Section 1: Closed management

1. Eye-catching and beautiful artistic fonts are written outside the fence, including: project name, construction unit, design unit, construction unit, quality supervision unit, safety and civilized construction supervision unit, and contact telephone number of construction permit number (brand).

2, the construction site access installation firm, solemn, beautiful door, door leaf airtight type.

3. Before the commencement of construction, the construction site shall be surveyed together with the construction unit, and corresponding protective measures shall be formulated for the surrounding municipal facilities, pipelines, buildings and structures that may be damaged in the construction area to ensure the construction safety.

general layout in the second quarter

1. The entrances and exits of the construction site and the main roads shall be hard-surfaced, with a thickness of 15 thick c25 concrete poured in the traffic part of the site and a pavement width of 4m; The rest of the stone powder layer is 1 thick, to ensure that there is no water in the construction site and smooth access, and set up corresponding safety protection facilities and safety signs.

2. The drainage culvert of the whole construction site must be unblocked, and there is no water accumulation, temporary water supply pipeline dripping and long running water. The construction sewage, mud and domestic sewage can only be drained into the urban drainage pipe network or river after being cleaned by a sedimentation tank.

3. Engineering signs (five signs and one map) must be set up on the construction site, namely: Engineering Overview Card, Civilized Construction Management Card, Organization Network Card, Safety Discipline Card, Fire Prevention Notice Card and Construction General Layout Plan. Five cards and one drawing adopt uniform specifications, with white characters on a blue background, which are uniformly customized by the company's security department. Each project department should set up a rain-proof publicity column in an obvious position within the gate of the construction site for posting five cards, one map and publicity content of safe and civilized construction.

4. Temporary buildings, including offices, administrators' dormitories (workers' dormitories are set up about 8 square meters off-site), canteens, warehouses, bathrooms, shower rooms and fire pools, etc., shall be set up in strict accordance with the location specified in the construction organization design. It is required to be stable, safe, clean and meet the fire control requirements. It is strictly forbidden to use bamboo shed, asbestos tile and linoleum.

5. The stacking positions of various materials, finished products, semi-finished products and mechanical equipment should be consistent with the construction plan.

6. The sand and gravel in the site should be classified and stacked with bricklaying barriers. Other pipes, templates and red brick bulk materials should be classified and stacked.

7. Steel products shall be neatly stacked according to specifications, and product identification plates shall be hung. Processed semi-finished products should be hung with identification cards in different categories and put on the shelf.

8, mixer, mortar machine, hoist and other machines and tools must build a solid protective shed for operation, and the machines and tools after use every day should be cleaned. At the same time, the ground around the machine should be hardened. Construction machine operators and special operators must hold valid operation certificates.

office and living facilities in the third quarter

1. There must be strict isolation measures between the construction work area and the living area, and steel pipes can be used as isolation barriers. Its height is not less than 2 meters, a green dense mesh safety net is hung on the guardrail, and the steel pipe is painted with yellow and black intervals. And hang up civilized construction placards or civilized construction rules and regulations, and there should be eye-catching safety warning signs in dangerous areas, and warning red lights should be set for night operations.

2. Container dormitories must be built firmly and have good moisture-proof, ventilation and lighting performance. The per capita area is not less than 2 square meters, the clear height of the room is not less than 3 meters, and the depth is not less than 5 meters. The bed should be a two-layer painted steel bed with a length of 2 meters and a width of 1 meter. The first bed is .5 meters from the ground, and the second bed is 1 meter away from the first bed, and each room shall not exceed 2 people. The dormitory shall be designed and erected according to the electricity consumption standards, and it is strictly forbidden to connect wires at will. It is strictly forbidden to use electric stoves, rice cookers and other appliances and cook food with open flame.

3. The site office must be hung with corresponding post responsibility system and supporting charts, tables and chairs, office supplies should be placed in an orderly manner, the environment should be kept clean, and electric water heaters and tea sets should be set up.

