Joke Collection Website - News headlines - Three steel pipe scaffold contracts

Three steel pipe scaffold contracts

Scaffolds and supporting frames erected for building construction and bearing loads are collectively referred to as scaffolding. What about the contract for steel pipe scaffolding? The following is the steel pipe scaffold contract I compiled, please refer to it.

Steel pipe scaffold contract 1

Employer: (hereinafter referred to as Party A) Contractor: (hereinafter referred to as Party B)

In accordance with the Contract Law of People's Republic of China (PRC) and other relevant laws and regulations, and in line with the principles of equality, fairness, honesty and credibility, both parties reach an agreement on contracting this project and conclude the terms of this contract for both parties to abide by.

I. Project name:

Oriental Peninsula Community Project of Hechi Meng Jun Real Estate Co., Ltd.

Second, the project site selection:

Renshang Village, Jinchengjiang District

Three. Project overview:

Scaffolding construction of external wall of Building 65438 1kloc-0/5 in Dongfang Peninsula Community

Four. Scope of contract:

1, 2, 2 residential building external wall steel pipe scaffolding, scaffolding, safety net erection and demolition (steel pipes for shear wall and column reinforcement shall be the responsibility of Party A, and pipe buckles shall be provided by Party B free of charge. When Party A uses Party B's buckle, it shall go through the collection procedures and return it to Party B in full upon completion).

Verb (abbreviation for verb) Contract mode and price:

1. Party A entrusts Party B to carry out the construction in the way of contracting for work and materials, and Party B provides steel pipe materials and is responsible for erection and demolition according to the progress of Party A's main project. ..

2. The contract price is calculated according to the facade area of the external wall shelf of the building, and the amount of work is measured by both parties on site.

Terms of payment for intransitive verbs:

Party A shall pay 70% of the project payment in advance every month according to the actual amount of work completed by Party B, and the rest shall be settled and paid within 30 days after the scaffolding is completely dismantled. (All payments are made in cash, and Party B only issues receipts instead of invoices).

Seven, quality and schedule requirements:

1. Party B must build an outer frame with qualified steel pipe materials and accessories according to the current national construction specifications, and the built outer frame meets the safety regulations and can pass the inspection and acceptance by the quality supervision station.

2. Party B must organize enough materials and manpower to ensure synchronization with the main project progress of Party A.. If Party B fails to keep pace with Party A's progress, Party A will fine Party B 1000 yuan for each day of delay.

Eight. Other agreements:

1. Party B's construction personnel must strictly abide by the relevant safety regulations on the construction site and be equipped with specified safety protection articles. Party B shall take full responsibility for the safety accidents of Party B's construction personnel.

2. If Rachel reinforcement is required for erection, it shall be provided by Party A, and Party B shall be responsible for the processing and embedding of reinforcement.

3. Party A has used Party B's external scaffolding for 65,438+02 months. If it is used beyond the time limit, Party A shall pay Party B a daily rent of 0.65,438+05 yuan per square meter.

4. The information input by Party B shall be kept and managed by Party B. If it is lost or damaged, Party B shall be responsible. If losses are caused by irresistible natural disasters, each party shall be responsible for it.

5. Before the outer frame is dismantled, Party A's tower crane shall not be dismantled to facilitate Party B's dismantling of the outer frame.

6. If there are any matters not covered in this contract, both parties shall sign a supplementary agreement through negotiation. This contract is made in duplicate, which shall come into effect after being signed by both parties, and each party shall hold one copy.

Signature of Party A: Signature of Party B:

ID number: ID number:

Tel: Tel:

Contract signing place:

Contract signing time:

Steel pipe scaffold contract 2

Employer (hereinafter referred to as Party A):

Contractor (hereinafter referred to as Party B):

In accordance with the Contract Law of People's Republic of China (PRC) and the Construction Law of People's Republic of China (PRC), in line with the principles of equal consultation, honesty and credibility, and in order to clarify the rights and obligations of both parties, this contract is hereby signed and abided by both parties.

I. Overview of the Project

Project name:

Project location:

2. The way and content of contracting

1. Party A will contract the internal and external works of the steel pipe scaffold of this project to Party B for construction, and Party B's contracting scope includes the erection and dismantling of external wall scaffolding, net hanging and bamboo basketry laying.

2. The internal frame material does not shrink, and the external scaffold channel steel is not included.

3. When Party B's materials are transported to Party A's construction site, Party B shall be responsible for keeping them.

