6 articles on engineering construction 2022 work summary
Project Construction 2022 Work Summary 1
1. Project and File Overview:
Nanfu 1st Road Road and Bridge Reconstruction Project The project is located in Shuangfu New District, Jiangjin District. Jiujiang Avenue, Chongqing Ring Expressway, Jinma Avenue and other high-end highways intersect in the new area. It is 2km away from the Zouma Exit of the Chengdu-Chongqing Expressway, a 10-minute drive from the Chongqing Inner Ring Road, and only a 35-minute drive from Jiangbei Airport. The venue is easily accessible.
The standard road width is 24 meters, two-way and four-lane, allocated as: 4 meters (sidewalk) + 16 meters (vehicle lane) + 4 meters (sidewalk). < /p>
Construction unit: Chongqing Shuangfu Construction and Development Co., Ltd. Quality supervision: Chongqing Jiangjin District Construction Engineering Quality Supervision Station
Design unit: Supervision unit of Chongqing Branch of China West China Engineering Construction Design Co., Ltd. : Chongqing Fukang Engineering Construction Supervision Co., Ltd. Construction unit: Chongqing Degan Construction and Installation Engineering Co., Ltd.
Our company leaders attach great importance to archives work and have formulated a complete archives management system. Company leaders have visited the construction site many times Inspect and guide file work. In order to ensure the smooth completion of project files, the company specially equipped the project department with necessary office supplies, 3 computers, and 1 printer, and also cultivated and valued the quality of the files. In the data management project, the archives team prepared a data management plan, formulated practical and operable archives management implementation details, and specifically formulated the key points for project completion data control.
2. Data formation:
According to the technical document material requirements for municipal project completion, the archives team is responsible for the numbering, registration, issuance and storage of the technical documents of the project department, and is responsible for the collection of completion data and accumulation.
The completed original data is formed as follows:
1. The project quality assessment data is formed by the project technical leader and quality inspector.
2. The on-site administrator will extract the test data from the test piece. After the supervision witnesses the sampling, it will be sent to the laboratory for testing according to relevant regulations. The laboratory will form data based on the test results and return two original copies of the data to the project department. The summary table and evaluation table are formed by internal data clerks and technical persons in charge.
3. The raw material quality guarantee certificate will be provided by the manufacturer when the material comes into the site. After receiving the materials, the material clerk will promptly submit it to the archivist for archiving, and the in-house technician will summarize and organize it.
4. The construction technical disclosure record is formed by the project constructor and submitted to the archivist for archiving.
5. Concealed inspection data and construction records are formed by the construction worker based on the actual conditions on site and submitted to the supervisor, quality inspection station, design institute, geology and other relevant units for signature and then submitted to the archivist.
6. The construction worker will provide first-hand on-site information for the as-built drawing, and the internal office will make changes to the as-built drawing after verification by the technical person in charge.
In the process of collecting and organizing files for this project, we adhere to the principle of synchronization with the progress of the project, and complete various technical disclosure records before construction, including earthwork construction records, concrete pouring records, steel hidden inspections, tensioning records, and Collection and arrangement of material certification materials, etc. During the construction process, various construction records, concealed acceptance records and inspection records were filled in in a timely and truthful manner, various tests were conducted in accordance with the specification requirements, and the records were organized in a timely manner. All records were signed in a timely manner, with accurate data and authentic content. When preparing as-built drawings, we must prepare them in a timely manner based on hidden records and technical change negotiation documents after the completion of each sub-project, so that the as-built drawings can be seen, touched, remembered clearly, and compiled accurately to ensure It ensures the inherent quality accuracy, timeliness, systematicness, authenticity and effectiveness of the project as-built drawings. When collecting, sorting, summarizing, and binding archival data, we must strictly follow the "Special Acceptance Measures for Chongqing Construction Project Archives" and the relevant requirements of Chongqing Urban Construction Archives to ensure that the archival data is complete, accurate, authentic, and complete. The Nanfu 1st Road Road and Bridge Renovation Project in Shuangfu New District, Chongqing has formed a project archive set. Each set includes a document book, a completed drawing book, and a photo album.