4. Flushing toilets for men and women should be set up on the construction site, and simple septic tanks or septic tanks should be set up, stamped and sprayed regularly. The ratio of squatting position to people is 1:2-25, and the brick is pasted. The toilet wall is plastered and whitewashed, and a special person is responsible for cleaning and disinfection every day to prevent mosquitoes and flies.

5. A shower room should be set up at the construction site, with the ratio of nozzles to tiles of 1: 2. There should be drainage and exhaust facilities in the room, waterproof boat heads, waterproof switches and leakage protection devices for lighting, and designated persons should be responsible for maintaining hygiene.

6. The internal and external walls and ceilings of the canteen should be whitewashed, the ground should be plastered with cement or paved with floor tiles, screen doors and screens should be installed, and facilities such as ventilation, exhaust and sewage drainage should be installed. The countertop of the stove must be tiled.

fire prevention on site in the fourth quarter

1. The fire control management system must be formulated on the construction site, and the person in charge of fire control management must be clearly defined, fire control safety activities and fire control safety knowledge publicity and education should be carried out, compulsory firefighters should be trained, fire equipment should be equipped according to regulations, and fire control files should be established.

2. Eye-catching fire safety slogans and signs should be hung on the construction site, and the fire operation area should be clearly divided. The distance between the fire operation area and the projects under construction and other temporary building facilities shall not be less than 2m, the distance between the acetylene generator and all open flames shall not be less than 1m, and the distance between the acetylene generator and the oxygen cylinder shall not be less than 5m.

3. In flammable places such as offices, container dormitories, carpentry sheds, kitchens, warehouses, etc., two or more hanging fire extinguishers should be set up respectively, and the extinguishing agent should be replaced regularly according to the instructions, and a fire-fighting pool and a fire-fighting sand pool should be equipped at the same time.

4. All projects that may generate fire sources on the construction site must be carefully cleaned up after the operation, so as to prevent fire hazards.

Section 5 Health Management

1. Define the responsible persons of health in each area of the construction site, formulate the health management system, set up enough garbage pools and trash cans, do a good job in environmental sanitation regularly, clean up the garbage and apply pesticides; Four pests, there must be no odor and toxic gas on the construction site.

2. Brick slag and lime sand sundries on the operation surface and floor must be cleared after work. Construction waste on each floor must be transported to the specified place in bags for unloading. It is forbidden to throw construction waste down from a height. Construction waste should be piled up and removed in a fence.

4. Transport vehicles must be washed before they can leave the site and drive on the road.

5. Vehicles carrying building materials, earthwork, construction waste and engineering muck should take effective measures to ensure that they will not pollute roads and the environment during driving. Strictly implement the "Several Provisions on Strengthening the Management of Earthwork Transport Vehicles in Shenzhen Special Zone" (Shenzhen Jian Zi [1997] No.185).

6. The daily necessities in the dormitory should be placed in order, clothes and bedding should be folded neatly, shoes should be placed well, clothesline racks should be installed outdoors, and clothes should not be aired indoors.

7, formulate dormitory health duty management system. Clean the dormitory every day and keep it clean inside and outside

8. The canteen on the construction site must apply for a hygiene license (go to the municipal health and epidemic prevention station) and meet the hygiene standards. Cooks should wear white work clothes (hats) and maintain personal hygiene. Cookers and tea workers should have a health check once a year and hold valid health certificates.

9, the canteen cooking should be clean and hygienic, food storage cabinets (boxes) and vegetable rice should be cooked separately and marked. Cooked food operation should have a fly-proof room or a fly-proof cover. It is forbidden to use non-edible plastic products as cooked food containers.

1. According to the number of diners, the site should provide dining places and simple dining tables that meet sanitary conditions. At the same time, there is a special insulated drinking bucket. It is strictly forbidden to litter waste and leftover meals.

