Joke Collection Website - Mood Talk - That's how the ceiling construction steps are done!

That's how the ceiling construction steps are done!

Nowadays, many people have high requirements for home decoration, among which the installation of suspended ceiling is an important link that cannot be ignored. The installation of the ceiling can improve the whole family. So, how to install the ceiling? The following small series will talk about the construction steps of the ceiling, let's take a look!

A, ceiling elastic line construction steps

According to the floor elevation line, measure the ceiling design elevation vertically with a ruler, play the ceiling elevation around the walls and columns, and draw the dividing position line on the wall along the ceiling elevation horizontal line.

2. Installation of large keel suspenders for ceiling construction steps

After playing the ceiling elevation horizontal line and keel position line, determine the elevation of the lower end of the suspender, and connect and fix the bolt-free threaded end of the suspender with the embedded reinforcement of the floor according to the position of the large keel and the hanging spacing.

Three. Installation of large keel in ceiling construction steps

1. Install the boom nut.

2. Install hanger in advance on the big keel.

3. Install the big keel: put the assembled big keel of the hanger into the corresponding hanger nut according to the position of the step line, and tighten the nut.

4. Connection of the large keel: install the connector, and adjust the elevation by pulling the wire to make it arch and straight.

5. Install a large keel at the mouth of the cave, and set the connection card according to the corresponding node structure of the atlas.

6. Fix the side keel with nails. When there is no requirement in the design, the nail spacing is1000 mm.

Four, ceiling keel installation construction steps

1. Press the ladder line of the middle keel and clamp the hanger of the middle keel.

2. Hanging the middle keel: according to the spacing of the middle keel specified in the design, hang the middle keel on the big keel through the hanger. If the design does not require it, the general spacing is 500 ~ 600 mm

3. When the length of the middle keel needs to be extended by more than one, the middle keel connector is used, and the middle keel is connected, straightened and fixed while hanging.

Verb (abbreviation of verb) Installation of small keel in ceiling construction stage

The steps of installing the small keel are actually similar to those of installing the middle keel above, and can be realized in the same way.

6. Installation cover plate for ceiling construction steps

Under the light rigid frame that has been installed and accepted, according to the specifications of the cover panels, a row of cover panels will be installed from the middle of the ceiling based on the direction of the middle keel, and then installed in branches on both sides. The spacing of self-tapping screws for fixing the cover panels is 200 ~ 300 mm ..

Seven, smallpox condole top brush antirust paint construction steps

Rust-proof paint should be applied to the ceiling and welding parts of light steel frame cover panel before completion.

The above are the steps of suspended ceiling construction shared by Bian Xiao, hoping to help you. If you want to know more about the ceiling, please stay tuned.