Handover set to Party A, the first copy, which includes a text booklet, a completed drawing book, and a photo album; handover to the archives room set, the first copy, which includes a text booklet, a completed drawing book, and a photo album; one set is kept by the construction unit , the first one, including the text information book, the completed drawings book, and the photo book.
3. Characteristics of the project archives:
1. The project archives team organized and collected the guarantee information and written information according to the actual situation, and a dedicated person was responsible for the comprehensive inspection, which was basically completed Tasks required for file organization.
2. Develop information around production with a realistic work style, and do not engage in "memoirs" or false information.
3. The materials formed by the archives group should be written in standard and block letters.
4. File formation is written in blue and black ink.
4. The working situation of the archives team:
Several comrades in the archives team focus on unity and cooperation to do a good job. They often study the requirements for archives organization together, give full play to their respective expertise, and Ensure timely and accurate file acceptance of project completion. Ask comrades in the archives office for advice on relevant issues that you do not understand. If it is indeed unclear, ask them to come and guide the work in person.
Emphasizing the importance of archives work, with the support of the project manager, the archives team boldly manages the work, adheres to the requirements of archives management, recognizes the truth, and enables the data creators to have a clear understanding of the current data management situation. Learn more.
During the construction process of this project, the project department has been inspected by the superior management department many times, and the archives have been affirmed by the relevant leaders. We will strive to make persistent efforts in future work to make our project archives Work continues to reach new heights.
5. Self-evaluation:
On September 5, 20xx, the company's technical department inspected my on-site files. After soliciting relevant personnel from the company, the file team staff A self-evaluation of the on-site files was conducted, and the project files basically reached the "qualified" level.
6. Experience and Summary
1. Handling the relationship with construction workers, quality inspectors, material supervisors, testing and other relevant departments is the key to the smooth implementation of archival work. In the process of file management, the relationship with data creators such as construction workers and quality inspectors must be properly handled according to the principle of "cooperation and mutual assistance".
2. Only by having a high level of professional skills can you convince others and establish the prestige of archives management. First of all, we must improve our own skills and go to relevant departments for archives training so that we can know everything about archives management.
3. As soon as the project starts, it should be organized in strict accordance with the requirements of the archives and high-quality structural standards to reduce the impact of some adverse factors on the archives work during the construction process.
4. Fully understand the role that archives work plays in the value of projects and projects, and be sure to manage archives well.
7. Future work plans:
1. Starting from now, focus on optimizing file management, digesting the relevant content of file organization through careful study, and communicating with owners and archives offices Opinions achieve the purpose of improving one's own abilities.
2. Organize relevant data formation personnel to study, and through meticulous work, strictly control the handover and acceptance of hidden projects and processes, do a good job in material testing and participate in the explanation of construction plans and construction technology to ensure that the data will be used in the next step. The project can be taken to a higher level.
8. Conclusion:
In the process of collecting and organizing project files, this project has received strong support from the construction unit, supervision unit and superior authorities, especially the leaders of the Urban Construction Archives Office We would like to express our sincere gratitude to the teachers who have visited the site many times to guide the work.
Engineering Construction 2022 Work Summary 2
Time flies, and the years fly by. In the blink of an eye, I have been working in the unit for half a year. This half year is an important step in my life journey. During this period, with the training and help of the leaders and the care and support of my colleagues, I gradually completed the work content from studying professional surveying and mapping engineering to the engineering department, and from university to xx high-grade highway. The dual transformation and adaptation of the environment and roles of the construction company. At the beginning of the year and the end of the year, I calmly review my work and life in the past six months, and I have gained a lot.
I now summarize my study and work in the past six months as follows:
1. Work:
In July XX, I was honored to work at XX High-grade Highway Construction Corporation. And was assigned to the 13th Bid Engineering Section of the xx Roadbed Project. The engineering department is the leader of the company and is mainly responsible for managing plans, measurement and other work. The engineering department is very training and can also learn a lot. During this half year of study and work, I learned the names of various parts of the bridge, some parts of the highway drawings, and mastered the relevant content of the industry, as well as the methods and rules for organizing completed materials. During this period, I learned a lot and summarized some shortcomings. I still need to work harder to learn relevant knowledge and go to the scene to learn more so that I can learn more knowledge on the spot. So in the next year, I will not be afraid of the wind and sun and have the opportunity to go to the field to study more. Consciously strengthen study, learn from theory, learn from professional knowledge, learn from colleagues around you, gradually improve your theoretical level and professional ability, overcome youthful impatience, be down-to-earth, improve work initiative, and not be afraid of doing more or doing small things , improve yourself through bit by bit practice.
