How to deal with the failure of the construction unit to perform the contract?

According to the relevant laws and regulations of our country, after signing the construction contract with the construction unit, the construction unit should complete the project construction within the specified time, and the project payment can only be obtained after passing the acceptance. If the construction unit fails to perform its contractual obligations, it is a breach of contract. The construction unit may require the construction unit to continue to perform the contract. If it fails to perform, it may require it to bear the liability for breach of contract. The following is my answer to readers. I hope the following knowledge will help readers.

A, the construction unit fails to perform the contract how to deal with?

1, the construction unit fails to perform its contractual obligations, which is a breach of contract. The construction unit may require the construction unit to continue to perform the contract, and may require it to bear the liability for breach of contract if it fails to perform.

2. People's Republic of China (PRC) Civil Code

Article 577 Where a party fails to perform its contractual obligations or fails to perform its contractual obligations in conformity with the contract, it shall be liable for breach of contract such as continuing to perform, taking remedial measures or compensating for losses.

Second, the construction contract dispute evidence what matters needing attention?

1, project meeting minutes and correspondence related to the project must all be saved.

2. Various construction schedules, including schedules prepared by the owner's representatives and subcontractors, and required equipment arrival schedules.

3, construction memorandum (diary), related matters that affect the time limit for a project and claim during construction, should be recorded in time.

4. Timely report to the supervisor and the owner in writing the verbal instructions of the owner and the supervisor for approval.

5. The project photos need to be managed by special personnel, and the photos will be sorted according to the progress of the project.

6. All contract bidding documents, contract drawings, modified and added drawings, change orders and materials. Fund documents and payment vouchers.

7, mobile phone messages as evidence materials, collection and preservation.

The above knowledge is my answer to relevant legal questions. If the construction unit fails to perform its contractual obligations, it is a breach of contract. The construction unit may require the construction unit to continue to perform the contract. If it fails to perform, it may require it to bear the liability for breach of contract.