, do a good job of first acceptance to ensure the preparation work before the main body construction.

3.20xx to 10 June, the main structure construction, this stage is the focus of this year, but also the top priority of the whole station construction. The previous work was aimed at the construction of the main structure, so at this stage, our work area needs to strengthen the management of all links. For example, comprehensive grounding, large-scale team management (large number of people), large-scale reserved holes, generous concrete pouring, large-scale steel binding, large-scale scaffolding and formwork erection, multi-level and high-frequency hoisting operations, especially carpet area construction, require our technicians to keep an eye on every working face at all times, learn from various successful experiences of Liangxiqiao Station, and take various mistakes of Liangxiqiao Station as a warning. Cast xx Square Station into a high-quality project.

4.20xx 10 to 12 is the stage of station backfilling, cover plate removal and ancillary structure construction. At this stage, it is mainly to improve the construction of the whole station and restore the road. The main difficulties are traffic guidance, rational site planning, and safe and efficient management and control.

Second, the technical management

1, carefully review the drawings, ensure the excavation depth, concrete purlin position, steel support spacing and lattice column reinforcement, organize everyone to study the construction drawing and architectural drawing of the main structure of the station, carefully check the quantity, and designate special personnel to carry out special management (reinforcement and concrete).

2. Seriously do a good job in the technical disclosure and safety technical disclosure of each working procedure and working face, and ask the leaders of the engineering department to review, and then let each technician know the working face he is responsible for, strengthen the management of the cooperative team, and let every worker at the scene know his work content, requirements and safety precautions. Technical problems should be pre-controlled, first disclosed, so as to lay the foundation for the construction quality, safety and progress of the project.

3. Seriously hold the on-site meeting, summarize the work of the day, arrange the work of tomorrow, and ensure the convergence of all working faces. Technicians and team leaders are required to attend the * meeting, and must be handed over at the scene when working with the next team *, and all kinds of unstable factors in the working face are specially explained.

Third, on-site management

1, project quality and safety control: according to the construction specifications and design requirements, check the elevation of each excavation face, the spacing of steel supports, steel bar binding, formwork removal, concrete curing, scaffolding, etc. All these must be carried out by people, and all working procedures and working faces must be watched by technicians. If quality and safety hazards are found during on-site inspection, it is necessary to understand the construction process in time, analyze the root causes of the hazards, coordinate the construction personnel to deal with them, and then conduct inspection and acceptance after the treatment is completed, so as to finally eliminate the quality and safety hazards.

2. Project progress control: pay close attention to foundation pit excavation, urge all excavations to face forward construction, ensure the supply of materials and equipment, do everything possible to make excavators and other equipment play the greatest role, actively contact unearthed units, ensure excavation volume, complete foundation pit excavation as soon as possible, and create a good situation for the main structure construction of the station.

3. Civilized construction: Respond to the call of the leaders of the project department and strive to make xx Square Station a civilized construction site in Wuxi. Last year, our workplace did not do enough in this regard. This year, we will divide the two sites into several blocks, one for each technician, and punish those who do not meet the requirements. And strengthen the management of the doorman.

4. Personnel management: As some new people have been added to our work area and lack of work experience, we will study the information and specifications of my leaders at the same time when carrying out various tasks, and ask Liangxiqiao Station and leaders for help in time if there are any problems in our work.

Fourth, the project cost control

1. Oil control: At present, there are many excavators working on the site. First of all, the system of three inspections (warehouse keeper, technician and driver) should be implemented to stop waste from the source. Let each excavator play the biggest role, shorten the transportation distance and transshipment times.

2. Raw materials such as steel bars and concrete: It involves the processing of semi-finished steel bars, and technicians need to check the drawings repeatedly to ensure the accuracy, necessity and practicability of semi-finished steel bars, the rational utilization of steel bars, and the non-scrapping and non-waste. When it comes to the use of concrete, technicians are required to report a planned dosage, and the construction team is required to report a planned dosage, which can effectively control the dosage of concrete.

3. consignee's work: carefully check the contract, determine the position and content of the consignee, and confirm with the consignee together with the leaders of the engineering department and accounting department. Do a good job of sorting out the receiver's data and report the receiver's results to the engineering department leader in time. Ensure the timeliness, authenticity and accuracy of the receiver.

Verb (abbreviation for verb) personal idea

1, Strengthening management of on-site civilized construction: 20th century 2 1 Advocating harmonious civilization, Wuxi municipal government requires us to be one, and the leaders of the project department require us to carry out high-standard civilized construction. Our work area resolutely responded to the call, strengthened the management of civilized construction, enhanced the strength of civilized construction, conducted high-standard doorways training, and strictly implemented post responsibilities. Train and cultivate the cooperative team, so that the cooperative team must meet the same standard.

2. Cooperative team management: technical disclosure and safety technical disclosure must be in place, and the phenomenon of anti-work must be resolutely put an end to. Promote the collaborative team to complete various tasks safely, quickly and with high quality. We must crack down on irregularities in our work.

3. Personal work promotion: Due to the lack of personal work experience and knowledge, there are many mistakes in previous work, so there are still many places to improve and learn. First, it should be commended. First, learn more, often learn to improve the plan, and avoid unnecessary losses. Second, learn more, often learn the main construction drawings and architectural drawings, so as to come up with good solutions to problems when there are difficulties in work. Third, learn more, and often learn all kinds of engineering cases and engineering materials. , improve the ability to deal with accidents, timely and effectively solve emergencies. Fourth, study more, study lecture materials irregularly, watch some entertainment programs irregularly, strengthen your communication skills, improve your communication skills with owners, supervisors and leaders, and let the work be completed efficiently.

Clear your own development direction, correctly understand yourself, correct your own shortcomings, seriously listen to the sincere opinions of others, work harder, study hard, strive to improve your cultural quality and various work skills, give full play to your own abilities, and let yourself really embark on the road of management. I will also learn from other colleagues, learn from each other's strengths, exchange good work experience with each other and make progress together. Get better working results.

The above is my work plan and development direction for 20xx. I hope that through my own efforts and the assistance of others, I can successfully reach the plan and make a breakthrough, achieve better results in 20xx and improve myself in an all-round way.