Joke Collection Website - Bulletin headlines - How to fill in the safety information of the daily dangerous operation bulletin board in the construction site? Need to have actual content.

How to fill in the safety information of the daily dangerous operation bulletin board in the construction site? Need to have actual content.

Daily bulletin board for hazardous operations

(Detailed Rules for Implementation)

Offices (branches) and projects under construction:

1. Each project department under construction must set up a "daily bulletin board for dangerous operations" and arrange it in a conspicuous position in the main entrance and exit passages and front-line operators.

Second, the contents of this card must be published daily, and the written materials should be filed as one of the contents of the safety account.

Third, the specific content:

① "Project Manager" refers to the person in charge of the on-site project department and must be signed by himself.

② "Safety Officer" refers to the full-time safety management personnel on site, and must be signed by himself.

③ "Today's operation arrangement (hazard source)" refers to the operation contents arranged by the construction team on that day. Such as: trench excavation, bridge slab hoisting, bored piles, etc.

(4) "Touching hazards (points) and adverse environmental factors" mainly refers to whether there is a source of accidents in the work of the construction team that day, including whether there are important energy and harmful substances, whether there are unsafe conditions of objects or unsafe behaviors of people.

For example: sewer construction

Hazard source: (1) When the groove depth exceeds 5m, there is no special safety construction scheme. (2) The driving depth of steel sheet pile is insufficient and the support is not firm. (3) The ditches are not piled with soil as required. (4) The operator should work within the working radius of the excavator. (5) insufficient lighting for construction at night.

Adverse environmental factors: (1) There are toxic gases in the unpacking head. (2) Sewage discharge. (3) Excavator noise, etc.

⑤ "Hazard analysis" refers to the quantitative evaluation method of risk when working in a potentially dangerous environment. Generally, the degree of danger is divided into five levels, among which extreme danger (unable to continue operation), high danger (requiring immediate rectification), obvious danger (requiring rectification), general danger (requiring attention) and slight danger are acceptable.

⑥ "Take control measures" mainly refers to the following aspects:

(1) Take engineering measures to limit risks.

(2) Work instructions and safety disclosure documents shall be formulated.

(3) Training and education.

(4) Make emergency rescue plan.

(5) Supervision and inspection by the on-site guardian.

⑦ "Number of workers" refers to the total number of all personnel involved in the construction of this dangerous source.

⑧ "On-site guardian" refers to the group leader who is responsible for today's work arrangement and must sign it himself.

Pet-name ruby "stuffer" refers to the full-time safety management personnel on the construction site.

IV. The Daily Bulletin Board for Hazardous Operations shall be implemented as of the date of promulgation. If it is not implemented, each project department will be fined 2000 yuan, and the subordinate office (branch) will be fined 200 yuan.