Joke Collection Website - Public benefit messages - With this flow chart, you don’t have to worry about starting the renovation!
With this flow chart, you don’t have to worry about starting the renovation!
There is a sequence for doing things, and there is a process for decorating! Only by knowing the specific process of decoration can we have an orderly and overall control. IDEA summarized a decoration flow chart based on the homework done during the decoration process!
OK, the decoration flow chart is here!
▲Decoration flow chart
The above steps are not absolute. Some of the order can be adjusted. There are also some small processes or details, which may not be listed comprehensively, but overall they are Those who are more comprehensive will also follow these major steps.
This picture is already very clear, but in a dedicated and professional manner, IDEA still wants to briefly analyze it.
1. Before the start of the project
There is actually a lot of work to do before the start of the project. IDEA only sorts out the more important ones. Basically three things.
1. Decoration company
Inspect the decoration company (or designer, construction team, etc., the same below), select a satisfactory decoration company, measure the room, issue a formal design, quote, etc. , a construction contract can be signed close to the start of construction.
The same applies to self-assembled Sumitomo friends. You should inspect and book workers you are satisfied with, and do not wait until one item is completed before looking for workers for the next item.
2. Decoration procedures
Nowadays, new communities generally need to go through decoration procedures before starting construction, so don’t ignore this step.
3. Pre-ordering of main materials
As the saying goes, "for water and electricity renovation, cabinets come first." Be sure to reserve the cabinets before starting work, because the cabinet company needs to design the kitchen water and electricity to coordinate with the decoration company's water and electricity design.
In addition, it is best to book central air-conditioning, fresh air, floor heating, enclosed balconies, etc. before starting work to avoid being in a hurry just after starting work.
2. Demolition and Construction Project
After the construction begins, the first thing to do is to carry out demolition and construction work and transform the structural layout of the house.
1. Protection
Protect certain parts that need to be protected, such as gas pipelines, corner guards, security doors, etc.
2. Demolition
Remove walls, unnecessary sliding doors or windows, etc. In some cases, it is also necessary to remove the putty on the top of the wall.
Many new residential areas are equipped with floor heating, but the quality of the floor heating is often not satisfactory. Many residents want to redo the floor heating, so they need to smash the floor.
3. Construction
According to the layout design of the house, build new walls. After the demolition and construction is completed, the walls and floors are usually painted and solidified.
4. Measure and draw the drawings
After the demolition and construction is completed, if you need to re-cover the balcony or replace the windows, you must measure the balcony and windows. IDEA recommends sealing the balcony and replacing the windows. The sooner it's done, the better.
At this time, the measuring tapes of the cabinets and the drawings of the kitchen water and electricity must be prepared, because the water and electricity renovation is about to take place.
3. Hydropower Project
1. Hydropower Positioning
According to the drawing design, hydropower is positioned on site. Sumitomo residents must pay attention to hydropower positioning and verify and confirm it repeatedly.
2. Hydropower transformation and acceptance
After the positioning is completed, the installation and laying of strong and weak electricity and waterways can be carried out. After completion, complete the water and electricity acceptance, leaving no regrets and hidden dangers.
3. Other construction
After the water and electricity are completed, the construction of floor heating, central air conditioning, fresh air, etc. can be carried out (central air conditioning and fresh air can also be carried out before water and electricity. Residents need to coordinate the various constructions by themselves. process).
Balcony sealing and window replacement can be carried out simultaneously with water and electricity construction.
4. Booking of main materials
Book the main materials that may be used in the next stage, such as wall and floor tiles, door stones, security doors, etc.
IV. Bricklaying
1. Waterproofing and closed water test
There are two main points to pay attention to when it comes to bathroom waterproofing. First, the ground waterproofing should be 300mm higher than the wall surface. The district waterproofing height is 1800mm; secondly, the waterproofing of the pipe roots must be properly handled.
After the waterproofing is completed, a closed water test should be done to check whether the waterproofing is qualified. Store no less than 20mm of water at the highest point of the bathroom. After 48 hours, go downstairs to check whether there is leakage, and check whether there is any leakage at the door of your bathroom. Drainage water (many people ignore this).
2. Tiling
Tiles can be laid after the waterproofing is qualified. Note that the cost of laying wall tiles, porcelain tiles and full tiles are different. Full tiles require the use of tile adhesive, and the thin laying method is more expensive.