2. Ideology:
First of all, consciously strengthen the study of political theory and improve party spirit. The company's strong political learning atmosphere deeply infected me. I actively participated in various learning activities organized by the company, and focused on self-study and serious study, which further improved my theoretical level and political quality, and strengthened my awareness of integrity and self-discipline. I also wrote an application for joining the party and a thought report, hoping that I could join the ranks of the Communist Party of China as soon as possible, and asked for the test of the company and the party. At work, I humbly ask my colleagues for advice, actively ask for advice when encountering problems, and can solve problems well. I still have a lot to learn in the future, so I have to persevere.
Third, the work plan for xx:
This year, I will mainly manage the completion data. Although I don’t know much, I humbly ask the leaders for advice and strive to improve this aspect. Made to perfection. At the same time, in the engineering department, we must obey the leadership's arrangements, conscientiously complete the tasks assigned by the leadership, and follow the organization's lead in all steps.
The company's five-to-five innovations have been implemented very well. We will continue to carry out "compare progress to create image projects; compare quality to create high-quality projects; compare project management to create clean government projects; compare safe production to create peace of mind Engineering; than civilized construction, create harmonious engineering."
The above is a summary of my work in the past six months. In the future, I will be down-to-earth, make achievements in the fertile soil of xx High-grade Highway Construction Corporation, and contribute to xx High-grade Highway Construction Corporation. own youth.
Engineering Construction 2022 Work Summary 3
I was recruited to work in the project management department of the company on December 10, 20xx. From the engineering construction unit to the engineering construction unit, although my job position and role have changed a lot, and it is also my first contact with the "Zhejiang Provincial Construction Project Budget Quota", with the care of the leaders and the help of my colleagues, I have been able to achieve the goal with my own strength. With his professional foundation and work experience, coupled with hard work and study, he quickly adapted to the work environment and achieved good results. The work situation is briefly summarized as follows:
1. Personal profile
From September 1996 to July 1999, I studied engineering cost in the Department of Real Estate of Hunan Urban Construction College ; From July 1999 to July xx, he worked in the Fourth Engineering Co., Ltd. of China Railway 19th Bureau Group, engaged in budget preparation and review, contract management, bidding management, etc.; In October xx, he participated in and passed the National Cost Engineer Qualification Examination .
2. Main work performance and achievements
1. Strictly abide by the company's rules and regulations. At the beginning of work, I carefully studied various rules and regulations such as "Veco Outline", "Daily Behavior Standards for Real Estate Segment Employees", "Basic Management System", "Job Function Description", etc., and kept them in mind, always reminding myself to Strictly abide by the company's rules and regulations and maintain the company's image. For example, insist on arriving at the company early every day, cleaning the office, and creating a clean working environment for colleagues.
2. Carefully study the budget preparation materials of Zhejiang Province. Although the principles of budget preparation are the same, the "Zhejiang Province Construction and Installation Project Quotas" are very different from the highway and railway project quotas that I have been exposed to more before.
Therefore, I first carefully and systematically studied the Zhejiang Province budget preparation materials, and insisted on studying while working. I quickly mastered the essentials and was able to independently complete the tasks assigned by the leadership; at the same time, I also In my spare time, I learned to use "Magic Calculation Software" to prepare budgets and "Luban Software" to calculate steel bars, which greatly improved work efficiency. In the future work, I will continue to explore and study to make the work more precise and perfect.
