1. Summary Report of Flood Control Safety Exercise

When the flood season comes, our coal mine prepares for the rainy season. While doing a good job in flood control in rainy season, we lost no time in organizing this emergency rescue drill, which laid a solid foundation for effectively improving the safety awareness of all employees in our mine and their ability to deal with emergencies, ensured the safety of our mine in flood season, and achieved remarkable results in flood control and disaster relief. The details of this flood control emergency drill are summarized as follows: On June 5438+05, our company predicted that there would be a rainstorm in XX area at noon on the day of coal mine simulation, and the mine flood control headquarters took this opportunity to organize the mine flood control team to conduct a drill of "emergency plan for flood control and emergency rescue".

First, the content of the exercise:

At noon that day, a rainstorm occurred in XX area, which caused the water in the main wellhead, auxiliary inclined shaft and return air shaft of our mine to reach 30mm deep, and the flood was likely to be pumped into the mine, which would directly threaten the safety of underground workers and the safety of the mine.

Second, the purpose of the exercise:

Improve the mine staff's awareness of prevention, plan ahead and take the initiative, so that the rescue team and relevant personnel are familiar with all the contents and safety precautions of the Emergency Plan for Flood Control and Emergency Rescue.

Third, practice steps:

On the same day, the dispatcher on duty immediately reported to the commander-in-chief after receiving the emergency notice from the meteorological department, and the commander-in-chief immediately issued a rescue order and started the emergency plan. The on-site command immediately organized 50 rescue personnel to be divided into five groups, each group 10 people loaded sand in the battlefield near the wellhead with shovels, woven bags, raincoats and rain boots, stacked the packed sandbags at the wellhead, simulated the rapid surge of rainfall, installed two submersible pumps to drain water, and fought hard for one hour.

Four, superior leaders to observe, guide and participate in the drill:

On the morning of June 15 1 1, more than 40 superior leaders came to our company's coal mine to observe and guide the emergency drill for flood control and emergency rescue, and more than 40 people attended the drill 100. After the drill, Director X of the County Safety Supervision Bureau and Director X of the Coal Management Bureau respectively commented on our company's emergency drill for flood control and emergency rescue. While affirming the results of the drill, they also put forward specific deficiencies, which has practical guiding significance for our company's next coal mine flood control and emergency rescue work.

After this "actual combat" drill, we obviously mastered the necessary knowledge of flood control in the whole mine, and educated the underground workers on the safety of flood control and disaster relief, which achieved the expected purpose and achieved good results. Training has improved the ability of our rescue team members and headquarters to prevent and deal with emergencies, and played an important role in testing emergency plans, improving mechanisms, training teams and educating employees. It is of great significance to fully understand the necessity of taking targeted measures through drills to ensure the safety of our company's coal mines in flood season. Through the drill, we can also see that there are some problems that can not be ignored in the personnel organization and program arrangement of our company's coal mine, which need to be further improved and perfected in the next step, and the emergency rescue plan also needs to be further revised and perfected according to the problems found.

2. Summary report of flood control safety exercise

In line with the attitude of being responsible for the project and employees, in accordance with the management policy of "safety first, prevention first, comprehensive treatment", and adhering to the principle of combining emergency and accident prevention, in view of the actual construction environment of the second bid section of the Lanzhou-Zhangjiakou 34th Line Project Department and the recent rainy season in this contract section, all staff, three operation teams, mixing stations and laboratories of our department organized and implemented this flood control drill. The first is to formulate plans and strengthen coordination.

(1) In order to ensure the normal conduct of this flood control and flood fighting drill and complete all flood control and flood fighting drill tasks in an all-round way, our department set up a leading group for flood control and flood fighting drill in Zhaoping, under the general command of Huawei, to scientifically divide the work according to the scope of this drill, clarify the responsibilities and tasks of each functional group, and mobilize before the war, which provided organizational guarantee for the standardized development of this drill.

(2) In order to make this flood control drill meet the requirements of flood control and flood fighting, according to the guiding ideology and target requirements of the drill determined by the superior, combined with the actual situation of the project, and based on this year's flood control plan, the opinions of all participating units were widely absorbed, which created conditions for the orderly development of flood control drills.

(3) In order to ensure the success of this flood control drill, on the afternoon of April xx, xxxx, a meeting of all the personnel of participating units was held at the drill site, and mobilization was carried out before the war. Participants are required to raise awareness, attach great importance to it, concentrate on improving, stick to their posts, earnestly perform their duties, communicate in time, coordinate and cooperate, and do a good job.

Second, the purpose of exercise

In order to effectively defend against catastrophic floods, reduce disaster losses to a certain extent, resume production as soon as possible after the disaster, ensure the construction progress, spend the flood season safely, improve the emergency rescue ability of this project for emergencies, strengthen safety knowledge education, let all employees of all participating units deeply understand flood control knowledge, and improve the quality and ability of employees in flood control and emergency rescue.

