Joke Collection Website - Bulletin headlines - Implementation plan of civilized construction management in engineering site?

Implementation plan of civilized construction management in engineering site?

I. Overview

1, project name

2. Project Location: Qiaoxi Village, Yong 'an City

3. Overview of architectural design:

Project scale: the total construction area is 7549.73m2;; There are two floors underground and seven floors above ground. The building height is 23.98 meters, the architectural design level is Grade III, and the building structure is frame structure. The reasonable service life is 50 years, the seismic fortification intensity is level 6, and the building fire resistance rating is level 2.

In order to do a good job in site civilized construction, improve the visibility of enterprises, reflect the management level of enterprises, and thus achieve good social benefits, the company leaders have attached great importance to this project since winning the bid, and devoted themselves to studying and formulating various schemes and measures for site civilized construction while planning various preparatory work. Therefore, the formulation of this implementation plan is the guidance of civilized construction on the project site. Its goal: to strive for a civilized demonstration site in the city.

Second, the civilized construction leading group

In order to better implement this implementation plan, through research, it is decided to set up a civilized construction leading group headed by Liu Ruohai.

1, member of the leading group

2. Division of responsibilities of members

Liu: Be fully responsible for the arrangement and guidance of the whole process of site civilized construction management.

Yang Hai: Responsible for the implementation of the specific contents of the management plan, conducting comprehensive inspections, inspections and organizing appraisal activities.

Chen Yongnan: Responsible for on-site city appearance, environmental sanitation, civilized construction, security, fire control and other work.

Wang Jian: Assist in the appearance of the venue; Responsible for the implementation of the whole process, such as the collection and management of internal data.

Chen Yongnan: Responsible for the implementation of all contents such as division and sub-division.

Li Jie: Responsible for the layout and implementation of the site framework.

Liao Shusheng: Responsible for on-site material stacking, security, fire fighting and material arrangement.

Liao Shusheng: Responsible for machinery management and construction electricity management.

Third, the system

1, according to the standards and terms of Jian Jian [1995] No.407 Trial Measures for Comprehensive Evaluation of Construction Sites and Jian Jian [1996] No.24 Comprehensive Evaluation Form and Description of Construction Sites, manage and sort out the civilized construction materials on site.

2. Formulate the management target reward and punishment system of Yong 'an Hongyu Plastic Products Factory 1# workshop project, the dormitory system of Yong 'an Hongyu Plastic Products Factory 1# workshop project, the open flame management system and the civilized code for construction workers.

Four, targeted for civilized construction management

According to the characteristics of the project, the field capacity, material management, environmental sanitation, comprehensive management, fire protection and other aspects are refined and managed by special personnel.

1, field appearance: strive to create a beautiful, hygienic and comfortable living and working environment. Details are as follows:

(1) In order to facilitate the construction and management, a gate is set in the northeast, the south is the main passage of the future material storage yard and construction operation area, and a reception desk and car washing platform are set in the northeast.

⑵ Separate the material field from life (see the construction layout for details). Brick houses (second floor) for office buildings in the office area and main dormitory buildings in the living area. Office area: the first floor is the manager's office, office, conference reading room, etc. The second floor is the management dormitory. Living quarters: canteen, staff canteen, dormitory, toilet, bathroom, etc. The inside and outside of the toilet and toilet are painted, and an open space is reserved as an activity place for staff to rest. The reception room has two floors: one is for night duty, and the other is the dormitory for security personnel.

(3) Afforest the office area and living area.

(4) Arrange two handymen to be responsible for the sanitation, cleaning and watering of the living quarters, office areas, material areas and main passages.

2. Site signs

(1) Set up construction signs, construction site plan, project team and staffing at the gate.

(2) The office area and living area shall be provided with bulletin boards, blackboard newspapers, safety production management system boards, quality policies, quality objectives and quality commitment boards, etc.

(3) In the living quarters, construction sites, office areas, material stacking areas, construction fences, etc., various safety and quality aphorisms and propaganda slogans are marked and hung.

(4) The office and the project manager's office shall be hung with responsibility cards of all departments, quality policy commitment targets, supervision cards of managers and warning signs of civilized construction management.

3. Site layout

In addition to the layout according to the requirements of field capacity and field appearance in 1, the layout of temporary electricity and water use should be arranged according to the requirements of specifications, and strive to be neat, beautiful and generous.

According to the needs of the project, the temporary erection of the production site and material warehouse must be arranged neatly in addition to meeting the functional requirements.

The implementation plan of civilized construction management on the above-mentioned project site was collected and sorted by Zhong Da Consulting Company.