Introduction to Futong Expressway?
Futong Expressway is a provincial expressway between Jilin Province and Liaoning Province, numbered S10. The starting point is in Tonghua City, at the provincial boundary between Wangqingmen Town, Xinbin County, Liaoning Province and Xiapai Village, Tonghua County, Jilin Province, 96.828 kilometers within Liaoning Province. The territory of Jilin Province is 45.677 kilometers. Zhongda Consulting consulted the CBI Construction Network information to obtain relevant information about the Futong Expressway:
The Futong Expressway (Fushun to Tonghua Expressway) project in Liaoning Province has a total length of 94.75 kilometers, starting from the Shenji Expressway in the west The Nanzamu hub interchange reaches Xinbinwang Qingmen Town in the east and connects with the Jilin Tonghua-Xiapai Expressway. The project is designed according to the standard of a two-way four-lane fully enclosed expressway. The driving speed is planned to be 100 kilometers per hour. The estimated total project length Investment of 4.8 billion yuan. The start of construction of this project will play an important role in improving the highway network in Liaoning Province, improving the transportation infrastructure conditions in the eastern part of Liaoning Province, strengthening economic exchanges between Liaoning and Jilin provinces, and promoting the economic development of areas along the route.
Futong Expressway - Basic Content
1. Basic situation of the project This project is located in the mountainous area in eastern Liaoning Province, starting from Shenji Expressway (K64 500 Wangqingmen Town, Fushun City ), passing through Wangqingmen Town, Xinbin County, Yongling Town, Muqi Town, and Shangjiahe Town to the end of the project, Nanzamu Town, Fushun City, with a total length of 94.4 kilometers.
The project has 3 service areas, 1 maintenance area, and 5 toll stations, namely Wangqingmen Service Area, Yongling Service Area, and Nanzamu Service Area, with a total construction area of ??17,418 square meters; ( Wangqingmen) main line toll station, Xinbin toll station and maintenance area, Yongling toll station, Muqi toll station, Shangjiahe toll station, with a total construction area of ??4470 square meters. The total project cost is 134 million yuan.
II. Project progress
(1) Project completion investment status
As of the end of this year, the Wangnan Expressway traffic management facilities project has completed a total investment of 51.76 million yuan yuan, accounting for 38.6% of the total project cost of 134 million yuan. The specific investment amount completed in each contract section is as follows:
The cumulative investment in the first contract section (Shenyang Overseas) is 16.52 million yuan, accounting for 29% of the total project cost of 57.44 million yuan; the total investment in Chapter 100 is 570,000 yuan, Wangqing The gate service area has completed a total of 12.05 million yuan, accounting for 35 of the project cost of 34.2 million yuan. The main line toll station has completed a total of 3.07 million yuan, accounting for 33 of the project cost of 9.44 million yuan. The Xinbin toll station and maintenance area have completed a total of 280,000 yuan. Accounting for 2% of the project cost of 11.26 million yuan.
The cumulative investment in the second contract section (the second construction of Jindi) is 35.24 million yuan, accounting for 35% of the total project cost of 99.8 million yuan. The Yongling Toll Station has completed a total of 1.42 million yuan, accounting for 5.26 million yuan of the project cost. of 26. The Yongling service area has completed a total of 14.85 million yuan, accounting for 35% of the project cost of 42.98 million yuan. The Muqi Toll Station has completed a total of 900,000 yuan, accounting for 21% of the project cost of 4.15 million yuan. The Shangjiahe Toll Station has completed a total of 1.76 million yuan, accounting for 44% of the project cost of 4.01 million yuan. The Nanzamu Service Area has completed a total of 14 million yuan, accounting for 45% of the project cost of 30.84 million yuan.
(2) Completion of project quantities
1. The first contract section (Shenyang Overseas): 83% of the site earthwork work has been completed, 88% of the foundation work has been completed, and 46% of the masonry work has been completed. Reinforced concrete work completed43. Among them:
(1) Wangqingmen Service Area: The earthworks and foundation projects in the south and north districts have all been completed, and the main works in the south district have been completed; the gas stations, dormitories, and auto repair shops in the north district have been completed. The main work of the dormitory building and comprehensive building has been completed, but the masonry work of the dormitory building, auto repair room and comprehensive building has not been completed; the foundation of the fire pool has been completed.
(2) Main line toll station; the earthworks, foundation engineering, and main engineering of the site have been completed, and the pouring of toll canopy columns has been completed.
(3) Xinbin Toll Station: 52% of the earthwork work in the site area has been completed, and other basic works and main works have not yet started.