Third, the exercise process

At (1) afternoon 15: 00, the second operation team flooded the temporary access road between Taicha 1# tunnel and Taicha 2# tunnel, which hindered the construction and caused great security risks. The person in charge of the site immediately reports to the emergency rescue leading group. After receiving the flood report and knowing the situation in detail, the commander-in-chief decided to start the emergency rescue plan immediately and instructed the emergency rescue office to notify the relevant departments immediately.

(2) In the afternoon 15: 10, the equipment and materials reserve team transported common relief materials such as woven bags and shovels to the site, while the emergency rescue teams rushed to the site to stand by. The commander-in-chief first observed the water situation, determined the scope and degree of danger, clearly requested and briefly explained the safety precautions to the rescuers. On the premise of completely controlling the water potential and ensuring the safety of rescuers, transport the equipment and materials to a safe place for implementation.

(3) In the afternoon 17: 00, under the leadership of the commander-in-chief, the rescue drill was successfully completed, ensuring the construction progress.

Fourth, the drill summary

After the drill, the head of the division organized everyone to summarize the drill activities: the whole activity was well prepared, the personnel were in place quickly and accurately, the responsibilities were clear, the organization and coordination were basically smooth and could meet the requirements, and the division of labor of the rescue team was reasonable and efficient, which achieved the purpose of the drill. It is believed that through this drill, the flood control awareness of the project department has been improved and the foundation for future flood control work has been laid. Rescuers should strengthen daily safety education, legal education and discipline education, so as to make emergency rescue rapid, accurate and effective, and ensure that the second bid section of the project department of bid section ZQ2 of Lanzhou-Zhangjiakou Line can complete the project construction safely, with high quality and high efficiency.

Problems in verb (abbreviation of verb) exercise

Because some comrades participated in flood control drills for the first time, they didn't know enough about the importance of effective cooperation of rescue teams, and sometimes there was a phenomenon of fighting in isolation, and coordination was not enough. A few employees are not serious enough, slow-moving, lax in discipline and not serious enough.

Follow-up work arrangement of intransitive verbs

Each operation team, laboratory and mixing station will improve the above shortcomings in future work and emergency activities, and further strengthen the training and publicity of flood control and emergency rescue work. Enhance the feasibility of emergency rescue plan for flood control. Ensure the timely arrival of rescue teams in future emergencies, and how to ensure the safety of personnel and materials in disaster relief during the rescue process. In order to improve the emergency handling ability of xxx Electric Power Co., Ltd. in the case of flood disaster and ensure the safety of personnel and property to the greatest extent, the office and power supply department of XXX Company organized emergency drills for flood control.

Flood control emergency drill is divided into two parts. The first part is the water retaining and drainage drill of the company's yard and office building, and the second part is the emergency repair drill of power users under flood conditions. Before the exercise, the company set up a leading group for exercise activities, made a careful exercise plan and prepared corresponding emergency exercise materials.

After the drill commander announced the official start of the drill, the company office received the rainstorm weather warning information, which was reported and conveyed in the order specified in the emergency plan. Commanders of all departments immediately put in place to carry out flood control emergency work, and took sealing measures for the exit on the first floor of the office building and the floor drain of the bathroom to drain the accumulated water in the hospital. At the same time, the flood control and rescue site personnel will report the situation to the flood control headquarters at any time.

In the afternoon 13: 00, the computer of the power dispatching center simulated the alarm, and the 2D22 accident was interrupted. The dispatcher immediately reported the accident information, and sent peripheral personnel to find the fault point in two ways. After overcoming the difficulties such as road water accumulation and vehicle failure, the peripheral personnel found that the cause of the accident was a box-type substation with low terrain at 13: 30, and the incoming cable connector was flooded, resulting in a short circuit. The dispatcher immediately directed the peripheral personnel to operate the ring network cabinet, and resumed power supply to other users at 13: 35, and the exercise ended successfully.

15: 00, Gao, general manager of the company and commander-in-chief of flood control headquarters, presided over the drill summary meeting.

At the meeting, the relevant persons in charge of the office and the power supply department reported the development of the drill work respectively, and put forward suggestions for further improvement, such as: rescuers should go through the formalities of entering and leaving the warehouse when receiving relief materials; Make use of mass short messages to ensure that flood warning is communicated in place; Statistics should be made on the road sections that are prone to water accumulation in the bonded area to find the driving route of emergency vehicles. Gao, the general manager of the company, stressed that after receiving the flood warning, the cadres on duty must stick to their posts, preferring to be a broken stone rather than a full one. In the emergency response, everyone should carry out their work according to the requirements of the plan, perform their duties and responsibilities.