3. The review of the final accounts of the winding workshop and temporary projects of the Dunhuang Branch of Veken Essence Group Co., Ltd. is progressing smoothly. Although the winding workshop and temporary projects have been completed for a long time, the relevant completion data is very incomplete, which brings great difficulties to the final accounts review work. After I took over this job, on the one hand, I actively asked the construction unit to improve the completion data, and on the other hand, I used the existing data in my hand to calculate the project quantity and check various data. In order to accurately grasp the project situation and ensure the accuracy of calculations, I also went to the site to check carefully. Through my efforts, this work has made rapid progress. Most of the information required for the final accounting review of the project has been collected, and the budget of the winding workshop has been verified with the construction unit.
4. Actively proceed with the civil engineering review of the commercial and residential building at No. 5 Huayan Street. After the leader assigned me to be responsible for the review of the civil construction budget of the project, I took the time to familiarize myself with the construction drawings and related materials, and went to the construction site many times to understand the situation, so that I could grasp the static and dynamic conditions of the project in the shortest possible time. In order to better protect the interests of the company and gain the initiative in the final accounts, I have advanced the engineering quantity calculation work to the current stage. After a period of intense and orderly work, the calculation of part of the basement project has been completed. In addition, I also carefully completed the review of the progress payment budget for December xx and January xx and the project contact orders that occurred in the previous period. Among them, the budget was reduced by 461,321 yuan in December xx and 163,723 yuan was reduced in January xx. Ten thousand yuan, which was affirmed by the department leaders.
5. Other aspects: ① Actively make reasonable suggestions to leaders, such as cost control and data management; ② Actively discuss cost control, contract management, data management, etc. with colleagues. Through discussions, we not only enhance the friendship among colleagues, but also improve our own business capabilities; ③ Take the initiative to communicate with colleagues and enthusiastically help others; ④ Actively participate in various activities organized by the company, such as participating in party member studies and New Year party performances.
3. Direction of efforts
1. Make full use of the advantages of passing the National Cost Engineer Qualification Examination and previous work experience, proactively contact various related businesses, and improve one's own practical experience operational ability, and make due contributions to the company's brand building;
2. Actively participate in self-study undergraduate examinations, study professional skills, and improve business capabilities and professional standards;
3. Give full play to the exemplary and leading role of party members and strive to be advanced.
In short, although I have achieved some results in the past three months, there is still a certain gap from the leadership's requirements. In the future, I will further strengthen my study, work hard, give full play to my personal strengths, and make due contributions to the company's greater success.
Engineering Construction 2022 Work Summary 4
Since graduating in 20xx, I have been engaged in quality inspection work, and I have formed a certain work model for quality inspection work. In May 20xx A new challenge stood in front of me on the 6th. Life must be full of challenges. Only in this way can we remember it without regrets for doing nothing.
Time flies really fast. In the blink of an eye, three months have passed by in my life. In these three months, I have learned a lot and I have also seen my own shortcomings. , the work situation of these three months is now as follows:
Longyu Coal Chemical Phase II is under construction. According to the construction requirements on site, the material supply can be divided into A supply (Longyu Coal Chemical self-purchased quality) and B supply (the construction unit purchases materials).
1. Material supply process.
The Engineering Technology Department and the construction unit will submit a material demand plan for review and approval by the Equipment Department, and make an inquiry and make an estimate based on the inventory situation, preliminary bidding situation and construction needs (supplier A or self-purchased by the construction unit). Report to Henan Longyu International Trade Co., Ltd. and Materials Management Center on the 20th of every month for approval (self-purchase or collective purchase), select manufacturers, review qualifications, answer technical questions and unify technical requirements to sign shortlisted Supplier recommendation form (department, finance, business management, supervision and leaders in charge) determines the time and place of the bidding and informs the suppliers and the enterprise management department (the enterprise management department is responsible for the selection of the bidding judges, and the number of judges should be odd). The judges and suppliers sign in at the bidding meeting site. The subject matter and technical requirements should be explained first. The supplier should clarify technical questions and submit the first quotation to the supervisor (indicate the delivery time and payment method). The supplier should vote on the second quotation (re-inspection without permission). No one is allowed to read the quotation. ) Approval of the bidding results and notification of the winning bidder to sign the contract within 7 working days after signing the technical agreement (the winning bidder shall pay the bid winning conference fee) Place the order, contract tracking, goods arrival and acceptance (planners, custodians, engineering and technical personnel , inspectors and suppliers should be on site) and the invoice should be posted (the content of the invoice issued by the supplier should be consistent with the content of the contract) and payment should be made.