11. Tea kiosks and buckets should be set up at the construction site, which should be covered and locked. The water cups used by * * * should be disinfected at any time, and summer construction should have heatstroke prevention and cooling measures.

12, the construction site should be equipped with medical order health care medicine box, commonly used trauma and life medicine should be complete.

Section VI Dust and Noise Management

1. There must be no flying dust in the construction site. For the hard parts that have not been done due to other reasons, the ground should be compacted and watered regularly to reduce the pollution of dust to the surrounding environment.

2. It is forbidden to burn toxic, harmful and foul-smelling substances on the construction site.

3. When loading and unloading materials with dust, they should be wetted with water and carried out in the warehouse.

4. When the noise of construction operation in the urban area may exceed the noise limit of the construction site, the construction project department shall report to the construction administrative department and the environmental protection department before the construction starts, and the construction can only be started after approval.

5. In the urban area, it is forbidden to carry out noisy construction work at noon and at night (from 12 noon to 2 pm, from 11 pm to 7 am the next day). Due to technical reasons that the construction cannot be interrupted and other special circumstances, if it is really necessary to continue the construction operation at noon or at night, an application should be made to the construction administrative department and the environmental protection department.

Section 7 Public Security Management

1. The construction site must establish and improve the safety and security system, and carry out those responsible for public security, fire prevention and family planning.

2. The doorman and full-time security guards must be set up on duty at the site, and a visiting registration system should be established. Family members and outsiders are not allowed to stay overnight.

3. Strictly entertain Shenzhen's regulations on labor and employment, and migrant workers must hold it when they enter the venue; Four syndromes; (that is, birth certificate, temporary residence permit, employment certificate, employment certificate) The project completes the formalities of labor contract for deleting the flower name and visa.

4. Managers and operators on the construction site must wear work cards. Work cards are uniformly customized by the company's security department. The work cards have company name, company logo, personal photo, name, position or type of work, and the work cards of managers and operators are color-differentiated.

5. Managers and workers on the construction site must wear safety helmets made by the company's security department according to the standard requirements and equipped with the company name logo.

6. The project manager should educate all personnel on the construction site about civilized construction, and educate the contents of civilized construction at the same time of safety technical disclosure, and have special records.

7. The project manager must organize all the staff of this project (migrant workers should seriously study the knowledge of relevant laws and regulations, enhance the concept of the legal system, and must not make trouble or fight. It is strictly forbidden to engage in illegal activities such as pornography, gambling and drugs on the spot, and put an end to criminal offences and violations of law and discipline.

8, the construction project department should take the initiative to build good relations with the relevant community units around the site, actively carry out * * * activities to build civilization, play the role of a window of civilization, and establish a good image of construction enterprises.

9. The project department should, according to the actual conditions, set up entertainment rooms as far as possible, and set up facilities such as newspapers, magazines, radio and television for study, rest and entertainment activities, so as to create a healthy and civilized cultural environment for the production of grass-roots enterprises.

various safety and security systems in section 8

I. Safety education and training system

In order to ensure safety in production and make employees familiar with and consciously abide by various articles of association in safety production, the following systems are specially formulated:

1. Any worker who newly absorbs or changes jobs must receive safety education before taking up his post, and only after passing the examination can he enter the post for operation.

2. Workers with special types of work should attend the training courses run by the competent department, and hold relevant certificates after passing the examination.

3. According to the safety contract, the theoretical assessment of safety technical knowledge should be conducted once a year, and the assessment results file should be established.

4. The main contents of safety education are as follows:

(1) To implement the principles, policies, decrees and regulations of the Party and the state on safety construction.

(2) safety production management regulations.

(3) Operating procedures for electromechanical and various safety technologies.

(4) Experience, lessons and preventive measures in construction and production dangerous areas and safety work.

(5) Hazards and protection of dust poison.

(6) Implement the three-level safety education system, such as joining the team, on-site education and on-the-job education.