When laying tiles, pay attention to whether there are hollows, seams in the sun corners, and the slope of the ground.
3. Floor leveling
If you want to lay the floor, you need to carry out fine leveling to meet the floor laying requirements; if it is a tiled floor, rough leveling is enough. Usually , the floor does not need to be rough leveled when closing the house, unless the floor heating is re-done.
4. Other construction
At this stage, the wall and floor tiles have been laid, and several tasks can be carried out: gas pipe modification, cabinet re-measurement, ceiling measurement, etc., security doors It can also be installed at this stage.
5. Carpentry
Nowadays, many Sumitomo advocates a simple style, and with the popularity of customized furniture, there is relatively less carpentry work. Basically, we simply make the ceiling and make a small amount of furniture on site.
1. Suspended ceiling
For gypsum board ceiling, pay attention to using L-shaped gypsum boards at the corners, V-shaped grooves at the joints, pasting kraft paper, and applying anti-rust paint to the nail holes. If there is central air conditioning and fresh air, there may be more suspended ceilings.
2. On-site furniture production
If you have a very skilled carpenter, it is also a good choice to buy the boards yourself and let the carpenter make the furniture on site.
3. Reservation of main materials
At this stage, the latex paint must be reserved.
6. Oil workers
Nowadays, the work of oil workers in painting has been greatly reduced, and more of them are painting walls, that is, latex paint.
1. Base treatment
For unequal top surfaces of walls, base treatment must be carried out first to repair and equalize.
2. Putty and latex paint (wallpaper)
Generally, putty is scraped twice. If the putty is too thick, it will easily cause the wall to crack. Latex paint usually requires one coat of primer and two coats of topcoat.
There are two ways to apply latex paint, one is roller coating and the other is spraying. Roller coating saves paint, and it is easy to repair damage in the later stage, but the effect is not as good as spraying; spraying has a good effect and a good paint film texture, but it consumes paint, and it is not easy to repair damage in the later stage.
3. Booking of main materials
Booking of indoor doors, measuring tapes, and floors.
7. Installation Stage
The general appearance of the house decoration has been revealed. As the installation stage progresses, the house will become more and more complete.
1. Flooring and baseboards
The floor has relatively high requirements on the ground, and the ground must be carefully leveled. The skirting can follow the floor or the door.
2. Interior doors, door cases, window cases
If you install window cases, you must first install the window sill stone (it is recommended to install it before putty) and then install the window cases. The door here The cover mainly refers to the pass. Of course, many minimalist styles do not require the installation of door covers.
3. Integrated suspended ceiling
After the tiles in the kitchen and bathroom are laid, the suspended ceiling can be made.
4. Cabinets, kitchen appliances, and bathroom ware
Similarly, after the kitchen and bathroom tiles are completed, cabinets, kitchen appliances, and bathroom ware can be installed. Just pay attention to the installation sequence of cabinets, ceilings, hoods, stoves, and gas water heaters.
5. Wardrobe
Generally, customized wardrobes are installed after the floor installation is completed.
6. Switches, sockets, and lamps
Generally, electricians from regular decoration companies will come to your home twice to install switches, sockets, and lamps (main lights usually need to be installed for a fee).
7. Cleaning
After all the things that need to be installed are installed, you can clean your home. Of course, cleaning once is often not enough.
8. Soft furnishings and move-in
After cleaning, you can arrange for curtains, furniture, home appliances and other soft furnishings to be moved in. After these are done, you can prepare to move in.
The main material reservation mentioned earlier refers to the latest reservation time. Of course, it is also good to inspect the main and auxiliary materials early and make an early reservation.
The content is provided by Haohaozhu users. For more questions, please come to the Haohaozhu APP to communicate directly with the homeowner~
- Related articles
- After n8 1 enters the SMS editing interface, it will automatically exit as soon as you press the number key. Who can help,
- I applied for a Unicom campus card. How to check traffic and telephone charges?
- Why do short messages in mobile phones become so big? How to transfer it back?
- Congratulatory message to enterprises
- Why don't you just delete the message?
- What does it mean that the invitation code of Tik Tok Extreme Edition does not conform to the account filling rules?
- How to check whether the courier sent back from abroad is taxed?
- Is the short message of online court true?
- Iqooz5, why can't the sound of this stupid mobile phone be adjusted?
- How is the "reboot" of "Tomb Raiders" going?