How to construct rice grain stone

I. Overview of the Project

1. The construction site is located in Xianghe.

2. This project belongs to exterior wall coating project, with an area of about 10000 square meters.

3, all construction personnel should be strictly controlled in technology, the quality of all materials must meet the standards and meet the construction requirements.

4. The construction temperature of all engineering materials (moisture-proof sealing primer, special waterproof putty for external wall and natural stone paint) shall be kept above 5 degrees.

Second, the construction personnel requirements

1, all construction personnel must go through the construction-related formalities in time.

2. The company arranges accommodation for employees.

3, the company should be targeted to develop engineering technology, quality, safety, equipment, tools, materials, civilized construction, ideological and political work, logistics services and a series of management systems. Prepare the construction plan and make written technical disclosure. Prepare the construction progress plan.

4, the project department should be equipped with relevant professionals, personnel are related certificates, by the production, technology, quality, safety, planning, material supply, budget and other corresponding management personnel, the project intends to project duration, quality, cost, cost, safety and civilized construction to implement comprehensive management responsibility contract. Coordinate the relationship with the owner in the construction process, do a good job in the deployment and supply of manpower, materials and equipment, solve the problems in the construction in time, ensure the performance of the construction contract signed with the owner, and successfully complete the task. At the same time guarantee the quality and time limit for a project.

5. The construction deployment of this project is arranged according to our previous construction experience of similar projects. Our overall deployment is to organize professional classes to carry out construction operations to ensure the project quality and construction date.

6, construction personnel should have excellent professional skills, noble ideology and morality, and strictly abide by the discipline stipulated by the company.

Third, the construction safety measures

1, adhere to the idea of "safety first", have enough safety awareness and carry out safe construction.

2, the construction site is equipped with full-time security officer, security officer in addition to strictly implement the system at ordinary times, seize the ideological propaganda, but also should carry out safety construction regularity education.

3, before construction, construction organization design, there must be a detailed construction plan. Temporary works such as warehouses, workplaces, machinery and equipment, living facilities, etc. shall be arranged according to the lines and meet the safety requirements.

4, the construction site safety net, safety helmet, seat belt and other limiting devices must be complete.

5. Safety placards should be set up on the construction site, and signs such as "safety color" and "safety sign" must be hung on dangerous parts, and red lights should be set up in holes and ditches where people pass at night.

6, scaffolding, hanging basket, tools or scaffolding, etc. Selection and design of construction scheme and safety protection measures.

7. Bare wires and plastic wires shall not be used for the power cord, and shall not be laid along the ground. The distribution box must be waterproof and rainproof, and the electrical layout shall be carried out in accordance with regulations.

8, to do a good job of scaffolding collapse prevention, tic-tac-toe frame, gantry, dangerous parts to support. Once an emergency is found, the construction should be stopped immediately.

9. If there are major hidden dangers or violations, they should be corrected immediately to maintain safe construction.

10, keep the construction site clean, and isolate the power supply from combustible materials.

1 1. Materials and tools should be stored in each warehouse, watched by special personnel, and equipped with fire extinguishers to prevent fire and theft.

12, the construction personnel shall eat and live separately, and shall not defecate anywhere, smoke at the construction site, and shall not bring the fire into the construction site for any reason.

13. Construction personnel must wear safety helmets when entering the site. If working at height, they must wear safety belts. Scaffolding can only be used after being inspected by the safety officer.

14, construction personnel are not allowed to venture into or through, and are not allowed to walk in forbidden places.

15, the construction personnel must go to the dormitory to rest before 10 in the afternoon, ask for leave in case of something, and are not allowed to go out without permission.

Fourth, building materials

2. Bottom material: special waterproof putty for external wall.

3. Surface decoration material: natural real stone paint (primer, real stone paint, topcoat).

4. Product features: super hiding power, excellent environmental protection performance and good construction tolerance.

Verb (abbreviation of verb) construction method

(compiled according to national standards, enterprise standards and the current situation of this project) 1. Basic treatment: batch scraping special waterproof putty for external wall.

2. Closed wall foundation: After the base treatment meets the construction requirements, the damp-proof sealing primer is selected for roll coating, and the high-quality short-wool pipe is selected as the construction tool for uniform coating, so as to achieve the effect of fixing the floating sand at the base and isolating the wall from flooding alkali.

3. Divide lines with textured paper according to the construction requirements, then spray natural real stone paint, and finally spray topcoat.

Six, project quotation and time limit for a project

1. Project unit price: development area of 83 yuan/m2.

2. Construction period: according to the existing engineering quantity, our factory plans to complete it in 60 days (in case of rainy days or special circumstances, Party A and Party B will postpone the construction period through consultation).