Joke Collection Website - Bulletin headlines - I need an article about the safety production system of self-operated and self-operated enterprises

I need an article about the safety production system of self-operated and self-operated enterprises

Safety Production Management System

(Deliberated and approved by the Manager’s Office Meeting on the year, month and day)

Chapter 1 General Provisions

Article 1 The safety management system is a basic work of safety management and an important means to ensure safe production. Macroscopic safety management includes three aspects: labor protection, safety technology and industrial hygiene, which are both interconnected and independent. In order to conscientiously implement the safety production policy of "safety first, prevention first". Safety production must be guaranteed by a strict management system. The safety management system mainly includes the following aspects: safety production responsibility system, safety education system, safety inspection system, and safety statistical reporting system.

Chapter 2 Safety Production Responsibility System

Article 2 The Safety Production Responsibility System is an integral part of the job responsibility system of construction enterprises. Based on the principle of "managing production must manage safety", it responsibilities for the safety of leaders at all levels, functional departments, relevant personnel and production workers during construction.

Article 3 Safety Production Responsibility System of the Engineering Management Department

The main work of this functional department is to supervise, inspect and evaluate safety production work, follow the leadership’s arrangements, and do a good job in all aspects of safety production management work.

Article 4 Safety Production Responsibility System of the Engineering Project Department

The key work of the construction project department must implement the principle of "managing production must manage safety", so as to plan, deploy, and While inspecting, summarizing, and evaluating production, we must also plan, deploy, inspect, summarize, and evaluate safety production work. And designate a dedicated person to take charge among the project management staff. To establish and improve safe production, the production safety officers of the teams and teams will implement the work of safe production at all levels, and there will be dedicated personnel responsible for each level.

(1) Responsibilities for production safety during the construction preparation period:

1. After the construction site is determined, when entering the construction site, overall arrangements must be made for personnel, machinery, and vehicles, " Mixing of passengers and goods is prohibited, and driving under the influence of alcohol is strictly prohibited.

2. Special personnel must be responsible for the transportation of large and important road construction equipment and the handling of precision instruments.

3. After entering the site, attention must be paid to the placement of temporary facilities and equipment. The site should be located above the flood level, not in alluvial fans (ditches), to prevent seasonal floods.

4. For dangerous explosives and oil depots, they must be separated from the personnel station in accordance with regulations, properly kept and distributed according to relevant regulations, and no loss is allowed.

(2) Safety production responsibilities at the start of construction:

1. Strengthen the daily work of the safety technical department and full-time safety personnel, clarify their responsibilities, follow the arrangements of the project leader, and do a good job in safety Production.

2. Establish safe production in the construction team and set up part-time safety officers in the team to assist the team leader in the safety production work of the entire team and cooperate with the management of leaders and full-time safety cadres. The duty team frequently inspects and urges workers to abide by rules and regulations, abide by safe production operation rules and regulations, use labor protection supplies rationally, correct and prevent illegal operations, discover various hidden dangers in a timely manner, and report problems that cannot be solved in a timely manner.

3. Before construction begins, a detailed investigation of the construction site, facilities along the line (optical cables, oil pipelines, etc.), cultural relics, ecological environment, etc. must be carried out, and staff must be reminded frequently during work to avoid accidents. ACCIDENT.

4. Supervise and inspect flammable and explosive chemicals and do a good job in fire protection.

5. To supervise and inspect the use of labor protection supplies and do a good job in safety production, all project department personnel must be mobilized to participate, each responsible for their own responsibilities, and responsible for labor protection, production safety and fire protection.

(3) Responsibilities for production safety during construction:

1. Determine safety management objectives and key points of safety prevention. The project objectives are determined as “four preventions and one creation”. "Eliminate" means: eliminate major employee casualties; eliminate major fire accidents; eliminate major traffic accidents; eliminate floods, fires and other accidents caused by construction. "One creation" means: create a safe and civilized construction section.

