Construction technology and matters needing attention of red brick wall

Red brick wall is a durable wall, but its relative cost is high. This paper will introduce the process and matters needing attention of red brick wall construction to help readers better understand the construction process.

Brick treatment

Bricks and blocks shall be watered and wetted two days before construction. Never cast-in-situ use. At the same time, it is forbidden to dry bricks directly on the wall.

Mortar use

Masonry mortar should be mixed and used now, and it will be used up within 3 hours after mixing. If the highest temperature during construction reaches 30℃, or even higher, then all the mortar needs to be used up within two hours.

Wall height

When building a wall, it shall not exceed 1.8m every day, and it shall not exceed 1.2m in continuous rainy days. Masonry mortar generally adopts medium sand, and the proportion of sand consumption is strictly controlled according to the design label of mortar.

Bricklaying technology

According to the played line, carefully check the size, and then proceed to the next step of bricklaying. According to the bricklaying method of one shovel, one brick and one hug, bricklaying must be carried out according to the line, and the horizontal and vertical mortar joint is generally 10 mm, but it should not be less than 8mm and not more than12 mm. In the process of operation, self-inspection should be carefully carried out, and if there is any deviation, it should be corrected at any time.