3. Summary report of flood control safety exercise

With the approach of flood season, Tang Ye Hydropower Station decided to hold a flood control exercise to protect Tang Ye Hydropower Station from accidents, and formulated an outline of the exercise, which laid a solid foundation for carrying out this flood control exercise. On May 8th, a vigorous flood control emergency drill was held in Tang Ye Hydropower Station. The main progress of the rig is summarized as follows: 1. Set up a leading group and define the post.

In order to ensure the normal operation of this flood control drill and complete all flood control drill tasks assigned by the company's leaders, according to the drill outline of this project and the notice requirements for doing well the flood control drill, a flood control drill leading group headed by stationmaster Yu was established, with four functional groups. According to the scope of this exercise, the responsibilities and tasks of each functional group were scientifically divided, and the study and explanation before the exercise were carried out, which provided organizational guarantee for the standardized development of this exercise.

Second, all functional groups stick to their posts and do their due diligence to ensure the normal conduct of flood control drills.

Since the flood control drill came to the rolling gate of the workshop at the drill site, all the drill personnel have arrived at their posts, and the responsibilities have been assigned to groups, with a scientific division of labor and clear responsibilities. The distribution of work responsibilities of each functional group played a central role in the drill and played a decisive role in the successful conclusion of this flood control drill.

Third, some gains from flood control exercises.

1, which improved the understanding of flood control exercises of Tang Ye Hydropower Station. Through study drills and flood control drills, and through actual participation, we have a deeper understanding that the operation and flood control of Tang Ye Hydropower Station are a whole.

We have tested our flood control plan and emergency rescue plan. The idea of this flood control drill is not very comprehensive. Therefore, the operability of our flood control plan, the accuracy and standardization of command and decision-making, the flexibility of flood control dispatching and the ability to respond quickly to accidents all pose new challenges.

3. Test the cooperative combat capability between functional groups. Through the coordination of flood prevention work such as flood forecasting, emergency rescue of equipment, communication information and logistics support, the ability of coordinating emergency rescue among functional groups has been improved.

4. Tested our workers, all drillers, stick to their posts, be disciplined and work in an orderly and intense way, showing a high degree of work enthusiasm and professional work quality. It is a working group with positive work, correct attitude and obeying orders.

Fourth, the problems existing in the exercise work

1. Due to the insufficient explanation of this flood control drill, the positions of some personnel are not clear.

2. As some drillers are participating in flood control drills for the first time, they don't know enough about the importance of effective cooperation among functional groups, and sometimes they are fragmented and lack coordination.

4. Summary report of flood control safety exercise

In order to effectively strengthen the flood control work, reduce the impact of flood disasters, and ensure the facilities and personal safety of our project department, the project department organized and carefully planned this year's flood control emergency drill at the construction site of Pushi shield tunnel at 14: 00 according to the requirements of the Emergency Notice of Kunming Metro Construction Management Co., Ltd. on Doing a Good Job in Flood Control and Drainage in the Area Affected by Metro Construction in 20xx. The main progress of this exercise is as follows.

Carefully prepare the 20xx emergency plan for flood control and flood fighting. In order to improve the effect of this drill and implement the specific drill work, prepare the emergency drill plan for flood control according to the requirements of the plan. Combined with the actual situation, according to the scope of the exercise, the scientific division of labor was carried out, the responsibilities and tasks of each functional group were clarified, and the pre-war mobilization was carried out, which provided organizational guarantee for the standardized development of the exercise.

Second, attach great importance to and strengthen leadership.

The project department set up a leading group with Zhang Peng, the manager of the branch, as the chief commander, to strengthen the organization, leadership and management. On the afternoon of June X, organize the project department manager and the main person in charge of the work area to hold a mobilization meeting for flood control drills, and arrange the specific matters of flood control drills in June 13. Employees participating in the drill are required to raise awareness, attach great importance to it, concentrate on their work, fulfill their duties conscientiously, ask for instructions and report in time, and all functional groups should communicate in time, cooperate with each other to do a good job, arrange various preparations, implement rescue tools, clarify the division of tasks, and assign responsibilities to people to ensure safety.

Third, the exercise process

At 1 and 14: 00, a large area of water accumulated around Chunyu Road in Xishan District due to continuous rainstorm, and the drainage equipment of Pushidun well could not meet the pumping capacity. If the water is not blocked or pumped in time, it will have a great impact on the initial support of the wellbore, reduce the initial support capacity, and lead to the convergence or deformation of the initial support of the wellbore. Wu Dawei, director of Pushidun well work area, promptly reported the danger to Zhang Peng, the leader of the branch, and requested emergency rescue. After receiving the report and confirming the danger, Zhang Peng, the leader of the branch, immediately informed the team members to rush to the scene, started the emergency plan for flood control and quickly organized emergency rescue.