Notes:
1. The name of the supplier must be written clearly and correctly;
2. Technical issues should be unified before bidding;
3. Before bidding, you must ask the supplier whether there are any unclear matters and whether he can participate on time;
4. Check the material items and prices when signing the contract, and clarify the specifications of each item to prevent delays in follow-up work.
2. B supplies materials.
The self-purchased materials carried out by the construction unit according to the construction requirements are called B supply. In order to control the quality and budget of the project, the quality and price of the B supply materials must be verified. To confirm the quality and price, the construction unit needs to provide the corresponding contract, invoice, price confirmation application form and material declaration form. The work of quality appraisal and price appraisal should be divided into two parts: quality appraisal and price appraisal. Quality appraisal is to inspect the quality of the project, and price appraisal is to verify the price of the materials used to see whether the amount declared by the construction unit meets the actual market price. , and whether it is within the budget. The quality and price appraisal work must be consistent with the self-purchasing work. During the inquiry process, care must be taken to prevent some suppliers from randomly reporting prices and affecting the price appraisal work.
3. Joint bidding.
Joint bidding is a bidding method in which the construction unit organizes the owners to participate. Both parties can recommend suppliers. Only the bidding method can alleviate the financial problems of the owners and reduce the conflicts between the construction unit and the owners. Some unnecessary friction, the joint bidding contract is signed between the supplier and the construction unit, but the owner has the obligation to ensure that the funds are in place, and joint bidding is a form of price recognition, so it requires Minister Zhang of the Development Planning Department of Yongmei Co., Ltd. join. The form of joint bidding is basically the same as that of private bidding. One thing that needs to be noted in joint bidding is that the owner must have more judges than the construction unit.
This is the main work to be done in three months. During these three months, I found that I still lacked organizational and coordination skills. This is the focus of learning next. Regardless of whether supply work is just a matter of buying things, learning how to purchase high-quality and low-priced materials is the foundation of supply work. Supply work also requires a timely grasp of market prices and market dynamics. It is necessary to form a price system in oneself and form a unified system for suppliers of various materials.
Supply work is the source of a company, and it is also related to whether the company can operate safely and long-term. Therefore, supply work must avoid selfishness and have a fair and just heart.
Supply work faces suppliers every day, which is another indispensable link in supply work. If the supply work lacks suppliers, the supply work is equivalent to lacking legs for walking.
Project Construction 2022 Work Summary Chapter 5
The project is located on Fengxian Road, Shenmingba. The project is a frame structure. It functions as an underground garage (83 parking spaces) during peacetime and during wartime. Second Class Personnel Shelter Section. The main part of the proposed project is on the ground floor, and there is a mezzanine (changing room) under the partial square stage. The floor height is 4.5m, and the building area is 4137.88m.
The engineering level is Level 2, the design service life of the structure is 50 years, the safety level of the structure is Level II, the seismic fortification level is 6 degrees, the garage fire protection classification is Category III, the fire resistance level is Level 1, the main waterproof level is Level 2, and the power station The waterproof level is level one.
Since the start of the project, company leaders have attached great importance to archival work and developed a complete archival system, subdividing archival information into place and comprehensively organizing it to ensure that the archives are synchronized and authentic with the construction. In order to ensure the quality requirements of archived materials, the company is specially equipped with computers, printers, copy scanners, paper cutters, binding machines, pagers, digital cameras/(video) machines and other equipment and office supplies to make the quality of archives more standardized.
During the collection and sorting process, the project files were strictly implemented in accordance with the national-level Chongqing local standards. With the strong support and help of the leaders of the Chongqing Wanzhou District Urban Construction Archives for this project, the owners, supervisors and construction workers Under the leadership's attention to this work, during the construction process of this project, the material quality assurance data and test data are complete, all types of hidden data, construction records and various functional test data are complete, and they are all filled in as the project progresses under the supervision of the owner and supervisor. , the signature procedures are complete, the handwriting is neat, the content is complete and true. To ensure that the data is synchronized with the project, the formation of archived data for the project has met the requirements of file management and acceptance standards.
