Minutes of safety inspection meeting

Time: December 12, 215

Venue: conference room on the third floor

Moderator: Wang Kai

Participants: Zhang Xuehui, member of the safety committee of the head office, Zhang Jingang Wang You, Long Yuan Company, Wang Kai, Sun Xiaodong, Zhang Xu, Huang Xin Recorder: Huang Xin

Meeting contents:

The leaders of the assessment team of the safety committee of the head office first issued the contents and scoring standards for Longjiang traffic inspection.

General Manager Wang Kai made a detailed report on the work safety in 215 to the members of the safety committee of the head office. Wang Kai, the chairman of Long Yuan Company, explained in detail the implementation of the company's annual production safety deployment. Regarding the two problems mentioned in the report, the company has no guard security, the vehicle has a long service life and there are security risks. Zhang Xuehui, a member of the assessment team of the Safety Committee, said that the arrival of security personnel is an important part in the implementation of the company's security work. Security personnel must be set up as soon as possible, and relevant personnel should be assessed and relevant systems should be established to require the company to implement them as soon as possible to eliminate potential safety hazards. For the problem that the vehicles are old and the driving safety of vehicles can't be guaranteed, Zhang Xuehui requires that the company must strengthen the driver's driving skills training, establish the awareness of safe driving, and strictly abide by the traffic laws and regulations. The car condition of the company is relatively old, and it is difficult to maintain it. However, it is difficult to solve the problem because the vehicle management is not within the leadership of the safety committee. Zhang Xuehui requested to implement the safety documents of the head office, sign in at the safety meeting, make preparations before the meeting and draw up a speech. Write the minutes of the meeting in time after the meeting, and thoroughly understand the hidden problems raised in the meeting content and solve them reasonably. At the meeting, Zhang Xuehui emphasized the construction safety of the project under construction in the Anda service area of Harbin-Dalian Expressway, and demanded that the policy of "safety first, prevention first" should always be implemented, the responsibility certificate for safety guarantee should be signed step by step, and a strict accountability system for safety production should be established. Full-time security officers shall be set up at the construction site. And set up safety warning signs and safety slogans in key parts.

Zhang Jingang, a member of the assessment team of the Safety Committee, requested to do a good job in the distribution management of safety documents of superior units, so as to ensure that the documents are circulated, executed and filed without any mistakes. In particular, the safety information on the construction site should be strictly implemented in accordance with the standards. After the implementation of the safety and security work, photos should be taken at the first time, and the electronic files should be managed well, so that they are well-founded and implemented to those responsible. Zhang Jingang requires drivers of the company to strictly abide by the safety driving code and do a good job in driver training. Drivers must abide by the law, stop driving by the rules, walk by the line and be punished by the rules.

Wang You, a member of the assessment team of the Safety Committee, asked the company to do a good job in employee safety training, and regularly send safety officers to advanced units for training and study when conditions permit.

Wang Kai, the general manager, said that he should pay close attention to the opinions put forward by the assessment team of the head office's safety committee, and made a concluding speech. Wang Kai emphasized that "safety management is no trivial matter, and safety responsibilities should be re-implemented" is the company's consistent policy on safety work, and the company should learn from the experience of the head office's safety management to make safety management work reach a new level. Strive to create a better safety production environment.

Heilongjiang Communications Long Yuan Investment Co., Ltd.

December 12, 215

Minutes of Safety Inspection Meeting [Chapter 2]

Project Supervision Department Document of Nanguang Luolongwan No.1 Project Phase I

No.: LLW-YQ-XTH-15

Nanguang Luolongwan No.1 Project Phase I Project

Meeting topic: Safety civilization inspection summary meeting

Meeting place: Shunjie meeting room

Meeting time: March 215. Division: Zhang Hao and Wang Hongyu

Shanghai Tianyou Engineering Consulting Co., Ltd.: Zhou Jinhuan, Zhou Zhizong, Zhou Guangsheng, Lu Yongping Jiangsu Shuntong Construction Group Co., Ltd.: Hu Hongchun, Cai Yunfeng

Zhejiang Shunjie Construction Group Co., Ltd.: Xu Lierong, Gu Fengguang

Chairman of the meeting: Zhou Jinhuan

Content of the meeting:

Chairman:

In order to achieve safety and no accidents during the construction of the first phase of Nanguang Luolongwan No.1 project, and the safety and civilization of the construction site meet the standards of relevant safety inspection regulations, a monthly safety and civilization inspection is organized at regular intervals, and after the inspection, the existing problems on the site are summarized, and the person responsible for rectification is determined within three days. Those who fail to complete the rectification on time shall be punished according to the punishment regulations ordered in the safety and civilization inspection system. There are problems on site:

Shuntong:

There is no safety hook device and no grounding pile in the mixer tipper beside Room 1 and 1#; 2. Oxygen bottles and acetylene bottles on the south side of Room 11 are stacked in the first phase;

3. The cables at the entrance of the power distribution room are messy and have no protective measures;

Shun Jie:

22 volts and 38 volts are mixed in the third-level distribution box on the landlord side of No.1 and No.13;

The tower crane in Room 2 and Room 13 has no special electric box, and the tower crane commander leaves his post without authorization;

3. There is no fire extinguisher in the woodworking shed, and the grounding is not standardized;

4. Next to the secondary distribution box on the south side of the clubhouse, 6 connectors are connected on the cable about 5 meters. Requirements put forward by the owner:

1. Distribution boxes at all levels on the site should be arranged according to the temporary electricity consumption plan for construction;

2. Report the group hoisting scheme of tower crane;

3. Put up safety and civilized slogans and set up safety warning signs at the site;

See Safety Civilization Checklist for details of the person responsible for rectification and the completion time of rectification

Shanghai Tianyou Engineering Consulting Co., Ltd.