Three. Unit price and calculation method

1. The square area of internal and external frames is calculated according to the total construction area. The unit price of supporting materials (steel pipes and fasteners) for internal and external frames is RMB per square meter (excluding tax).

4. Duration

1. The construction period is calculated from the date when Party A notifies the materials to enter the site to the date of year, month and day, and the contract construction period is 12 months (360 days).

2. If Party A delays the construction period within the time stipulated in the contract, Party A shall pay Party B the deferred payment per square meter of 0.2 yuan per day according to the actual construction area, and the deferred payment shall be paid once a month. The project payment and deferred payment shall be calculated to the date when Party A notifies the framework to be dismantled. Duration outside the frame within the month.

Verb (abbreviation of verb) payment method

1. Party B pays RMB 654.38+10,000.00 Yuan, and 70% of the engineering quantity is paid for each floor.

2. Party A shall pay the balance to Party B in one lump sum before notifying the demolition.

3. If Party A fails to pay the progress payment on time, Party A shall be responsible for the economic losses caused by Party B's delayed production, and Party B has the right to stop work.

Obligations and responsibilities of both sides of intransitive verbs

1, and pay according to the quantities agreed in the contract.

2. Party A must provide Party B with a place for stacking materials, and the necessary vertical transportation, traffic and other convenient construction conditions will make the place level for Party B to recycle and transport.

3. In the process of construction, Party B shall obey the unified command of Party A's site builder, build scaffolding according to the construction progress, and must ensure the safety of scaffolding.

4. All safety accidents occurred during the construction of Party B shall be borne by Party B. ..

5. Dismantle scaffolding when the main body is completed, excluding exterior wall painting.

Seven. responsibility for breach of contract

Under the condition that Party B guarantees that the scaffolding used by Party A is in place, Party A must put the payable project funds in place. If Party A fails to pay in place, Party B has the right to stop the installation, and all losses caused thereby shall be borne by Party A. ..

The total construction period of Party A's use of external scaffolding is 65,438+02 months (360 days), counting from the date when Party B's materials enter the site for erection. If Party A fails to use it in time, Party A shall pay Party B the overdue use fee of steel pipes, fasteners and other materials per square meter of 0.2 yuan of the project every day, and Party A shall pay the overdue cash before using it. If Party A fails to abide by the contract, Party B has the right to dismantle all scaffolding at the time agreed in the project.

Eight. Special terms and conditions

During the performance of the contract, if the contract cannot be fully performed due to force majeure (including war, natural disasters, inability to carry out construction in the same industry, major adjustment of national laws, etc.), both parties shall not be liable for breach of contract. Any dispute arising from the performance of this contract shall be settled through negotiation. If negotiation fails, either party may bring a lawsuit to the people's court in the place where the contract is performed.

Nine. supplementary terms

This contract is made in duplicate, one for each party, and shall come into effect as of the date of signature and seal. For matters not covered in this contract, both parties may sign supplementary terms separately, which have the same legal effect as this contract.

Signature of Party A: Signature of Party B:

Company seal: company seal:

ID number: ID number:

Guarantor of Party A:

Contact information: contact information:

Year, month, sun, moon, sun.

Steel pipe scaffold contract 3

Party A: Fujian Toubao Construction Engineering Co., Ltd.

Party B: Fifth Construction Engineering Company of Jinjiang City, Fujian Province

In accordance with the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and other relevant laws and regulations, and following the principles of equality, voluntariness, fairness, honesty and credibility, the two parties reached an agreement on the contracting of steel pipe scaffold erection and demolition projects.

Rule number one. Project overview:

1. 1. Project name: Binhai Yujingcheng

1.2, structural form: frame-shear structure.

1.3, construction area:

1.4, quality grade: qualified.

1.5. Contract method: contracting for labor and materials.

1.6, project site: the ruins of Binhai Yujingcheng, Shuitou Town, Nan 'an City/steel bowls of buildings kloc-0/#, 2#, 3#, 5# and 6#.

1.7, erection form: landing double-row steel pipe scaffold.

Article 2, project contracting scope and work content:

Transportation inside and outside the yard, installation of base, pre-embedding of steel pipes and iron parts, selection of materials, erection of scaffolding, laying of bamboo poles according to the specification requirements, installation of skirting boards according to the specification requirements, hanging of dense mesh safety nets (Note: the safety nets can only be used after Party A's approval, and the safety nets within the market price of 35-40 yuan must be used), and unloading platforms for passenger and freight elevators, double-layer protective sheds for passenger and freight elevators and double-layer protective sheds for steel pipes in aisles will be built on all floors.

