Report to the leaders and experts on the construction of the project you are responsible for.

Start with the following points:

I. Overview of the Project:

For example:

1, construction site

2, construction engineering level

3. Design service life

4. Design fire resistance rating

5, building seismic fortification cracks

6, building structure floor type

7. Total construction area

8. Building basement area

9. Number of building floors

Second, the contractor:

construction unit

Design organization

Supervision unit

Supervision unit

construction organization

Three, about which branch structure is completed:

In strict accordance with the design drawings and construction acceptance specifications and procedures, our company has completed all the work contents from a certain day to a certain day. For example, in civil engineering, the project * * * produced 482t of binding steel bars, poured 4320m3 of concrete and filled 8 19m3 of wall masonry, and successfully completed the construction of many subprojects.

Fourth, the project quality control:

1. Control of raw materials used in this project: After the reinforcement enters the site, it has been jointly accepted by the construction, supervision and construction, and recorded. Steel bar should have factory certificate and inspection report when entering the site, and it can be used in the project only after being sampled and rechecked by the supervisor. The welded parts of steel bars have witnessed on-site sampling inspection, which meets the standard requirements. All kinds of aerated concrete blocks and cement bricks have factory certificates and inspection reports.

Main structure of a section 16-28 and b section 1-6 201to 20 15 July 20, 20 165438:

Standard input tonnage

6.5 7 2 1.7 ? 8 12 16 1.2

10 13 1 1 1.8 ? 12 6 37.3

14 8 59.8 ? 16 4 12.2

18 3 13 ? 20 5 20.8

22 5 23.4 ? 25 4 3 1.2

492.4 tons of steel bars have entered the site, and all of them have passed the second interview.

Collection of engineering quality control data;

Number, project name, quantity (copies), and verification result of witness sampler.

1 commercial concrete control data 69 Li Yuanji qualified.

2 steel factory quality certificate 43 Li Yuanji qualified.

3 rebar retest report 43 Li Yuanji qualified.

4 electroslag pressure welding retest report 26 Li Yuanji qualified.

5 cement factory certificate, 3 Li Yuanji qualified cement retest report.

7 Stone Re-examination Report 1 Li Yuanji Qualified.

8 sand retest report 1 Li Yuanji qualified.

9 aerated concrete block certificate inspection report and second interview report 2 Li Yuanji qualified.

10 KP 1 type perforated brick certificate inspection report and retest report 3 Li Yuanji is qualified.

1 1 cement brick certificate, retest report 1 Li Yuanji qualified.

12 C30 and C25 concrete mixture ratio 1 Li Yuanji is qualified.

13 M 15, M 10, M7.5, M5 mixed mortar mixture ratio 4 Li Yuanji qualified.

14 detection of anchorage pullout force after Li Yuanji passed through concrete structure.

15: The thickness of protective layer of steel bar was tested 2: Li Yuanji was qualified.

2, steel subdivisional work:

The specifications, spacing and fabrication of the main structure reinforcement comply with the design requirements and construction specifications. Reinforcement binding, anchorage length, lap length, reinforcement welding and skeleton geometry all meet the quality acceptance standards of reinforcement engineering, and all of them have passed the acceptance of concealed works.

69 concealed engineering acceptance record * * *; 69 commercial concrete control materials, 69 acceptance; 43 steel certificate and retest report; 26 copies of electroslag pressure welding.

3, the template component project:

(1), material control, according to the construction scheme, the shear wall adopts large formwork, the roof adopts 6×8cm square wood and 15mm thick multi-layer mirror panel, and the support system adopts? 40 steel pipe, and under the witness of the supervisor, provide the factory certificate and material certificate to ensure that qualified materials are used in this project.

(2) Erecting wall formwork, the main control: hoisting large formwork safely, positioning steel bars according to the construction plan and each pay-off, and erecting large formwork in place according to the control line. According to the construction plan, the main roof control: the spacing between the vertical poles of the support system should be within 1.0m, the horizontal poles, sweeping poles and 250×250mm wooden mats at the bottom of the steel pipe should be tied firmly, and the elevation of the control panel should be adjusted with adjustable screws to avoid safety accidents caused by formwork instability.

4, concrete component project:

(1), the concrete entity is vibrated compactly, the surface is flat and vertical, the concrete section size is correct, there is no honeycomb pits, and the steel bars are exposed, which meets the requirements. The concrete strength, grade and mixture ratio of shear wall and beam slab all meet the design requirements, and the concrete slump has been tested 69 times on site, which meets the construction requirements.

(2), reinforced concrete protective layer thickness detection:

Party A entrusts Baoji Hui Zhen Construction Engineering Quality Inspection Co., Ltd. to inspect the concrete protective layer. On August 20th 11,1,16-A, the 28th floor was tested with 650 marks, and the pass rate was 6 15, with 94.6%.

20 11August1,B-section podium, * * * measured 280 points, qualified 267 points, and the qualified rate was 95.3%. The result was judged to be qualified.