The key points of safety precautions are: (1) Ensure the safety of traffic on existing access roads; (2) Prevent material transportation safety accidents; (3) Overturn accidents in lifting equipment and structures of engineering vehicles; (4) Prevent electric shock, Electric shock accidents; (5), prevention of falling accidents from heights; (6), prevention of roadbed collapse accidents.

2. Strengthen safety education for employees. Firmly establish the idea of ??safety first, take safety classes regularly, and insist on weekly safety education activities. Carefully search for potential accident hazards and implement preventive measures to prevent serious injuries and deaths.

3. Implement a level-by-level safety technical disclosure system. The management department will organize relevant personnel to conduct detailed safety technical disclosures. All personnel participating in safety technical disclosures must complete the signature procedures and save the information. Full-time safety officers supervise and inspect the implementation of safety technical measures and keep records.

4. Vigorously promote safety system engineering management and safe construction target management technology, increase investment in construction sites and equipment, and ensure that safe production is based on scientific management, reliable technology, and adequate protective facilities. .

5. Technical Measures for Production Safety

Based on actual engineering conditions, formulate safety measures for the site, construction machinery, pile foundations, earthwork operations, road surface operations, bridge and culvert operations, protective engineering operations, etc.

(1). Construction site safety technical measures

The layout of the construction site complies with safety regulations such as fire prevention, flood prevention, lightning protection and various construction requirements. Production, living and office buildings, warehouses, material storage yards, parking lots, repair yards, etc. at the construction site should be arranged according to the approved general layout plan.

(2). The road on site should be smooth, solid and smooth. Signs in accordance with GB2893-82 "Safety Colors" and GB2893-82 "Safety Signs" should be hung at dangerous locations. Red lights should be placed on potholes where pedestrians pass. As a warning, large safety slogans were set up at the construction site.

(3). Sufficient fire-fighting water sources and fire-fighting facilities should be provided in on-site production and living areas. Fire-fighting equipment should be managed by dedicated personnel and must not be taken or placed indiscriminately.

(4). The fire safety distance of various types of houses, warehouses, warehouses, etc. shall comply with the regulations of the public security department. Inflammable materials shall not be stacked. Smoking is strictly prohibited in wood processing yards, warehouses and other places; on-site Inflammable debris should be cleaned up at any time, and it is strictly prohibited to pile up in or near fire sites.

(5). Temporary power use at the construction site shall be strictly carried out in accordance with the "Technical Specifications for Safety of Temporary Power Use at Construction Sites". It is strictly prohibited to connect lights or other electrical appliances indiscriminately. It is strictly forbidden to use other metal wires instead of fuse wires.

(6) When construction is found to endanger ground buildings or dangerous goods or cultural relics, construction should be stopped immediately and construction can only begin after the treatment is completed.

6. Safety control measures for construction machinery

(1) Various machinery operators and vehicle drivers must obtain operation certificates, and operations inconsistent with the certificates are not allowed. Machinery, it is not allowed to hand over the operation of mechanical equipment to personnel who do not have the machine operation certificate. Files must be established for mechanical operators and managed by dedicated personnel.

(2). Operators must follow the instructions of this machine and strictly implement the inspection and maintenance system before work, observation during work and inspection and maintenance after work.

(3). The cab or operation should be kept clean. It is strictly prohibited to operate the machinery after drinking, and it is strictly prohibited to operate the machine while sick or overloaded.

(4). When parking mechanical equipment at the construction site, a safe parking location should be selected, and special personnel should be supervised at night.

(5). Fireworks are strictly prohibited when refueling the machine.

(6). Repair, maintenance, adjustment and other operations on operating mechanical equipment are strictly prohibited.

(4) Safety production responsibilities in the stone blasting section during roadbed construction:

Construction shall be carried out in strict accordance with the construction specifications. Conduct a thorough investigation of the blasting area and the surrounding environment (including pipelines and buildings), equip professional blasting personnel and equipment, and arrange safety sentries and safety guards in the blasting area. Pay attention to the blasting area and flying rocks, check people, materials and objects in strong earthquake areas and eliminate blind blasts, and measure the blasting effect.

