Joke Collection Website - News headlines - How to write the crane evaluation report materials?
How to write the crane evaluation report materials?
Scheme of transforming ordinary crane into metallurgical crane
A, electric single beam crane transformation scheme
According to the LD crane provided by your company and the spirit of the national (Quality Inspection Office No.2007375) document, our company now makes the following plans:
Manually dismantle the connecting cable of the crane, and rent the crane and truck crane to transport it to the construction site.
This project needs two mechanics, two riveters, an engineer, a person in charge, a security officer and two electricians.
Safety technical requirements: All personnel involved in this phase of the project shall carry out the construction in strict accordance with the safety operation specifications of this type of work, and illegal operation is strictly prohibited.
Technical standards for the construction of this project:
The trolley motor adopts high-temperature resistant motor with insulation grade H and protection grade IP54.
The trolley sliding cable adopts high temperature resistant cable.
The motors of electric hoist trolley are IP54 and H-class motors.
Equipped with overload limiter, radiation shielding, double braking and double safety limit.
The steel wire rope adopts high temperature resistant steel core steel wire rope.
The hook wheel of the hook is made of cast steel.
The control adopts ground operation and remote control operation.
Completion acceptance:
After the crane transformation, the transformation department and the user should go through the completion acceptance procedures, fill in the acceptance report carefully, notify the tenderee to organize relevant departments to carry out the acceptance, and deliver it to use after it is qualified.
Second, the double beam crane transformation scheme:
1, metal structure:
(1) The metal structure is intact, and the static stiffness of the main beam must meet the standard requirements.
(2) The metal structure shall be welded (connected) reliably, and the cab shall meet the requirements of safety standards and be fixed reliably.
(3) The reconstructed hoisting machinery must pass the dynamic load and static load tests and meet the standard requirements.
(4) The lifting weight and dangerous parts shall be marked completely.
2. Lifting mechanism:
(1) motor: the whole vehicle adopts special motor for metallurgical hoisting machinery, with insulation grade H and protection grade IP54. The main hoist motor (single motor) should be selected according to M7 working system. When the crane exceeds 20t (including 20t), an overspeed protection switch shall be installed at the shaft end of the motor.
(2) Reducer: The main hook reducer is selected with medium-hard tooth surface or above (including medium-hard tooth surface), and the assembly type is high-speed shaft with double output shafts. Two sets of independent brakes (double brakes) are installed at both ends of the reducer.
(3) The main hoisting drum is made of cast steel or steel plate.
(4) Steel wire rope: High-quality metal-core high-temperature resistant steel wire rope is selected, with a safety factor of more than 6 times.
(5) Pulleys and hooks: All pulleys of the crane are cast steel or rolled with safety shields.
3. The size of the trolley operating mechanism shall be M6 or above. (including M6)
4. Electrical appliances: safety protection
(1) The main hook is equipped with a weight limiter and a digital display on the screen to realize overload limit protection and alarm functions.
(2) The main lifting mechanism is equipped with heavy hammer and rotary lifting and lowering limiters (double limiters), and there are protective switches such as lifting limiters, truck and truck running limiters, overspeed protection and zero protection, and the switches of each mechanism should be sensitive, reliable and safe.
(3) The main hook adopts SCR stator voltage regulation and speed regulation, energy consumption braking and SCR power supply. The control panel of the main hook is equipped with a positive and negative contactor, which has the safety functions of electrical interlocking and mechanical interlocking to prevent the motor from being powered off while the brake is still energized, thus causing stall. One set of electrical equipment powered by the main hook motor is provided with a bypass safety device. If one set of electrical equipment fails, the other set of electrical equipment can work normally.
(4) Single control lifting limit, single control main lifting double brakes, regardless of size, casting crane main lifting control panel.
XXXX crane group co., ltd
2XXX year x month x day
Reconstruction construction scheme of crane
Preparation before construction
I. Personnel Organization
According to the workload of crane renovation and repair in your company, our company plans to invest 6 site managers and related technicians, namely 1 project manager, 1 engineer, 1 inspector and 6 skilled workers (including 2 electricians, 2 fitters and 2 welders).
Second, the transformation site has the conditions.
The reconstruction site should have the conditions of three links and one leveling, and have sufficient use area and hoisting capacity. To meet the needs of lifting and overturning in the transformation process.
Three, crane repair tools and inspection instruments
(1) Main construction equipment
Main construction equipment
Serial number equipment name equipment capacity equipment quantity
1 3 5t and 3t inverted chains.
2 jacks, 32t and 8t, 2 each.
3 welding machines 2 manual welding machines
4 sets of locksmith tools 10.
5 6 sets of complete sets of electric tools
6 2 sets of gas cutting tools.
(2) Main inspection instruments and measuring tools
Mainly check the status of test instruments and equipment.
No.: name of equipment, capacity of equipment and quantity of equipment.