From the beginning of the project, the full-time data clerk of this project collected project data in strict accordance with the acceptance standards and archives requirements. Organize the work and strive to standardize the data archiving. After collection and sorting, the information is now reported as follows:
*** sets of archived information on this project have been completed. Hand over to the owner a set of * copies, including a copy of written materials, a copy of the completed drawings, a photo album, and a photo album.
From the start of the project to the completion, the formation, collection and improvement of archives. All have received strong support from the superior authorities. Without the guidance, care and coordination of the leaders, the difficulty of archival work can be imagined. The arrangement of the archives of this project has benefited us a lot and accumulated valuable information for the archives arrangement of the next project. I would like to express my most sincere gratitude to all teachers and leaders for this wealth of experience!
Project Construction 2022 Work Summary 6
Since I started working in June 20xx, I have participated in the Jingba Road Project, xx Project, xx Road Project, xx Port Development Zone The construction of xx West Road Project, xx East Road Project, xx Project and other projects. Now I am responsible for the data compilation of the port bt project construction in xx, and have served as a student, data clerk, contract administrator and political worker.
During my tenure as a data clerk in the Construction Technology Section, I worked meticulously and conscientiously. The main tasks include:
1. Cooperate with professional engineers to strictly control engineering data. Because engineering data truly reflects the results of project construction, data are various forms of information records formed during the project construction process. Only by fully cooperating with other professional engineers can this work be completed and done well.
2. Responsible for the management of construction data, and collect, organize and archive construction data. Construction data is a true record of the project construction process and is a systematic project. It involves the substantive work of the supervision unit, construction unit, construction unit, design unit and other project participating units, and is a sign of scientific, standardized and legalized construction work.
3. Prepare meeting minutes.
4. According to the data regulations, the construction data included in the reception range of the Urban Construction Archives will be moved to the xx Construction Archives. Only when all the early stages are completed can the transfer to the archives be smoothly carried out.
The South Ring Road project we built is not only of excellent quality, but also adds a beautiful scenery to the port area in appearance; during the construction of the xx Road project, I actively cooperated with the leaders and technical staff, and worked with The construction unit and the supervision unit should form a good working relationship to ensure that there are no mistakes in the signing and transfer of materials.
In June 20xx, in response to the "Creating Safe Construction Site Activity" of the xx Municipal Planning and Construction Bureau, I was included in the "Safe Construction Site Leading Group" and became one of the main persons in charge of the activity. I was responsible for establishing "Creating a Safe Construction Site Ledger" was unanimously praised by the project department and company leaders, and passed the first inspection when superiors inspected it, which had a positive impact on the company. Since then, he has also been responsible for the "One Law, Three Cards" activities and "Creating Civilization" "Construction site" activities and other work, be conscientious and responsible at work, and be able to complete tasks assigned by leaders in a timely manner. The construction materials and completion materials of the four projects that I participated in or was responsible for were all completed in a timely, conscientious and high-quality manner, laying a good foundation for the projects to be completed on schedule and final accounts. For this reason, I have been praised many times by the leaders of the project department and the construction technology department.
In addition, during the construction process, I was also responsible for the contract management of the project. The unit had a large number of labor contracts that needed to be re-signed, as well as centralized management of migrant workers, from which I learned a lot. Knowledge. During my work, I continued to learn and improve my professional skills and practical experience, hoping that I can do better in my future work.
- Previous article:How does Apple's SMS intercept advertisements?
- Next article:Will China Mobile Universal Card expire?
- Related articles
- I didn't need a mobile phone number before. How can I return it?
- Today, I received several harassing calls, saying that I registered my friend information on your 58-city network, and my mobile phone also received your SMS notification for no reason. What happened?
- Is there a fixed format for searching questions by SMS?
- Slogans related to the law
- What if the dual micro-signals set by the mobile phone can't be displayed?
- Holiday copywriting
- Which way to take from Quanshun to Luoyigao?
- What should I do if crowdsourcing doesn't send orders after Le Run breaks the contract?
- I want to check the credit card application progress of Weifang Bank.
- Golden Gate Lake began to clean up. Last year, the coaching staff of the first team has received arrears.