For work. Clean the steel pipes around the scaffold. The supporting surface should be painted with black and yellow steel pipes and maintained normally. After the outer frame is dismantled, the materials shall be temporarily stacked at the place designated by the project manager, and all scaffold materials shall be dismantled on time according to the time agreed in this contract. (Note: After a bamboo pole is laid on the first floor, it will be laid every 3.6 meters, so it is estimated that a bamboo pole will be laid and a bamboo pole will be laid on the top floor. )

Article 3, engineering quality and technical requirements:

3. 1. The quality shall be set and accepted according to the requirements of the safety construction site issued by the Ministry, and at the same time, it shall be accepted synchronously with the layers according to the requirements of the company. Scaffolding progress is one step ahead of the construction layer. At the same time, bamboo poles should be laid in time and a vertical dense mesh safety net should be set up.

3.2. According to the Safety Technical Specification for Fastening Steel Pipe Scaffolding in Building Construction (JGJ30-20_) and its implementation guide, the Safety Inspection Standard for Building Construction (JGJ59-99), the Safety Technical Specification for Building Construction Operation (JGJ80-9 1) and the relevant specifications, standards and operations of current national, provincial, municipal and foreign scaffolding companies. Note: (Four horizontal steel pipes must be used for each horizontal pole, and two horizontal steel pipes should be set for handrails, and the maximum distance between vertical poles should not exceed 1600mm).

3.3. Party B shall establish an inspection system for the outer steel pipe frame project, equip a management team with strong technical management level, and accept the inspection of Party A and the supervision and security inspection departments at any time.

3.4. Party B shall be responsible for the technical safety disclosure of the operators, carry out the construction in strict accordance with the rules and regulations, ensure the quality and safety of the scaffolding, and provide the scaffolding units and scaffolders with certificates. The team leader must sign in at the construction site every day, check the quality of the outer frame, rectify the potential safety hazards in time, and have no holidays.

3.5, responsible for organizing the acceptance of scaffolding subdivisional work, for the requirements of the relevant departments to check unqualified should be seriously rectified, to ensure the safe use of scaffolding, if there is a fine due to scaffolding quality and safety problems, its economy and responsibility shall be borne by Party B. ..

Article 4, safe production and civilized construction:

4. 1, all obey the command of the site management personnel, and do not blindly produce. Workers must wear safety helmets when entering the site, and are not allowed to wear three shoes and use child labor, otherwise each person will be fined 200 yuan each time, which will be deducted when the project payment is made.

4.2. Scaffolding shall be constructed according to the safety operation regulations. If it is not constructed according to the regulations, Party B shall bear the economy and responsibilities in case of safety accidents.

4.3. If Party B needs to dismantle the enclosure or safety protection facilities on the construction site (subject to Party A's consent) or accidentally destroy them, it shall be restored in time, otherwise the expenses shall be borne by Party B..

4.4. If Party B's workers are found to urinate and defecate on all floors, Party A has the right to fine 200 yuan every time, which will be deducted when Party B pays the project payment or Party B's workers find other shift workers urinating and defecating on all floors, and Party A will reward 200 yuan.

4.5. Organize on-site civilized construction of safety production in strict accordance with the operating rules of safety production and relevant rules and regulations of the company, and Party B shall be responsible for all safety matters and safety fines.

4.6. For the safety problems caused by Party B (including the third party), Party B shall bear the economic and legal responsibilities.

Article 5, the construction period:

5. 1. In strict accordance with the construction period planned by Party A, the external scaffold shall be constructed synchronously with the main body from the date when Party A notifies it to start erection, and the scaffold erection height shall be higher than one step per construction floor, otherwise, the compensation for the construction period will be 1000 yuan for each day of delay, and so on, and the above compensation for the construction period will be deducted when Party B pays the project payment.

5.2. The construction period of each single building scaffold is 360 days from the date of erection. If it is used beyond the time limit, 0. 1 yuan /m2 per day (calculated according to the actual project). The construction period starts from the erection of individual buildings and ends on the date when Party A notifies Party A to dismantle them. The demolition time of each floor will not stop for 20 days, and the part that has not been demolished for more than 20 days will be calculated according to the construction period.

5.3. If Party B's technical strength or labor shortage affects the progress of the project, Party A has the right to hire a team other than scaffolding to subcontract, and Party B shall be responsible for the part where the unit price of the team other than scaffolding exceeds the unit price contracted by Party B. ..

