Joke Collection Website - News headlines - Demolition of the encirclement in advance and returning the road to the people Chengdu Metro Line 4 will be opened in February next year.
Demolition of the encirclement in advance and returning the road to the people Chengdu Metro Line 4 will be opened in February next year.
Yesterday morning, dozens of construction workers were busy at the construction site of Wen Jia Station of Metro Line 4 on the north side of the second section of Guanghua Avenue. Since the enclosure construction began in February, the station has completed the earthwork construction and entered the construction stage of the main structure of the station. According to the construction progress, the main structure of the station will be capped at the beginning of 10, which will be 6 months ahead of the original construction period. ? Due to the early completion of the main body, it provides conditions for the shield to go down the well. The shield machine can be launched around the end of August, which is also four months ahead of schedule. ? Xu Shaoping, overall head of Wen Jia Station of China Railway 13th Bureau, said.
Point 1
Restore the original traffic on Qingyang Avenue at the end of April next year.
According to Jiang, deputy director of Engineering Department I of Chengdu Metro Construction Company, the construction time of the original main structure of qingjiang road station at the intersection of Qingjiang Middle Road and Qingyang Avenue is from July 3 this year to September 30 next year. By adjusting the construction method, the intersection node cover excavation method is optimized as cut and cover construction for quickly laying temporary steel temporary bridge, and the three-time edge-reversing construction process is optimized as two-time edge-reversing construction, which ensures the two-way six-lane traffic of Qingyang Avenue at the intersection. The time for the intersection to occupy the road is 4 months ahead of schedule, and the original traffic of Qingyang Avenue will be restored at the end of April next year. At the same time, in the later period, the open-cut and reverse-edge construction of the north side subsidiary structure crossing the road was changed to the underground excavation construction, which reduced the occupation of the middle road of Qingjiang Middle Road, and the original two-way traffic of Qingjiang Middle Road could be fully restored by the end of August next year.
Second point
The traffic of frozen green trees has been restored, and the traffic of Shi Yang Street is expected to be optimized in advance.
The reporter learned that the original preliminary design plan of Taisheng Road Station set up shield starting wells and track row wells at the intersection of Frozen Qingshu and Zhonglisi East Road. As the starting point of the shield, the frozen Qingshu Street and Zhonglisi East Street must be closed for nearly two years. In order to ensure the rapid construction of the shield section and avoid the traffic jam of the frozen Qingshu Street and Zhongliesi East Street, the starting shaft of the shield was adjusted to Taisheng Road Station for initial shield excavation, and the traffic of Zhongliesi East Road, the frozen Qingshu Street, Yuefu Street and Xiawa North First Street was restored 22 months in advance (from 201April to 201February).
In addition, according to the specific situation of the corresponding station construction, the subway company has been organizing and studying the scheme of adjusting the shield departure of Shi Yang Street to the station departure. If the scheme is feasible, the one-way traffic condition of Shi Yang Street will be optimized to two-way four lanes more than 12 months in advance.
the third point
The following year 1 Wucheng Street resumed traffic at the end of the year.
Jiang told reporters that the transfer station of Metro Line 4 and Line 3, Provincial Federation of Literary and Art Circles, is located at the intersection of Hongxing Road and Wucheng Street. The original construction plan covers a period of * * 26 months from February 2065438 1 day to April 30, 2004. In order to shorten the construction period as much as possible, we are organizing construction 24 hours a day. It is planned to complete the construction of the main structure of the station at the end of 20 14 and 1, and resume the traffic of motor vehicles in Wucheng Street three months ahead of schedule.
- Previous article:Looking for narrative material
- Next article:Why can't I pay a New Year call on the first day of the first month?
- Related articles
- What does Nanhai Wenchang chicken mean?
- What are the best items for school charity sales?
- Shaoxing domestic waste classification slogan
- National Security Education Day theme class meeting
- Pinduoduo's online shop name is a creative online shop name?
- The slogan of community garbage classification in Times
- Who can tell me why Shanshi started school so late?
- What does the lottery card for Hamburg say? How to write?
- Asking for promotional techniques for the movie "Hero" directed by Zhang Yimou, refer to Hero's Encyclopedia "For the first time, many domestic films adopted marketing techniques that had never been s
- Key points of supermarket decoration design