Joke Collection Website - News headlines - Management scheme of safety and anti-theft in construction site

Management scheme of safety and anti-theft in construction site

Chapter 1: Anti-theft scheme of construction site

1. Purpose: This plan is formulated to strengthen the management of materials, tools and construction machinery vehicles in the construction area, prevent theft and ensure that the company's property is not damaged.

Second, the general situation of construction area:

(1) The construction sites in the construction area under the jurisdiction of this project division are: 13# building, 19# building, 20# building, 2 1# building, 22# building, 23# building, 24# building and 25# building.

(2) The main management objects of each construction area are: materials, tools, waste materials, mechanical vehicles and various equipment and facilities needed for construction and production, temporary oil storage and explosive storage, living and office facilities and vehicles of the project department, laboratory instruments and various articles, and various articles and materials in the canteen.

Three, the construction site anti-theft agencies and responsibilities

(a) the project department set up a leading group for anti-theft management on the construction site:

Team leader: Zhang

Deputy leader: Zang Shaobing

Members: Ma Diankai, Li Zhiqiang, Ma Guodong, Sun Cong, Zhao Jun, Zhao.

(2) The project division has an anti-theft office on the construction site in the comprehensive office of the project division, and the director of the comprehensive office is responsible for organizing the daily work.

(3) Responsibility

1. Responsibilities of team leaders

1) The team leader is the first person in charge of anti-theft management on the construction site within the management scope of the Division.

People, take full responsibility for the anti-theft management within the construction scope of the Division.

2) Be responsible for external coordination of resources required for anti-theft management on the construction site of the Branch.

3) Be responsible for organizing and handling the theft on the construction site.

2. Responsibilities of the Deputy Team Leader

1) Assist the team leader and be responsible for the specific arrangement of anti-theft management on the construction site within the scope of division of labor management.

2) Be responsible for organizing the formulation of anti-theft management scheme.

3) Be responsible for the specific investigation of theft on the construction site and report to the team leader.

3. Responsibility of members

1) All members of the anti-theft team are responsible for the specific work of anti-theft management within their respective jurisdictions and cooperate with the project department to do a good job in anti-theft management.

2) Be responsible for organizing and managing the daily management, inspection and inventory of all materials, wastes, tools and mechanical equipment within the jurisdiction.

3) Complete the work arranged by the anti-theft management team of the project department.

4. Responsibilities of the anti-theft office

1) is responsible for the specific implementation of anti-theft management of the project division. Dispatch the required vehicles and equip the required materials as required.

2) Responsible for effectively setting up security according to anti-theft management.

3) Responsible for organizing anti-theft patrol work according to the needs of the construction process.

4) Responsible for organizing and coordinating the handling of theft incidents.

Fourth, anti-theft measures

(1) The anti-theft work in each construction area is organized by the construction unit under its jurisdiction, and each construction area has its own anti-theft management organization, which is integrated with the anti-theft management organization of the project department.

(2) In the concrete implementation process, the project department will set up a temporary anti-theft patrol team of the project department to patrol irregularly for 24 hours, and be responsible for inspecting and supervising the safety work of each construction area.

1. Strengthen the management within the jurisdiction of each construction area, and prohibit non-construction personnel from entering the construction site; When outsiders need to find someone, they must wait outside the construction scope and be summoned by the construction site manager, otherwise they will be driven out of the construction site as non-construction personnel.

2. The Project Department shall set up a temporary anti-theft patrol, which has the right to inspect and inquire about the personnel and vehicles entering and leaving the construction site during non-production time or under suspicious circumstances, and report the problems to the anti-theft office immediately if found, and the anti-theft office will immediately organize the handling according to the actual situation.

3. All kinds of materials, machinery, equipment and facilities entering and leaving the construction site must have complete allocation procedures, and the temporary anti-theft patrol of the project department has the right to detain all kinds of materials and vehicles with incomplete procedures entering and leaving the construction site for processing.

(3) The anti-theft emergency team set up by the project department is composed of all security personnel of the project department and the anti-theft emergency team of the construction unit, which is uniformly dispatched by the anti-theft office and is responsible for maintaining the order of the anti-theft incident disposal site of the project department, protecting the safety of internal employees and preventing the theft from expanding.

(4) Strengthen the publicity of anti-theft knowledge.

Five, anti-theft event handling procedures

(1) Anti-theft incidents: People, vehicles, materials and supplies entering and leaving the construction site, important parts or the living and office area of the project department are all anti-theft incidents, such as incomplete procedures, unknown sources, forced looting, etc.