Project Supervision Department of Nanguang Luolongwan No.1 Phase I

Minutes of Safety Inspection Meeting on March 22, 215

On August 6, 215, Yongxin Jiayuan Project Department of Hebei Construction Group held a mobilization meeting for safety inspection. The meeting was presided over by Mei Deqing, and all the management personnel of the project department attended the meeting. The meeting carefully studied the requirements of the safety inspection activities of the Construction Bureau, formulated the implementation plan of the safety inspection activities of the project department, and mobilized all. The summary of the meeting is as follows:

1. Mei Deqing, the manager of the project department, made clear the requirements of this activity:

1. The management of the project department at all levels made clear the division of labor;

2 do a good job in the investigation and rectification of potential safety hazards;

3 collect and report the activity information.

4 strict accountability: the team and individuals who fail to implement the safety inspection activities, leave a dead end in the investigation of all hidden dangers, and find problems that are not rectified in time and thoroughly will be dealt with severely.

2. Establish a leading group for the safety inspection activities of the project department:

Team leader: Mei Deqing

Deputy Team Leader:

Members:

3. Inspection requirements

The project department should attach great importance to it, act quickly, take the lead by the project manager, and immediately engage in the safety inspection activities to ensure the safety and stability of Yongxin Jiayuan project construction, 1

. The management personnel of the project department strictly implement the responsibility system for safety step by step. The communication of safety information among the management personnel of each team in the project department should be strengthened, so that any potential safety hazard must be communicated with the project department in time, regardless of whether the team is involved or not. To do a good job in the investigation and rectification of potential safety hazards, we should pay attention to practical results, grasp the key points and key points of safety work, sort out the problems, blame people and rectify within a time limit. The team project department will give serious treatment to the team that fails to implement the safety and quality inspection activities, leaves a dead end in the investigation of potential safety hazards, and finds that the problems are not rectified in time and thoroughly. During the safety inspection activities, the project department will give economic penalties to teams and individuals who are not in place and irresponsible. Project department personnel deduct the bonus at the end of the year. Do a good job in the dynamic account of personnel in each department during the inspection. Do a good job in dynamic accounting of mechanical equipment. Improve the safety and quality awareness of technicians and workers in various positions. Do a good job in the investigation of potential safety hazards during this activity, and do a good job in emergency preparations such as fire prevention and windproof.

IV. Summary of the meeting

Mei Deqing, the project manager, summarized the mobilization meeting of the safety inspection activity, which was requested by Qinhuangdao Construction Bureau and Hebei Construction Group Company. Through this inspection activity, the safety awareness of the project department and the construction team was enhanced and the work level was improved. Participants in the project department also stated that they fully understood the importance of safety inspection, and they must sum up better and more reasonable safety management experience and methods during the inspection, go all out to carry out this safety inspection activity, and stick to this strict requirement for a long time through this activity.

2

Minutes of Safety Inspection Meeting [Chapter 4]

Time: August 15th, 211

Location: Maying Coal Mine Meeting Room

Chair: Yan Wen

Attending: Sun Zhifeng, Wang Pengfei, Kan Guodong, Shao Min, Luo Shengshan, Jia Hui

Peng Weimin, Jiang Xingguo, Han Dongbin, Zhao Jinfu.

theme of the meeting: mobilization meeting for "Hundred Days Inspection of Safety in Production"

Contents of the meeting:

1. Mine Manager Wang conveyed Shan Zheng Mei Zi No.21124 (Notice on Printing and Distributing the Work Plan of Carrying out Hundred Days Inspection of Coal Mine Safety in Shanyin County), and the meeting decided that the safety supervision station would be specifically responsible for organizing, guiding and urging all units to carry out the "Hundred Days Inspection of Safety in Production" and be responsible for this activity.

2. At the meeting, Director Yan asked:

1. Strengthen leadership, mobilize deeply and make careful arrangements. The heads of various departments personally went into battle, participated in the formulation of feasible work plans, widely mobilized all forces, took effective measures, and actively carried out the investigation and rectification of various hidden dangers.

1

2. The safety supervision station should strengthen publicity and improve the safety awareness of employees; It is necessary to widely mobilize employees to participate in safety production work such as investigation and rectification of hidden dangers to ensure the effectiveness of the activities.

3, to clear responsibilities, strict standards, focus. All relevant departments and teams should be positioned according to their functions to ensure the smooth development of this activity.

4. Intensify the inspection of production safety. All units should work hard and continue to do a good job in safety inspection in strict accordance with the requirements of superiors. All kinds of potential safety hazards should be rectified immediately, and production should be stopped for rectification if necessary. According to the assessment content of the "anti-three violations" activities in July, the "Investigation and Management System for Safety Production Hidden Dangers in Maying Coal Mine" was strictly implemented, and the "closed" management of safety hidden dangers was adopted, so as to achieve "five implementations" and nip the hidden dangers in the bud.

5. Continue to conscientiously implement the spirit of documents No.21129, No.21133, No.2111 and No.21134 of Jin 'an Power Generation Company to ensure the safe and steady development of our mine.

6. Finally, I hope that through our concerted efforts, we can do a good job in the inspection of this activity, and take it as a new starting point for safety production, pay close attention to the implementation of the safety production work system and daily management, promote the establishment and improvement of the long-term mechanism for safety production, and completely reverse the passive state of safety production management.