How much does it cost to build a commercial concrete station?

Under normal circumstances, the capital required to invest in the construction of a commercial mixing station is about 3 million-10/00000. The cost of building a mixing station consists of land cost, workers' wages, equipment cost, material cost and daily expenses.

Taking the construction of a HZS60 concrete mixing station as an example, js 1000( 1 (square 1) forced concrete mixer, PLD 1600 concrete dosing machine (linear dosing machine), 9-meter spiral conveying, and a set of water, cement, fly ash and additives are used for weighing.

Extended data

1, type of commercial mixing station. If we want to build a large-scale commercial mixing station, we need more equipment, personnel and other factors. Small-scale commercial mixing stations have low cost and low risk, but the rate of return is relatively low.

2. Equipment cost of commodity mixing station. To build a commercial mixing station, besides the concrete production line, it also needs transportation equipment, substation equipment and experimental equipment. For example, a set of concrete mixing station HZS 120 costs about 900,000, substation equipment is about 200,000, experimental equipment needs about 6,543,800+million, and a large concrete transporter costs hundreds of thousands.