Second, the safety technical disclosure system

1. Before the project starts, the safety technical measures should be carefully disclosed to the employees participating in the construction along with the construction organization design, so that the employees know when and what operations should be taken and explain their importance.

2. Before the start of each single project, the safety technical measures of the single project must be repeatedly explained, and the phenomenon that only the editor knows but the builder doesn't know must be resolutely corrected.

3. The system of safety technical disclosure shall be implemented step by step. Before construction, the technical director shall make disclosure to all employees. When two or more construction teams or types of work cooperate with the construction, the safety disclosure of cross-operation shall be made according to the progress of the project. The team leader shall make safety disclosure to the workers on the construction requirements and working environment every day. When the construction task is issued, the safety technical disclosure card must be filled in.

III. Safety technical measures and safety technical measures plan

1. Safety technical measures:

(1) All operators participating in the construction should be familiar with safety technical regulations and safety operation regulations, that is, technical leaders, and must be familiar with safety technical regulations for construction and installation projects; Workers must strictly abide by the safety technical operating rules of construction safety workers;

(2) Safety technical measures must be taken in the construction organization design (construction scheme) of all projects. For large-scale special projects such as blasting, hoisting, underwater, high-rise scaffolding, temporary construction, demolition and deep pit, a single safety technical scheme must be prepared, otherwise construction is not allowed;

(3) The plane positions of roads, sewers, roads, electrical lines, material stacking and temporary facilities on the construction site should meet the requirements of safety, hygiene and fire prevention, and strengthen management to ensure safe production and civilized construction;

(4) The safety protection devices of various mechanical and electrical equipment should be complete and effective, otherwise they can't be used, and they should be repaired and maintained regularly. When overhauling mechanical and electrical equipment, the safety protection device should be overhauled at the same time;

(5) Scaffolds, tic-tac-toe frames and safety nets must be inspected and accepted by the engineering department's garbage clearance personnel before they can be used. During the use, special personnel should be appointed to maintain them, and timely reinforcement should be made in case of deformation or inclination.

(6) Pits, ditches, wells and all kinds of holes in the site should be filled up or fences, cover plates and drainage ditches should be set up in the site. Temporary command should be set up at intersections where the site is narrow, pedestrians and traffic are frequent; Fences and safety signs should be set up in inflammable and explosive places, around transformers and dangerous places, and red lights should be used for warning at night;

(7) All kinds of safety facilities, equipment, signs, color codes, etc. are not allowed to be dismantled without authorization, and must be approved by the person in charge of the construction site and the safety department;

(8) Implement a step-by-step safety technical disclosure system. Before the start of construction, the technical director will make disclosure to all employees. When two or more construction teams or types of work cooperate with the construction, the safety disclosure of cross-operation should be carried out according to the project, and the team leader should make disclosure to the workers on the construction requirements and the safety of the working environment every day;

(9) Concrete mixing stations, asphalt processing plants (sites), quarries and painting workplaces should all take measures to reduce the concentration of dust and poison, so as to reach the prescribed standards;

(1) The innovative achievements of various safety technologies and industrial hygiene must be tested, appraised and corresponding measures formulated before they can be used;

(11) Use personal protective equipment correctly. Anyone entering the construction area must wear a safety helmet, hang up a safety belt when working at heights, etc. It is forbidden to wear slippers, high heels or enter the construction site barefoot.

(12) The construction unit that does not have safety conditions shall not contract out the project, and the general contractor shall strengthen the safety management of subcontractors and organize and manage the safety production on site in a unified way;

(13) The operation of construction machinery shall be carried out by special personnel, and the operating procedures and operator listing system shall be implemented;

(14) Construction site, wood processing plant (workshop) and warehouse for storing explosive equipment. It is necessary to establish a fire prevention management system, prepare sufficient fire prevention facilities and fire extinguishing equipment, and check them regularly to keep them in good condition.