Joke Collection Website - Bulletin headlines - Enterprise Construction of Gubei Coal Mine
Enterprise Construction of Gubei Coal Mine
Since entering the new century, Huainan Mining Group Company has conscientiously implemented the spirit of the 16th National Congress of the Communist Party of China, implemented the corporate purpose of “all for development, all for employees”, seized the rare opportunity of the country’s strong energy demand, and taken the lead. In one step, it put forward the strategic goal of "building large mines, operating large power plants, and developing capital", and was approved by the National Development and Reform Commission as one of the first batch of 1.3 billion tons of coal bases in the country. Huainan City is close to the Yangtze River Delta region, with obvious location and status advantages. Zhejiang Province, located in the Yangtze River Delta, is also a large economic province with energy shortages. Huainan Mining Group and Zhejiang Energy Group hit it off and established the Gubei Coal Mine of Huainan Coal and Electricity Company. and Fengtai Power Plant, both projects have also been designated as "861" key projects by Anhui Province. As Vice Premier of the State Council Zeng Peiyan said, Huainan Mining Group’s integration of coal and electricity has “driven the small ball towards the big ball”, and the concept of power transmission from Anhui to the East has been confirmed. Against this background, the Gubei Coal Mine came into being. The Mining Group announced the establishment of the Gubei Mine Construction Project Department on February 18, 2004, with an investment of 1.2 billion and a construction period of 28 months. Construction started on March 1, 2005. It was put into operation on July 1, 2007, with an annual output of 6 million tons. This kicked off the large-scale construction of Gubei Mine, and on March 2, 2004, the first batch of coal mine builders who were willing to endure hardships and shoulder heavy responsibilities came to this hot construction site. The environment during the preparation stage for mine construction was difficult. There were no electric lights, no roads, just weeds and wheat fields. The living conditions were extremely poor and we had to endure mosquito bites. But no one complained. We were here to suffer, not to enjoy. of. From project managers to ordinary employees, everyone was crowded together. There was no office space, so they rented a farmhouse, lifted up their bedding and worked on the bed. This was used as both a dormitory and an office, and the intense preliminary preparations began. In the face of temporary difficulties, no one backed down. Everyone was very enthusiastic and energetic. They determined the location of the well in the design, determined the industrial square, and purchased the land. The location of the wellbore was determined on March 5, and the wellbore was inspected and drilled on March 8 to solve the power supply problem. All work was in order. From design to installation, the staff of the project department did everything themselves. Despite the shortage of equipment, few personnel, and blocked roads, they overcame many difficulties and completed a 3.5-kilometer 35kv double-circuit overhead power supply line and a 3.5kv temporary transformer within 2 months. The power station will deliver electricity 10 days in advance. Many comrades did not take a break from work for several weeks. Some comrades went to Huainan for business and passed through their homes many times without returning. It was the hard work of these comrades that Gubei Mine quickly completed a number of mine construction projects in a relatively short period of time. They had only one purpose in preparing for the work, which was to complete the Gubei Mine as soon as possible. Every step forward in the construction of Gubei Mine is inseparable from the care and guidance of leaders at all levels. Since the establishment of the project department in February 2004, provincial, municipal and group company leaders have always paid attention to the progress of Gubei mine construction and learned about Gubei through various channels. The local government and various departments of the group company also provide a lot of support and actively provide guidance and solve problems encountered in the mine construction. Duan Zhiji, Director of the National Development Bank, Zhu Ming, President of the Provincial Development Bank, Zhu Jili, Mayor of Huainan City, and other relevant provincial, municipal, and county leaders visited the Gubei mine construction site to visit and express condolences to the participants, understand the construction situation, and solve problems on site. related issues. Group company chairman and party secretary Wang Yuan, vice chairman and general manager Kong Xiangxi and other group company leaders came to Gubei construction site many times to inspect the work, and discussed how to control the "three major controls", speed up the mine construction, and design drawings , Project bidding and put forward guiding opinions. For some major construction issues, the leaders of the group company personally organized relevant experts and professors to conduct technical research to provide technical guarantee for Gubei construction. To build a modern mine in the shortest time, scientific and reasonable arrangements and control of the construction period are crucial. Comrade Kang Yanmin, the manager of the project department, often warned the project department staff at meetings: Although many of our comrades here are very experienced in mine construction and have drilled many wells, the speed of well construction in the past is definitely not good. We must break the rules and grasp the situation. We must control the nodes and time of each construction process well, and race against time while strictly controlling quality. The project department carefully studied all aspects of each project, including drawing design, construction plans, and selection of construction teams, and made scientific and reasonable arrangements.