5, infilled wall masonry engineering:

According to the Technical Specification for the Application of Autoclaved Aerated Concrete Building and the requirements of JGJ/T 17-2008, the infilled wall is vertical and flat, the mortar joint is firm, the mortar is full, and the Rachel reinforcement and lintel constructional column of the wall meet the design requirements and specifications; Section B KPL perforated brick masonry meets the design requirements and specifications.

Stone inspection report 1 copy; 1 sand test report; Mortar mix ratio M 15, M 10, M7.5, M51;

Cement brick factory inspection report and certificate 1 copy, and passed the second interview; 2 parts of aerated concrete block; Cement factory inspection report and certificate of approval 3 copies, retest report 3 copies, all qualified;

The mix ratio of C30, C25 and C 15 concrete is1; Mortar test block 13 groups, of which 16-22 layer expires in 7 groups, qualified in 7 groups and expired in 23-28 layers in 6 groups; 6 groups of mortar test blocks in section B and 6 groups of qualified mortar test blocks;

6. The drawings of masonry Rachel reinforcement on June 27th, July 7th and August 27th, 20 165438 * * were approved;

7, wire tube laying subdivisional work:

The welding of lightning protection downlead and equipotential bonding meets the requirements of single-sided welding; 12 times d, double-sided welding, 6 times d requirements, buried and reserved conduit, distribution box installation, etc. Comply with the design requirements, specifications and safety standards; There are 66 inspection lots reserved for lightning protection grounding and electrical pipelines, including 54 blocks A and 2 blocks B/kloc-0, all of which are qualified.

The inspection report of concrete test block reaches the qualified standard after evaluation.

Standard curing test block of concrete: C30 44 group; C25 10 group;

Concrete blocks with the same conditions: C30 53 group; C25 10 group;

Layered and segmented with the same strength grade

Sample block

Series n

intensity

Average mfcn

Standard deviation sfcn strength evaluation standard (GBJ 107)

conclusion

Part number mnfcu ≥

1. 15 FCU . kfcu . min≥

fcu.k

Floor 16- roof c3044 37 0.135.4 "27 33.4" 25.5 qualified.

Second floor-C2510 32 0.6 30.9 22.5 28.122.5 is qualified.

8, settlement observation:

Construction unit: entrust the precision survey team of China Railway No.1 Engineering Group No.5 Engineering Co., Ltd. to conduct settlement observation on each floor according to the requirements of the specification. Up to now, it has been observed for 28 times, and the settlement observation result table has been sent to the construction site, with three reference points and ten observation points. The cumulative settlement is -7.0 1 mm, -8.28 mm, -7.93 mm, -7.99 mm, -7.20 mm, -5.57 mm, -6.87 mm, -8.73 mm, -9.46 mm and -5.92 mm respectively. The observation results show that no abnormal settlement is found.

Verb (abbreviation of verb) quality acceptance:

In August of 20 1 1 year, the project department, together with the construction unit and the supervision unit, carried out the main structure survey on floors A 16 -28 and B 1-6 of the comprehensive building. The measured items include: smoothness, verticality and section size of concrete surface, with 2 12 points actually measured. The qualified rate reached 9 1.5%, and the measured quantities and visual quality acceptance of the floors A 16 -28 and B 1-6 of the comprehensive building were generally rated as qualified.

Conclusion of intransitive verbs:

1, 16-28 floors, ***4 subdivisional works, with 289 inspection lots, including reinforcement 1 12 inspection lot; Template 1 12 inspection lot; 54 concrete inspection lots; Filled wall 1 1 inspection lot; Bid B: 1-6 * * 4 subdivisional work, with 66 inspection lots, including 24 inspection lots for reinforcement; Template 24 inspection lot; 12 concrete inspection lot; Masonry 6 inspection lot;

2. In view of the above construction quality, the main structure of this project is section B 16 floors-roof and 1-6 floors, and the project supervision is in place. Our project department can always take the project quality as the center, seriously accept the valuable opinions and suggestions put forward by supervision, construction and quality inspection units, and make timely rectification in place. This division has no quality hidden trouble, the project quality reaches the qualified standard, and the visual quality is good. Self-evaluation of sectional works of the main structure of section B/floors KLOC-0/6-28 and 1-6 of the comprehensive building is qualified, and now we urge quality inspection units, design units, survey units, construction units and supervision units to accept them.

Regarding the requirements of civilized production, we can talk about ten new technical standards of your site, all of which are very good.

You can talk about the following.

I. Project management objectives:

Second, the construction site management specification:

Third, the purpose of creating a civilized construction site

Fourth, the appearance of the field.

Verb (abbreviation of verb) working environment and environmental protection

Six, fire, explosion, gas

Seven, construction organization design and management

Eight, construction safety standards

Nine, excellent engineering quality

Ten, "three treasures" and "four mouths"

Eleven, building energy conservation and environmental protection application technology;

Twelve. Office and living environment

Just try it. I wish you success! .