Joke Collection Website - News headlines - How to determine the location of distribution point in working face? What are the requirements for the equipment layout of the distribution point?

How to determine the location of distribution point in working face? What are the requirements for the equipment layout of the distribution point?

Determination of the location of distribution points in the working face: the working face is calculated from the cushion. This drawing generally does not need to calculate the working face, because the cushion is already 200 wider than the foundation. When the foundation material is brick, the working face is generally two sides of the foundation 200.

What are the requirements for the equipment layout of the distribution point?

1, power distribution maintenance (construction) operation, when the working ticket issuer or working director thinks it is necessary to conduct on-site investigation, he should organize on-site investigation according to the work task and fill in the on-site investigation records.

2. The on-site investigation shall be organized by the working ticket issuer or the person in charge of the work, and the relevant personnel of the person in charge of the work, the equipment operation and maintenance management unit and the maintenance (construction) unit shall participate. For operation projects involving multiple disciplines, departments and units, the competent departments and units of the project shall organize relevant personnel to participate.

3. On-site investigation should check the power outage range required for maintenance (construction) operation, reserved live parts, installation position of grounding wire, adjacent lines, crossing, multi-power supply, self-provided power supply, underground pipeline facilities, working site conditions and other dangerous points that affect the operation, and put forward targeted safety measures and precautions.

4. After the on-site investigation, the on-site investigation records shall be sent to the working ticket issuer, working director and relevant parties as the basis for filling in and issuing the working ticket.

5. Before starting work, the person in charge of the work or the person issuing the working ticket shall review the on-site investigation. If there is any change from the original investigation, the corresponding safety measures shall be revised and improved in time.