First, the construction plan was optimized, and grouting was carried out after conventional inspection drilling. The insurance factor was large. The main leaders of the project department reviewed the information, and based on the geological structure characteristics of Gubei Mine, relied on rich experience and made decisive decisions, using inspection drilling parallel to grouting. operation, thereby greatly shortening the construction period. Secondly, we created a working atmosphere in the mine, using blackboards, slogans and other forms to promote the working atmosphere. In the hot summer, the project department sent cooling mung beans and watermelons to the construction units. Carrying out small-target labor competitions, evaluating every Monday, cashing in on the spot, and providing clear rewards and punishments. These practices have greatly mobilized the enthusiasm of project construction personnel. For example, in the construction of frozen holes, the #4 wind shaft machine constructed by the Coalfield Geology Team No. 3 once set a national record of a daily single machine well length of 346m; in the end, every construction link was grasped, such as the largest main shaft in Asia weighing 820 tons and 72m high. For the well derrick, in all aspects of design, bidding, foundation construction, derrick fabrication and lifting, the project department focused on construction quality and construction schedule, and completed the installation 10 days ahead of schedule. An important link in mine construction is investment control, in order to ensure the completion of the Gubei Mine with 1.2 billion. The team of the project department unanimously believed that in addition to strengthening internal management and careful budgeting, the focus should be on the project cost. The project department established a bidding leading group with the manager as the leader, and strictly followed the requirements of the group company to invite bids for all projects exceeding 500,000 yuan. Each tender is based on the principle of "openness, justice and fairness" and operates in strict accordance with the procedures required by the tender. In order to prevent private fraud, in addition to the participation of project department personnel, the leaders of the relevant business departments of the group company and the disciplinary committee of the group company are also invited to the tender. , Legal Counsel Office personnel participated to ensure objectivity and impartiality. Since the mine was prepared, tens of millions of yuan have been saved through bidding according to the budget price. Due to the heating up of new mines across the country in recent years, frozen units often bid in conjunction with each other during bidding. Although bidding was invited, the price still could not go down. Under the guidance of the group company leader, the project department took the initiative to interview the frozen units. After many price negotiations, the bids were compared. The price dropped by tens of millions of yuan. By the end of December, the project department had completed an investment of 260 million yuan, including 106 million yuan for mining construction projects, 48 ??million yuan for civil engineering projects, and 18 million yuan for installation projects. The project department has conducted public bidding for 24 projects, with a total amount of 440 million. Safety first, high-quality and efficient construction of mines is the motto of Gubei Constructors. Soon after the establishment of the project department, various safety management systems, safety inspection systems and safety hazard investigation systems were established. A safety production management office was established with full-time personnel. Safety inspections and irregular inspections were carried out every Thursday. The inspection results were In the form of "Four Fixed Tables", each unit was issued a deadline for rectification. Strictly control the preparation, approval, implementation and implementation of construction measures. We conscientiously implement one project, one measure, strictly prohibit unmeasured construction, strictly implement "one well, one system", and intensify the fight against "three violations" and accidents. So far, 118 people with "three violations" have been detected, and safety 467 hidden dangers. At the same time, attention was paid to increasing safety training. In addition to sending some personnel to the group company for training, the project department also organized 5 safety trainings for management personnel totaling 29 people. The project department carefully carries out quality standardization work and formulates and improves various management systems. First, give full play to the role of supervision. During the construction of various mining construction, civil engineering, and electromechanical installation projects, supervisors are required to supervise the entire process to ensure the reliability of quality; second, control quality from the source and inspect all construction materials and materials. The equipment must be strictly submitted for material inspection and must be complete and must be inspected and approved before use; thirdly, the construction process does not relax the requirements due to the progress. During the construction, the construction unit is required to strictly follow the joint review of the owner, supervisor, and construction parties. Carry out construction according to the measure plan and construction measures. At the same time, the monthly acceptance work is carefully organized and organized by the project department, with the participation of various business departments and unified countersigning. The quality qualification rate of the projects that have been accepted so far is 100%. Entering the site on March 2, 2004, the three wellheads were positioned on March 6, drilling started on March 10, the civil engineering project started on April 12, the wind well grouting was carried out on May 24, and the main well was started on July 8 Drilling started during freezing. The main well was frozen on November 1, and the main well derrick was successfully lifted on December 10. On January 11, 2005, the ground was broken for the lock entrance of the wind shaft. In this short period of 11 months, through the joint efforts of all the staff of the project department, the mine construction has begun to take shape.
In terms of civil construction: the district team office building, compressor room, boiler room, mixing station, material warehouse, machine repair workshop have been basically completed, 1#~5# single dormitory building, Kegan apartment building, comprehensive mining equipment warehouse, industry-wide joint Construction has started, and the main roads in the mine have been repaired; in terms of mechanical and electrical installation projects: the main and auxiliary shaft derricks are standing tall, and the compressors and boilers are in normal operation; in terms of mine construction: three wells have been drilled for freezing holes 180,000 meters has been fully completed and has begun to freeze. Among them, the main and wind shafts are ready for excavation. Today, the farmland at that time no longer exists, water, electricity, gas, communications, roads and other systems have been initially formed. All staff have moved into the spacious and bright district team office building, and living conditions have been greatly improved. What you see are tall buildings and majestic derricks, what you hear is the sound of roaring machines, and what you feel is a scene of intense work. All preparatory work is now in place before the start of construction, achieving the goal of starting construction more than one month in advance. Although the initial battle was successful, it was only a good start, and the tasks ahead were still very heavy. We will continue to keep a clear head, conscientiously implement the spirit of the "Two Sessions" of the group company, and actively strive for strong support from local governments and relevant departments. Rely on technological progress and update management concepts. In accordance with the requirements of the Scientific Outlook on Development, we will strive to achieve the "three major controls" of construction period, quality and investment with the greatest determination and the most powerful means. Use full enthusiasm, high morale and fighting spirit to build a green, environmentally friendly and modern mine.
- Previous article:Toast at the housewarming banquet
- Next article:Who can briefly talk about the plot of Kung Fu Dream in Jackie Chan's martial arts films?
- Related articles
- How to quickly and effectively remove acne?
- The slogan that people turn off the lights while walking.
- Spring forest fire prevention promotion banner
- Practical | @ Teachers, students and parents, here are some safety tips for preventing drowning during the summer!
- What are the specialties of Yancheng?
- The class is carrying out an activity with the theme of "Learning from Lei Feng's Good Example". Please participate and complete the small questions. (8 points) Question 1: ①March 5, in order to prom
- Ask for an elective course, a paper on automobile enterprise culture, about 3 pages of stationery.
- Luoning Shangge Apple Festival Address
- Sports cheering sentences for senior high school entrance examination
- A complete collection of slogans for cycling activities