Joke Collection Website - Bulletin headlines - Seek the emergency plan for bridge demolition safety?

Seek the emergency plan for bridge demolition safety?

8. Safety measures

8. 1 safety control mechanism

8.2 Safety management personnel configuration

Project intends to set up a safety production department, equipped with 1-3 full-time security officers responsible for daily safety management. Each production team shall have a part-time safety officer, and the team leader shall be a part-time safety officer.

8.3 Safety measures

8.3. 1 Safety production guarantee measures

The safe production of demolition project has always been a decisive factor restricting the construction period and the success of demolition. In order to do a good job in production safety in the process of bridge demolition, after carefully consulting the original bridge design drawings, listening to the opinions of the owners and supervisors, according to the engineering characteristics, environmental conditions, machinery and equipment invested, and in accordance with the requirements of the laws, regulations and rules of the state, local governments and our company on production safety, the safety production guarantee measures for bridge demolition projects are formulated.

(1) safety management plan measures

The project manager is the main first responsible person for the construction safety of this project, and carries out the responsibilities of each post.

Improve and implement safety rules and regulations, such as: high-altitude safety operation procedures, machinery safety operation procedures, safe power consumption system, lifting operation safety system, etc. Complete necessary labor protection articles, such as safety helmet and life jacket. All personnel entering the construction site must wear safety protection articles according to regulations. Set up safety regulations bulletin boards and safety publicity slogans at eye-catching positions on the construction site.

(2) Safety technical guarantee measures

① All temporary structures shall be designed in detail and the data shall be filed.

(2) When the wind is too strong to ensure safety, the operation should be stopped.

(3) Night operation should have sufficient lighting, electricity and fire fighting to prevent electric shock and fire.

④ Pay close attention to the weather forecast and establish a normal weather forecast receiving system.

⑤ All electrical equipment must be of reliable quality, with reliable leakage protection and grounding devices, and outdoor electrical equipment should have rainproof measures.

⑥ Carry out regular safety inspection, combined with regular inspection, dynamic inspection, special inspection and other inspection forms; In view of the weak links in production safety, we should seriously rectify them.

⑦ The rigger shall operate in strict accordance with the operating rules, and the hoisting machinery, equipment and spreader shall be kept in a division of labor, and the maintenance work shall be done regularly to ensure the safe operation of the supply.

⑧ The hoisting area must be clearly marked, and the main passage should be supervised by special personnel, with safety flags and warning lights.

Pet-name ruby tensioning, it is forbidden to stand opposite the jack, in case of prestressed tendons or anchorage snap pop-up cuts.