2. In the second contract section (Jindi Second Construction), 86% of the earthwork work has been completed, 100% of the foundation work has been completed, 52% of the masonry work has been completed, and 93% of the reinforced concrete work has been completed.
Among them:
(1) Yongling Toll Station: The earthwork and foundation engineering of the site have been completed, the main project of the toll station office building and comprehensive building has been completed, 28 masonry projects have been completed, and the masonry of the office building has been completed. The project is not completed, and the main body of the toll canopy has been completed.
(2) Yongling Service Area: A total of 76% of the earthwork works in the South and North Districts have been completed, all basic projects have been completed, all the main projects in the North District have been completed, and the masonry work of dormitories and comprehensive buildings has been completed. Not yet completed; the main project of the southern gas station is completed, the canopy columns are completed, and the complex building frame columns are completed.
(3) Muqi Toll Station: The earthwork and foundation works of the site have been completed, the main works of the toll station office building and comprehensive building have been completed, 48% of the masonry work has been completed, and the toll canopy columns have been completed.
(4) Shangjiahe Toll Station: The earthwork and foundation works of the site have been completed, the main works of the toll station office building and comprehensive building have been completed, 82% of the masonry work has been completed, and the toll canopy columns have been completed .
(5) Nan Zamu Service Area: 92% of the earthwork work in the east and west areas has been completed, all foundation projects in the east and west areas have been completed, all the main works in the west area have been completed, the main work in the east area gas station has been completed, and the comprehensive building area has been completed. The beam pouring is completed, the main frame of the auto repair room is completed, the main project of the fire pool is completed, and the masonry work is completed66.
First contract paragraph: Ning Wei, project manager of Shenyang Overseas Construction Group Co., Ltd.
Second contract paragraph: Liu Chun, project manager of Liaoning Jindi Second Construction Responsible Company
Supervision unit: Dong Wei, Director of Shenyang Highway Engineering Supervision Co., Ltd.
Futong Expressway - passing through provinces and cities
Jilin Expressway passing through the province and passing through the city Tonghua Jingha Expressway Heda Expressway Jishuang Expressway Changshen Expressway Daguang Expressway Tieke Expressway Hunwu Expressway Yanchang Expressway Jihei Expressway Shenji Expressway Songchang Expressway Benji Expressway Tongshen Expressway Wangyan Expressway Yingdong Expressway Yiliao Expressway Fuchang Expressway Expressway Shensi Expressway Changping Expressway Shenha Expressway Changyu Expressway Yantu Expressway Jijiang Expressway Changji Expressway Liaoning Fushun Jingha Expressway Heda Expressway Danfu Expressway Shenhai Expressway Changshen Expressway Xinlu Expressway Fujin Expressway Naying Expressway Chisui Expressway Shenji Expressway, Danxi Expressway, Liaozhong Ring Expressway, Benji Expressway, Pichang Expressway, Yonghuan Expressway, Liaokai Expressway, Zhuanggai Expressway, Shen-Kang Expressway, Beijing-Shenyang Expressway, Shensi Expressway, Shen-Ha Expressway, Danla Expressway, Danla Expressway, Shenyang-Dalian Expressway, Tuyang High-Speed ??Railway Chao Expressway Coastal Expressway Panhai Expressway Panying Expressway Jinchaogao Expressway
Speed ??Dan-Chen Expressway Shen-Zhang Expressway Shen-Fu Expressway The above is Zhongda Consulting’s introduction to Fu-Tong Expressway. For more knowledge about highways, please pay attention to the construction knowledge column of Zhongda Consulting.
For more exclusive information about the construction industry, please pay attention to the WeChat account of Construction Network in real time.
For more information about the writing and production of bid documents and improving the bid winning rate, click on the customer service at the bottom for free consultation.
- Previous article:Medical waste prompt closed bucket slogan
- Next article:Can I lose weight like this?
- Related articles
- Lunan district, Tangshan announced the measures for reporting the special action of lightning storm.
- Take the best route from Zhengzhou to Hangjinqi.
- Write a composition of not less than 800 words with the theme of "Dream takes off here". "Here" refers to the university.
- Wuming Guihuo teenager "showed off his skills" on the road in the middle of the night and was photographed by the traffic police. What safety awareness do teenagers lack?
- What words can be used to pay tribute to the anti-epidemic hero?
- Traffic safety slogans on campus
- Hermes luggage design poster-Hermes classic platinum bag Birkin, what are the brand stories?
- Exciting high school slogan English
- Common musical expression terms
- What is an e-ticket?