Article 6: Payment and settlement method and lump sum unit price:

6. 1. Party B shall pay 60% of the monthly workload. Party B shall pay 20% of the capping of the main body, 65,438+05% of each scaffold after dismantling, and 5% of the balance, and pay after all materials are returned.

6.2. Payment method of project funds: cash payment.

6.3. Engineering quantity settlement method: Calculated according to the projected concave-convex expansion area of the external wall of the building (including both sides of the balcony, both sides of the convex window and around the patio), and the height is from the outdoor natural ground to the roof structure.

6.4, lump sum unit price:

1. According to the projected area of the building, the unit price is 48 yuan/m2, including the construction of double-layer protective shed (i.e. protective shed for steel yard, protective shed for entrance of passenger and cargo elevator, protective shed for entrance of safe passage), installation of unloading platform (provided by Party B), reserved hole, stair handrail, five-sided enclosure and tower crane attachment frame for protection. If you need to hang a flat screen, each piece (6.00╳3.00) is calculated at 300.00 yuan/piece.

6.5. The above-mentioned comprehensive lump sum unit price has taken into account the scope and work content of the project agreed upon in the contract period and the influence of various factors on the price and labor costs, and will not be adjusted under any circumstances.

Article 7: Responsibilities and obligations of Party A:

7. 1. Party A shall provide the stacking yard, vertical transportation equipment (goods elevator is used for loading and unloading the frame) and power supply, and shall be responsible for leveling and tamping the plain soil around the building, basically removing obstacles on the construction site, leveling the construction site and ensuring the foundation bearing capacity required by the outer frame.

7.3. The embedded φ 16 steel bar fixed by I-beam shall be provided by Party A, made by Party A, and cut by Party A and Party B after the embedded iron piece is dismantled.

7.4 Without Party B's consent, Party A shall not use Party B's steel pipes and fasteners.

7.5. If the project completed by Party B is put into use after passing the on-site acceptance by Party A, if it is damaged by other teams on site, Party A shall be responsible for repairing the workers' wages and material expenses.

Eight. Responsibilities and obligations of Party B:

8. 1, be familiar with the construction drawings carefully, be responsible for formulating the erection scheme of the off-frame facilities, and carry out the construction according to the requirements of the construction drawings, the current construction acceptance specifications and relevant operating procedures to ensure that the quality of the frame body meets the quality qualification standards agreed in the contract. Do a good job in safe production and civilized construction to ensure that it is completed within the time agreed in the contract.

8.2. Be responsible for the technical safety disclosure of the workers entering the site, and carry out safe construction in strict accordance with the specification requirements. In case of accidents caused by Party B's improper operation during construction, Party B shall be responsible and bear economic responsibilities.

8.3. Responsible for organizing the acceptance of scaffolding subdivisional work. If the inspection by the relevant departments does not meet the requirements of the specification, it should be seriously rectified to ensure that the scaffolding inspection is qualified. If the inspection is still unqualified, Party B shall be responsible for and bear all the expenses incurred each time, and deduct them from Party A when paying Party B the progress payment.

8.4 During the use of scaffolding, materials such as frame body shall be kept by Party B. If steel pipes, fasteners, safety nets and bamboo purlins are found missing, or steel pipes are cut, welded or severely deformed or bent, Party B shall send someone to rectify them in time, otherwise the contractor shall be responsible for the safety problems and economic responsibilities arising therefrom.

8.5. After the workers enter the site, Party B shall sign a labor contract with each worker, and submit a monthly salary report with the signature of the worker and the provincial certificate number of each worker to Party A, and obey the management of Party A's migrant workers' salary payment supervision system, otherwise it will be fined Wu Bai Yuan each time.

Article 9, Others:

9. 1. Matters not covered in this contract shall be settled by both parties through consultation.

9.2 This contract is made in triplicate, two for Party A and one for Party B. ..

Representative of Party A: Representative of Party B:

Tel: Tel:

Three related clauses in the steel pipe scaffold contract:

★ Three contracts for steel pipe scaffold project.

★ The latest model of steel pipe scaffold contract 3.

★ Three latest scaffolding contracts

★ Three latest scaffolding construction contracts

★ Three scaffolding contract templates.

★ Three scaffolding construction contracts

★ 3 simple scaffolding contract templates

★ 3 The latest external scaffolding contract.

★ Template of Steel Pipe Scaffolding Contract

★ 3 Model steel pipe sales contract