2. Yue Zhenmin, the chief engineer of the project, immediately worked out the specific rescue plan and technical implementation of the rescue process according to the flood control emergency plan, and evaluated and analyzed the possible technical problems in the drill.

3. After receiving the emergency rescue instruction, each emergency rescue team immediately rushed to the construction site of shield well in Pushi, and each team entered the state of emergency rescue and disaster relief, and organized emergency rescue work in an orderly manner according to their respective responsibilities.

4. The emergency rescue team built a water retaining wall with sandbags to block the accumulated water around Chunyu Road to prevent the accumulated water from continuing to flood into the construction site; A pump is added to the bottom of the shaft for pumping water. Through the above rescue work, the danger has been effectively controlled. All the drillers rushed to the assembly site, arranged in formation according to the corresponding positions, and the heads of each group counted the number of people. Commander-in-Chief Zhang Peng announced the end of the flood control emergency drill and made a brief comment.

Fourth, the drill gains.

1, which improved the understanding of all personnel in the project department on flood control emergency drills. Through actual participation in this flood control exercise, we have more deeply realized the importance of flood control to personnel safety and company property protection.

2. Test the feasibility of the emergency plan for flood control. Through this drill, new requirements are put forward for the operability and rationality of our various safety emergency plans, the accuracy and standardization of command and decision-making, the flexibility and scientificity of flood control dispatching, and the ability of rapid response to accidents.

3. Test the coordination ability between functional groups. Through the coordination of various flood control work among functional groups, such as danger report, scheme formulation, command and dispatch, flood control organization, engineering emergency rescue, communication information, logistics support, etc. The cooperative combat capability has been improved.

4. It tests all our staff and combatants, sticks to their posts, strictly observes discipline, works nervously and orderly, and shows high political quality and professional work quality.

Verb (abbreviation for verb) The shortcomings of this work.

1, in the face of danger, individual emergency rescue team members are not very serious.

2. The effective cooperation between functional groups is not very tacit, and sometimes there is a phenomenon of fragmentation, and mutual cooperation is not enough.

3. There are still some shortcomings in the preparation of this drill, and the drill procedures can not be very orderly and smoothly connected. In future drills, it is necessary to strengthen training, strengthen the combination of theory and practice, and comprehensively improve and demonstrate the emergency prevention of the project department.

5. Summary report of flood control safety exercise

In order to ensure that this project can reduce casualties and property losses caused by typhoons and frequent rainy seasons, enhance safety awareness, protect the safety of projects, personnel, equipment and facilities, and improve the ability to deal with emergencies, the project department specially carried out this typhoon prevention and flood control emergency drill on June 13. Based on the characteristics of its own construction and site, the project department divides this drill into two stages: one is the on-site disclosure before the drill, and the safety precautions during the drill are disclosed; The second is the actual drill on the spot. Through the combination of theory and practice, this exercise is more deeply rooted in the hearts of the people and the purpose of this exercise is better realized.

On June 13, 14: 00 sharp, the safety and quality department of the project department first made on-site disclosure to all employees participating in the emergency drill in the conference room. In addition to disclosing the division of labor and protective measures of various mechanical entities in the special emergency plan for typhoon prevention and flood control, the link of people falling into the water is also highlighted.

14: 30, the drill commander Guo announced the start of the drill. Immediately, the project manager Guo introduced the typhoon information (see the drill plan for details) and gave the order to stop the field operation. According to the emergency plan, the technical organizer immediately informed the working construction team and informed them to take corresponding measures according to the established plan: the prefabrication team immediately transferred large machinery to protect the molding blocks, templates and machines, and assembled at the gate of the office area after completion. In the process of reinforcement, 1 workers accidentally fell into the water, and other personnel immediately reported to the safety supervision department, which made an emergency response and immediately sent an emergency rescue team to rescue the man overboard. The man overboard was in good condition. 15: 00 and 10: 00, all personnel have completed the specific work of typhoon prevention and assembled at the site of the project department. The counted personnel have returned to their positions, and then Deputy Manager Tian organized orderly boarding and evacuation.

15: 20, project manager Guo announced the end of the exercise. The Safety and Quality Department inspected the emergency measures taken by various construction teams, and the typhoon prevention work in various places met the requirements of the plan. The whole exercise process was tense and orderly, and it was a complete success.

This emergency drill for typhoon prevention and flood control not only enhanced the safety awareness of all employees, but also clarified their respective responsibilities in the plan when the typhoon struck, further improved the ability of all employees to deal with emergencies, and clarified the route of safe production, laying a solid foundation for efficient and orderly work in the future.