1 theodolite J6E 1
Level 2 DS3 1
3 boxes horizontal 250×250 1
4 megohmmeter SL-500V, SL- 1000V 1
Five steel tape measures are 30m and 50m 1 respectively.
6 square (level 2 or above) 3 15×200 3
7 vernier caliper 0.02mm (0.03mm) × 0-1000mm2
8 feeler gauge 2
9 steel wire φ 0.49-φ 0.52 200m
10 heavy hammer 150kg 2
1 1 micron 0-700 mm 1
12 dial indicator 0 0- 10/0min 1
13 welding inspection ruler φ40 2
14 steel wire bracket and pulley 2
15 ultrasonic damage control instrument 1
Fourth, the work arrangement before construction
1, clean up all items and objects that hinder the construction on the site;
2. Stop the crane at a suitable position, cut off the power supply and fix the traveling wheels to prevent the cart from swimming during inspection and construction.
3. Set construction warning signs and isolation belts according to the construction safety site;
4. Transport the machinery, materials and accessories used to repair the crane to the construction site, and connect the power supply of the construction equipment.
5, according to the construction needs to build scaffolding.
Five, crane equipment inspection items before repair
See attached table for main inspection items and technical standards (crane overhaul items and technical standards).
Six, crane equipment maintenance before the technical preparation order:
Crane repair
Bidder:
Seven, quality assurance measures
1, establish and improve the construction management system
1) Strictly implement the system of the blue prints.the design of construction drawings and the technical disclosure system of the construction site, carefully organize the construction, ensure the product quality with the quality of work, check the key parts and key working procedures when raw materials, equipment and accessories enter the factory, and carry out the construction in strict accordance with the construction drawings, construction specifications, standards and technical documents;
2) Construction personnel of special types of work must hold relevant certificates;
3) Strictly implement the "three inspection systems" of quality, that is, self-inspection, mutual inspection and special inspection, and carefully fill in the inspection records and sign them for filing. Concealed works must be checked and confirmed by on-site instructors, supervision departments and special inspectors of equipment manufacturers, and recorded before they can be transferred to the next working procedure.
4) Strengthen the filing system of technical files to ensure clear information after the project is completed.
Eight, the construction progress guarantee measures
1, earnestly study relevant laws and regulations, strengthen safety technology training, and improve the quality of the workforce.
2. Break down all parts of the project layer by layer and implement them to those responsible.
3, engineering and technical personnel to ensure that the technical work to the forefront of the construction, to ensure the smooth progress of the project construction.
4, strictly implement the construction organization and quality standards, so that the construction personnel know the construction methods and standards, to ensure that each project is a success, to avoid secondary operations.
5. In case of special circumstances during construction, the next operation can only be carried out after the approval of the leader of the competent factory.
Nine, safety technical guarantee measures
1, strictly abide by the Technical Specification for Safe Construction of System Installation and related labor safety laws and regulations.
2. All personnel involved in the construction must study hard and be familiar with the construction organization plan. Firmly establish the idea of "safety first". During the construction, there must be a special person under unified command, hold a pre-shift meeting strictly, explain the safety precautions, clarify the tasks, construction methods and quality requirements, and conduct safety inspection throughout the process to eliminate hidden dangers of accidents.
3, construction personnel should wear complete safety labor protection articles, the correct use of seat belts, who found violations, immediately stop their work.
4. Cut off all power supplies at the upper part of the workshop, and put up a warning sign "No sealing, construction is under way" until the whole machine is installed and restored.
5, the installation site set up security cordon and fence, to ensure the normal operation of other equipment, and there are obvious safety warning signs.
6. Use the spreader correctly and fix it firmly, pay close attention to the movement of installation equipment and tools, especially the lifting setting, whether the fixed connection of steel wire rope and binding joint is intact and firm, and the braking reliability of the brake.
7. Choose the hoisting focus and hoisting auxiliary structure, pay attention to the correct positioning of various parts of the vehicle and the correct connection in the air, especially to ensure that the connectors are firm and effective and conform to the installation specifications.
8. Fire prevention measures should be taken for on-site welding and various fire sources, and all gas cutting and welding work must be supervised by special personnel.
9, oxygen and acetylene bottles should be put into use according to the provisions of the state.
10, electrical installation must be carried out in strict accordance with national and industrial building safety standards.
1 1. There must be full-time or part-time security personnel.
12, safety construction must be ensured according to safety requirements.
- Previous article:Ancient style wedding blessing words
- Next article:What is the most interesting word on the cake?
- Related articles
- What is the idiom of running errands?
- Choose 45 sentences to express your love for your husband
- Where is Dali suitable for enjoying the snow scene?
- The copywriting language of the dinner party is clean and neat.
- Two slogans were put forward: "the time to learn from foreigners and master their skills in controlling foreigners" and "the time to settle down when you are busy outside"
- The slogan on the wall of the tree hole
- How to do a good job in media advertising marketing
- Is Hangzhou Bank listed?
- GDP slogan
- A passage describing Longmen Grottoes