1. Decoration construction can be roughly divided into the following stages:

(1) civil construction stage

(1) After entering the site, demolish the wall and build a wall.

(2) Grooving, hydropower transformation and acceptance.

(3) Underground trunking concealed hydropower renovation project, waterproof project, 24-hour closed water test of toilet and kitchen floor.

(4) Wall tiles shall be attached to the bathroom and kitchen floor.

(2) Primary treatment stage

(1) When the woodworker comes into play, the ceiling and gypsum corner line.

(2) Door cover and window cover, making wooden cabinet frame.

③ At the same time, make all kinds of wooden doors, modeling doors and flat pressing doors.

④ Brush dust-proof paint (clear oil) on the board.

⑤ The marble countertops on the windowsill are leveled and laid.

⑥ Stick veneer, make thread and install carefully.

⑦ Treatment, grinding and leveling of wall base.

⑧ Paste adhesive (edge protection) at the joints of furniture and doors and windows.

(3) Detail processing stage

(1) The wall shall be painted at least three times.

(2) When furniture paint comes into play, nail holes and paint.

(3) Processing corners, laying floor tiles, solid wood or composite wood floors, waterproof marble strips and skirting lines.

④ Installation and debugging of lamps, switches, sockets, sanitary wares, handles and door locks.

(5) Clean the floor tile joints and evacuate the site.

⑥ Internal preliminary acceptance of decoration company.

⑦ Three parties make an appointment for formal acceptance and deliver it to the owner.

2. General process and work type of construction

(1) Step one, go through the admission procedures. Generally speaking, the check-in formalities need the original and photocopy of the ID card of the person in charge of the decoration team, the original and photocopy of the owner's ID card, the copy of the business license of the decoration company, the copy of the construction permit of the decoration company and the decoration deposit. Of course, you need to specifically ask the owner's housing management office before going through the formalities.

(2) The next step is to knock on the wall. The calculation of knocking area can be based on the floor plan of the house, which has various detailed data about the house. Remember to measure the area to be knocked on the wall before knocking on the wall. You should know that knocking on the wall is based on the area.

(3) After knocking on the wall, clean up the garbage, and Plaster workers comes into play. Masons are mainly responsible for building walls, painting, sporadic repair, tiling, waterproofing, leveling the ground and installing floor drains. Cement mortar is used for wall building and plastering, and the difference is only in different proportions. Bricklaying and plastering are the preliminary work of plasterers. After finishing these two items, the mason's union will first measure the actual area of bricklaying and plastering, and then he will check these dimensions with the owner. In addition, it is best to tile a room by one person. If two people do it, the effect may be different because of different styles.

(4) After the wall is built in Plaster workers and before plastering, the plumber will enter the site for hydropower transformation at the same time. The main work of hydropower transformation includes hydropower positioning, slotting, pipe burying and threading.

① The first step of hydropower transformation is hydropower positioning, that is, the position of switch socket and waterway interface in the whole house is determined according to the user's needs, and the plumber should explain the line direction to the user according to the position of switch, socket and faucet.

(2) After hydropower positioning, the next step is slotting. The grooves made by a good grooving master are basically straight lines, and the edges of the grooves are basically hairless. Note that before slotting, be sure to ask the plumber to mark all the hydropower trends on the wall, and remember to compare them with the hydropower map to see if they are consistent.

(3) When the waterway is rebuilt, pay attention to the cleanliness around it. When signing a waterway reconstruction contract, it is best to indicate the materials used for waterway reconstruction. In addition, attention should be paid to the size of the sewer pipe in the original room during waterway reconstruction, and the pipe connected with the sewer pipe should preferably match the original sewer pipe.

(4) During the circuit transformation, pay attention to where the lamps and electrical appliances in the whole house are installed in advance to determine the position of the switch socket. At the same time, it should be noted that the price of new buried wires is different from that of replacement wires. You'd better buy a wireless doorbell.

Finally, it should be noted that it is best to indicate in the contract that carpenters must enter the site after the completion of hydropower transformation. The advantage of this is that users don't have to pay attention to two things at the same time. Hydropower transformation is a very important work in decoration, and it is also a large part of the profit of decoration company. Moreover, the hydropower transformation is very hidden. If carpenters enter the site at the same time, it will distract your attention and you can't concentrate on the hydropower transformation.

(5) After the hydropower transformation is completed, carpenters will enter the site, and attention should be paid to:

When you get the designer's drawings, you'd better check the dimensions carefully before signing.

(2) Carpenters should bring their own tools, such as tool boxes, work tables and air compressors. In particular, the workbench must not be made of wood bought by users by decoration workers. Be sure to make it clear to the foreman of the decoration company or the decoration team before the decoration.

(3) Before the carpentry comes into play, the plates shall go first. Take a closer look at whether the board entering the site is in line with the contract and whether it is genuine. Remember to let termite companies prevent termites when decorating some places in the south.

Like the plumber, carpentry is also a big source of profit for the decoration team and a big source of formaldehyde in the decoration. To control this, we should not only comply with the national environmental protection regulations, but also choose the wood paint used.

(6) The painter shall enter the site to approve putty after the dry ash wall is approved in Plaster workers, that is, the first stage painting mentioned in the attached table. If there is a plaster line, it will be installed at this time. It is the painter's business to install plaster lines.

If the decoration is painted with a primer and two topcoats, then the wall must be polished three times. The first grinding is to grind the dry wall with sandpaper after the putty is approved and before brushing the primer for the first time; The second grinding is before the primer is applied and the top coat is thoroughly applied. At this time, it is better to use sandpaper with higher label than sandpaper polished for the first time. The third time is before painting the top coat for the first time and before painting the top coat for the second time after drying. At this time, the wall must be polished with advanced sandpaper, and only in this way can the brushing effect of the wall be guaranteed. Otherwise, nine times out of ten, your wall will feel like flour after painting.

Another point to mention is the problem of adding water to the paint. There are certain restrictions on the proportion of water added to each coating, so it is necessary to pay attention to the construction in strict accordance with the construction instructions.