Keep explosive detonators on the working surface properly and promptly to prevent them from being lost or causing major hidden dangers.

(5) Safety production responsibilities in pavement engineering construction:

Strengthen the safety production management of asphalt mixing, pay attention to fire prevention and life safety when melting asphalt, and equip with sufficient fire-fighting equipment and necessary Labor protection supplies and various equipment are arranged according to on-site regulations to play the role of quick fire protection. And do a good job in ensuring safety for the purpose of production.

(6) Safety production responsibilities during bridge and culvert construction:

1. Pile foundation construction: First, do a good job of flood prevention and rescue work in the river. The main purpose of the river is drainage and flood control. Especially seasonal rivers must be arranged to avoid construction during the flood season. If some pile foundations need to be constructed during the flood season due to special circumstances, regular contact with the local water conservancy department must be maintained. In case of danger, construction equipment and personnel can be evacuated to a safe area in time.

2. Cofferdam piling: The cofferdam design must meet the highest water level of the river and facilitate construction during flood periods. During construction during flood periods, dedicated personnel must be on duty and sufficient emergency supplies must be prepared on site.

3. Pier and abutment construction: When the height exceeds 2 meters, a working platform and protective railings should be installed around it. When workers go up and down the pier. Use dedicated horse paths and avoid crawling along scaffolding.

4. Beam installation: After the single-piece beam is installed in place, people are prohibited from walking on it. After the entire span of the beam is installed, edge protection measures should be taken immediately. Edge protection facilities must not be removed before the formal bridge railings are installed. .

5. During construction of the bridge superstructure, warning signs and barriers should be set up at both ends of the bridge to prevent non-construction vehicles and personnel from entering.

Chapter 3 Safety Education

Article 5 Safety education is the education and training work carried out by construction enterprises to improve the safety technical level of employees and their ability to prevent construction. It is an important task to do a good job in safe production and safety ideological construction in enterprises:

1. The content of safety education:

Ideological and political education, education on labor protection guidelines and policies, and safety technical knowledge Education, education on typical experiences and accident lessons;

2. Form of safety education:

Refers to the three-level education of new workers on construction projects, construction teams, and construction teams after they join the work;

(1) Safety education for special types of work;

(2) Regular safety education;

(3) Safety competitions and safety rewards and punishments.

Chapter 4 Safety Statistical Report

Article 6 Statistical reporting of accidents is necessary to learn lessons from accidents and avoid recurrence of accidents.

The content of the safety statistical report of highway engineering construction enterprises mainly includes monthly reports. At the end of each month, the situation of the whole month is summarized and reported to the superior competent department according to regulations. General accident reports report major accidents within three days after the accident. Report the accident to the competent department within 24 hours by telephone, telegram, or telex, and then submit a supplementary accident report (form). The accident must be timely and accurate, without concealment or fraud.

Chapter 5 Safety Inspection

Article 7 Safety inspection is a regular and prominent inspection activity carried out by the company on the safety during the construction process based on the characteristics of the construction. Inspection content: including construction technology, construction methods, facilities and equipment, rules and regulations, operating behaviors, and ideas. It can be summarized as inspection of ideas, inspection of leadership, inspection of site, inspection of hidden dangers, inspection of system and inspection of management.

It is necessary to continuously discover unsafe factors in construction through various forms of safety production inspections, constantly eliminate unsafe factors, and ensure safe production in project construction.

Chapter 6 Safety Committee

Article 8 The company shall establish a safety committee to organize, lead and supervise the safety production work of the entire company (including branches) and implement safety regulations for each project. The committee is chaired by the relevant leader of the company and consists of a number of committee members. The composition of the committee shall be stipulated separately by the company below.

Article 9 The Safety Committee Office is located in the Engineering Management Department and handles all daily work on production safety.

Chapter 7 Supplementary Provisions

Article 10 The Engineering Management Department is responsible for the interpretation of these regulations.

Article 11 These Measures shall come into effect on the date of promulgation.