(2) The anti-theft management agencies at all levels must report the theft incident to the anti-theft management office of the project department, which will organize the handling, and it is strictly forbidden to handle it privately.

(3) Alarm telephone number of anti-theft management office of the project department: 68023064.

(four) the project division theft disposal procedures:

Chapter II: Security and anti-theft measures on the construction site

Edited by Jing Tian

Reviewed by:

Approver:

Date of compilation: June 8, 201X.

With the continuous progress of society, the concept of safe production has been deeply rooted in people's hearts. In the accident-prone construction industry, how to ensure the personal safety of construction workers, promote civilized construction and protect site property is a top priority for construction units and superior departments. Seriously implement the policy of "safety first, prevention first", further strengthen the safety production management of the project department, control and reduce the occurrence of theft cases, and take effective measures to minimize property losses.

1. Basic situation of the site and current security situation

1. 1 Basic information of the site

The residential general contracting project is a group residential project invested and undertaken by real estate co., ltd. The project is located in Qingnian Street, Shenyang, surrounded by commercial concentration areas, and located in a prosperous area. The site is about 90m long from east to west and 2 10m long from north to south. The total construction area of the project is about 146547.95 meters. Underground for the second floor garage (27649. 6㎡)。 Buildings 6#, 8# and 10# have three floors underground and 48 floors above ground, and the building height is 147.6 meters. Building 7# has three floors underground and 33 floors above ground, with a building height of 97. 25 meters. Building 9# has three floors underground and 32 floors above ground, with a building height of 97. 50 meters .. 1 1# building lobby on the second floor, with a height of 8.35 meters.

1.2 security status

(1) security setting: 20 security personnel from the security company are hired as the security force of this project.

(2) Site enclosure: There are three gates on one side of this project, and the enclosure of two transformers is incomplete;

There is a heritage gate on the south side, and the height of a fence is not enough; There is a vehicle storage door and a fence in the staff dormitory on the east side. Now there are doorposts at the south gate and the northwest gate.

(3) Warehouse: At this stage, there are subcontractors' warehouses in the basement of the construction site and individual buildings.

There are watchmen in the warehouse.

(4) Material storage yard: At present, there is a temporary storage yard for subcontractor's materials in the open space between buildings, and each subcontractor is responsible for it.

Responsible for their own site, the general contractor is responsible for the inspection of the whole site.

(5) Exit of on-site passage: At present, the emergency passage gate is set at the south gate, which is guarded by security guards. It is strictly prohibited to use it in non-emergency situations.

Access; Simon set up a gate as the main entrance and exit, guarded by security guards; There is no post on the east side of the gate, but it is guarded by permanent security personnel. There is a main road in the site for vehicles to enter and exit from the south gate to the west gate; The west gate faces the ramp entrance for vehicles to enter and exit the basement; Only people can enter and exit through the path from the office area to the east gate.

2. On-site anti-theft management institutions and responsibilities

2. 1 On-site anti-theft management system

2, the project department set up an on-site anti-theft management team headed by the project manager, its personnel composition is as follows:

Group length:

Deputy team leader:

Members:

2.2 The main responsibilities of the leading group

(1) Unified deployment of security equipment and personnel

(2) responsible for the information release of on-site anti-theft work.

(3) responsible for the inspection and guidance of on-site anti-theft work.

(4) Be responsible for educating the on-site operators and security personnel on anti-theft safety, and call relevant personnel to study measures and methods that are beneficial to anti-theft.

2.3 set up a security team at the scene.

The Project Department has hired a security team, whose personnel are as follows:

Person in charge:

Team leader:

Team members:

2.4 Responsibilities of the Security Team

(1) Check that all construction personnel must get in and out of the vehicle with the site pass when entering the construction site.

(2) Foreign service liaison business personnel must go through the registration formalities in the gatehouse before entering the site, and can only enter after being confirmed by contacting relevant personnel and approved by the doorman.

(3) When materials enter and leave the site, there must be an application from the material management personnel or the personnel designated by each subcontractor, and the security personnel are allowed to issue the exit sheet issued by the general contractor.

(4) Vehicles entering and leaving the site shall be inspected by the doorman with the vehicle driving license, and the doorman shall have the right to ask the vehicles and personnel entering and leaving the site to assist in the inspection, or even open the package for unpacking inspection.

(5) Personnel entering the construction site must dress as required. The doorman has the right to refuse people who don't wear helmets and slippers to enter the construction site.

