Joke Collection Website - Bulletin headlines - Safety technical measures for building and disassembling material platform in office building project?

Safety technical measures for building and disassembling material platform in office building project?

What are the safety technical measures for assembling and disassembling the material platform of the office building project? The following Zhong Da consults the bidding teacher to answer your questions for your reference.

Safety technical measures for loading and unloading platform of office building engineering;

1, erection of metal fastener double-row scaffolding, used in high-rise buildings, should be carried out in strict accordance with the requirements of relevant national special specifications.

2, for general construction projects, should be strictly in accordance with the requirements of the relevant industry laws and regulations of the ministries and agencies.

3. Steel pipes shall be strictly screened before erection, and bars with serious corrosion, thin wall and serious bending and fission shall not be used.

4. Fasteners with serious corrosion, deformation, cracks and bolt thread damage are not allowed to be used.

5, scaffolding foundation in addition to the set by the regulation, drainage treatment must be done.

6. When the high-rise steel pipe scaffold stands on the channel steel, it must be connected and protected by a sweeping rod, and the common scaffold pole must be protected by a base.

7. Socket-type steel pipes should not be used for the vertical rods staggered at the bottom.

8. The tightening torque of all fasteners should reach 45-55 N.m.

9, the same facade putlog, should be staggered, at the same time, the vertical rod straight up and down.

10, diagonal extension, butt fastener is not suitable. Lapping shall be adopted, and the spacing between two fasteners extending from two rotating fasteners shall be not less than 0.4m.

1 1. Lead wire climbing frame is not suitable for the pull rod of metal scaffolding in high-rise buildings, and rigid materials in the form of embedded parts must be used.

12. A warning zone must be set up at the demolition site, and eye-catching warning signs should be hung. Non-operators are prohibited from passing through the warning zone or continuing construction under scaffolding. Ground monitoring personnel must perform their duties. High-rise building scaffolding demolition should be equipped with good communication tools.

13, carefully check whether the hoisting machinery (including rigging) is safe and reliable. Lifting machinery is not allowed to be erected on scaffolding, and should be set up separately.

14, in case of strong wind, rain, snow and other special climate, scaffolding shall not be removed.

15, demolition work at night, should have good lighting equipment.

16, the workers working at heights in the hospital should strictly abide by the regulations on working at heights, observe the safety discipline, and comply with the requirements of the demolition process and scheme.

17. All windows in the building must be closed and locked, and it is not allowed to open or pick out objects.

18. After the demolition personnel enter the post, they should check first, reinforce the loose parts, and remove the materials, objects and garbage left by the Taiwan class. All cleaning materials should be safely transported to the ground, and it is forbidden to throw them from a height.

19. Demolition shall be carried out according to the reverse procedure of erection, that is, safety net → vertical retaining basketry → cushion laying basketry → protective railing → joist → diagonal tie rod → even wall pole → main rail → small rail → vertical pole.

20, are not allowed to separate surface demolition or two steps up and down at the same time (step). Do a good job step by step, one stroke at a time.

2 1, all wall parts, diagonal tie rods, row separation measures and climbing measures must be lowered synchronously with the removal of scaffold steps. It is not allowed to open it first.

22. When all bars and fasteners are dismantled, they should be carried out separately. Fasteners are not allowed to be attached to the bar conveying ground, or two bars are dismantled at the same time.

23, all mat shop basketry dismantled, should be erected from outside to inside, handling, prevent from inside to outside after turning up, basketry surface garbage objects directly fall from a height.

24, scaffolding must use welding gas cutting process, should be carried out in strict accordance with the requirements of the national special type of work and fire laws and regulations. Full-time staff, equipped with hopper (barrel), to prevent sparks and chips from splashing down. It is forbidden to use cutting tools without a license.

25, after the completion of the day, should carefully check the situation around the post, if found hidden parts, should be timely repair or continue to complete to the end of a program, a part, can leave the post.

26. All the bars, fasteners and other objects transported to the ground should be classified and piled up.