1. Leveling layer

(1) Ash cake and screed: plastered with cement mortar on the same layer.

⑵ Brush plain cement slurry combination layer: cement mortar plastering on the same layer.

(3) Spread cement mortar screed-coat: The screed-coat shall be made of 1: 3 hard cement mortar, which shall be leveled first, then leveled with a ruler according to the screed, and then leveled and compacted with a wood trowel to make the surface smooth and dense and keep rough. After the leveling layer is plastered, water it for at least one day the next day.

2. Block mosaic

(1) After a day's leveling layer maintenance, vertical and horizontal or pattern chalk lines will pop up on the leveling layer according to the design requirements, and then cut strips according to the chalk lines.

⑵ Brush the lower part of the frame with pure cement slurry into a splayed angle, embed the long seat firmly (at an angle of about 30 degrees with the leveling layer), and bury the iron wire worn by the copper bar. The application height of pure cement slurry is 3 ~ 5 mm lower than that of grid strip. Grille bars shall be embedded firmly, with tight joints and top surfaces on the same plane, and straightness shall be checked through lines.

(3) After framing, water curing shall be started every 12 hour, and the curing shall last for at least two days.

3. Wipe the stone slurry surface

Cement slurry must be measured in strict accordance with the mixture ratio. Color terrazzo should first dry mix white cement and pigment repeatedly according to the mixture ratio, and after mixing, it should be carefully screened for many times, so that the pigment can be evenly mixed in white cement, and the reserve of slurry filling can be adjusted. Finally, it should be evenly mixed with stone rice according to the proportion, and stirred with water.

polish

(1) Mechanical grinders should be used for large-scale construction, and small-scale portable grinders can be used for grinding small areas and corners. When mechanical grinding is not available locally, manual grinding can be used. Grind before grinding. If the stone particles are not loose after grinding, grinding can be started. In general, grinding time is related to temperature and cement grade.

⑵ The polishing operation should adopt the method of "two slurries and three grinds", that is, the whole polishing process is divided into three polishing and two slurry filling.