(6) Patrol the perimeter of the fence on the construction site to prevent anyone from climbing over the fence or throwing objects.

(7) Security guards in living quarters and office areas should regularly patrol the management area to check suspicious personnel and prevent theft. For valuables brought in and out, such as laptops, a registration system should be established. Toolboxes and suitcases carried in workers' living quarters should be checked out of the box to prevent wires and cables from entering the site.

(8) According to the arrangement, enter the construction floor to check the rooms and facilities for important equipment, check suspicious personnel and prevent theft.

(9) All safety posts should have perfect handover records, and report the material distribution bill to the Ministry of Security daily.

(10) Conduct regular safety post training, and conduct quality training such as safe and civilized language and drills.

(1 1) The security team needs to establish class and team-level management, and establish an internal supervision and inspection system and a reward and punishment system to deal with off-duty players who violate labor discipline.

(12) The project security team is also the emergency rescue team of the general contractor. In case of fire, worker group fights and other emergencies, the rescue work should be carried out under the deployment of the general contractor's security department.

3. Safety management measures

(1) Strengthen the management of all employees, contract workers and laborers, strengthen legal education, and raise awareness and vigilance against theft.

(2) By increasing monitoring facilities, strengthen the anti-theft monitoring on the construction site, so as to achieve "anti-theft, prevention first", nip in the bud, and ensure a good construction environment and construction order.

(3) Strengthen the inspection of the construction site. The subcontractor and the security team will jointly form a patrol, and individuals will conduct regular inspections and take effective measures to prevent the materials from being stolen.

(4) Strengthen the management of materials, materials and equipment on the construction site, clear the site after work, and report to the competent anti-theft department of the project department in time after erection and addition of wires.

(5) Strengthen the recycling management of the remaining pipe fittings and cables on the construction site. No one is allowed to collect and resell them without permission to prevent criminal cases arising from pipe fittings and cables. If anyone is found to have the above situation, it will be handed over to the public security organs and relevant units for handling.

(6) When patrolling the construction site, if there is any situation, immediately report to the team leader and truthfully report the site situation for future investigation.

(7) The anti-theft work of migrant workers' compound should be carried out to those responsible, and the materials of migrant workers' compound should be managed by special personnel. In case of theft or loss, the parties concerned shall be given financial punishment.

(8) All departments shall strictly abide by the rules and regulations, and the personal belongings on site shall be properly kept by individuals, so as to ensure the safety of valuables, equipment, materials and funds.

(9) The station should watch, check, ask and stare frequently, and the key parts should be well controlled to ensure the safety of the station.

(10) The resident should strengthen the guard management and patrol by special personnel to prevent personal belongings, materials and equipment from being stolen. When a case is discovered, it should be reported in time and to the local public security organ, and criminal acts should be punished and cracked down by relying on the law.

(1 1) In case of holidays, all anti-theft matters shall be inspected, arranged and arranged to ensure the continuity of anti-theft work.

4. On-site anti-theft management regulations

4. 1 Provisions on Daily Management of Anti-theft Work

(1) All units shall implement the policy of giving priority to prevention and comprehensive management, and implement the responsibility system for safety prevention.

(2) Install security measures such as monitors and metal detectors in places where theft cases are prone to occur.

(3) actively cooperate with the personnel department to do a good job in the ideological and moral investigation of employees to ensure the purity of the workforce. If inappropriate personnel are found, they will be replaced or dismissed according to relevant regulations.

(4) Security personnel should strengthen daily patrol work and report suspicious people and things in time.

4.2 Disposal method of stolen property on site

(1) Immediately report the security department and telephone number of the general contractor.

(2) Don't move the scene decoration or touch anything, but protect the scene and shoot with a camera.

(3) block the scene in time, and no one is allowed to enter.

(4) Observe whether there are suspicious people coming in and out, and record the value and time of stolen goods.

(5) After the law enforcement officers arrive at the scene, they should assist them in their work and provide copies of the information so that the law enforcement officers can conduct internal investigations.

(6) Investigate and take confessions of personnel from relevant departments, and conduct a close investigation on key parts and individuals.

4.3 All departments must abide by the following provisions in anti-theft work.

(1) Organize legal education for employees at least once a month to strengthen their legal awareness.

(2) Organize regular or irregular inspection of security and anti-theft work, and rectify in time when hidden dangers or loopholes are found.

(3) Improve the duty system of cadres, manage their own belongings, and report to the general contractor's security department in time when materials are found missing on site.