After the project is completed, how to check the quantities and unit prices in the Final Account of Construction Project provided by the constructor?
1. If the contract stipulates that the unit price is not adjusted, then the unit price can only be based on the budgeted unit price;
2. If the unit price is allowed to be adjusted according to the contract, it shall be adjusted by referring to the price adjustment method agreed in the contract; If the price adjustment method is not stipulated in the contract, it is a bit troublesome to negotiate with the construction party;
3. If a project is not included in the budget due to changes, there are three ways to determine the unit price of the project. You can look at the FIDIC contract terms, which are very simple;
On the audit of engineering quantity:
1, review and compare the engineering measurement list signed by all parties;
2, check all kinds of change files;
3, the project site measurement;
Because I don't know what your project is, I can't be specific.
- Related articles
- When someone asks you what brand of your watch is, how to answer humorously?
- In Yongzheng dynasty, how did Kangxi know that the old eight changed into fourteen dead eagles?
- A sentimental copy [recommendation] that is a metaphor for love but is not allowed to talk about it.
- Write marriage sentences
- How to write five short self-evaluations?
- The immortal who is suitable for excerpt surprised the original sentence.
- What did you eat when you were the hungriest?
- What is the meaning of the sword?
- What are the matching friends who send roses?
- A villager in Qinhuangdao did not cooperate with the epidemic prevention test, killed a staff member and then escaped. Why did this villager do this?