Construction site management and civilized construction are an important part of safe production and an important symbol of modern construction. It is a basic management work for construction enterprises. Safety production and civilized construction complement each other. Ensuring that construction is orderly and changing the dirty and messy appearance in the past has far-reaching significance for improving investment efficiency and ensuring project quality.

1. Develop a construction site floor plan with reasonable layout and comprehensive content, and submit it to Party A for approval before conducting on-site layout. 2. The roads and construction sites at the construction site must be hardened. Concrete is used as the hardened material. The road must be smooth and have circulation trunk roads to meet transportation and fire protection requirements and ensure no subsidence or dust. The middle part of the road must be arched, with drainage ditches on both sides and the main trunk. The width of the track is not less than 4-6M, and the thickness is 20CM. The thickness of the construction site is 10CM, and a drainage system is installed.

3. The construction site is surrounded by iron plates higher than 1.8M, which are arranged continuously without leaving any gaps. They are 50MM above the natural ground, and there are no less than 2 pull points at 6M to ensure firmness, stability and cleanliness. Beautiful, the height is consistent with the same line.

4. The construction site adopts closed management, and a guard room is set up at the door, with dedicated personnel on duty. The door must be strong and beautiful, and must have the company name or logo. The logo must include the words "Longji Taihe", the door pillars and the ceiling. It is fully covered with aluminum-plastic panels, with a total height of not less than 4.5M, and a closed door with a total width of not less than 6.5M.

5. Worker dormitories and office areas must be built separately. The buildings must be made of colored steel, and the filling material must be rock wool. The appearance must be uniform in color. The open space in front of the office must be hardened with concrete, and the space in front of the window must be hardened. Place a flower pond. Staff dormitories should be located in a ventilated and dry location, equipped with daily necessities counters, outdoor trash cans, and a cool clothing area.

6. The canteen should be located in a ventilated and dry location, 50MM above the natural ground, and 30M away from toilets, garbage stations, and toxic and hazardous places. An independent production room and storage room should be set up in the canteen, and there should be a rat-proof baffle of no less than 20cm below the door. The stoves and surroundings in the canteen production room must be covered with ceramic tiles, with a height of not less than 1.5M. The hardened floor must have anti-slip treatment, sewage discharge facilities must be provided, an oil leakage pool must be set up, and sealed dirty buckets must be installed. A canteen sanitation responsibility system and responsibility must be established. Implement the appointment of people and strengthen management.

7. The clearance of the toilet shall not be less than 30M. The materials shall be made of red bricks. The roof shall be made of anti-smash and rain-proof materials. The hardened floor shall be treated with anti-slip treatment. The flushing facilities shall be set up. The setting system requires a dedicated person to be responsible and regular cleaning is required. Clean the septic tank.

8. The processing and production shed at the construction site is required to be erected with a steel structure. The ceiling is required to have a buffer layer and rainproof requirements. The height is not less than 3M, and it is enclosed on all sides. A slogan is hung in front of the roof eaves, and the other three sides are made of wooden boards. To maintain the red and white paint decoration, all protective shed floors must be treated, there are no potholes and uneven spots, and red bricks and stones are used to pave the ground. The electrical facilities in the shed are solid and stable, with unified heights. One machine, one box, one gate and one leakage protection are used, and the mechanical operation is The procedures should be displayed in a prominent position, a responsibility system should be implemented, and a designated person should be responsible.

9. The on-site materials must be covered with signboards. It is required that the height is not exceeded. Safety slogans and safety knowledge must be displayed at prominent locations on the construction site. A smoking room must be set up no less than 10m away from the site. The ground must be hard. The stone treatment has a rain-proof ceiling and fire protection settings. 10. There should be no less than 2 waste recycling stations at the construction site, each with an area of ??no less than 20M square meters, surrounded by iron sheets, and regular clearing and transportation should be ensured.

11. Banners, colorful flags, safety signs, and warning slogans at the construction site must be complete and hung neatly, and must be updated every 2 months.