How to write the elevator installation application report?
3 Basic requirements
3. 1 The quality management of the installation unit's construction site shall meet the following requirements:
3. 1. 1 has perfect acceptance criteria, installation technology and construction operation procedures.
3. 1.2 has a perfect installation process control system.
3.2 elevator installation engineering construction quality control shall meet the following requirements:
3.2. 1 Before elevator installation, civil handover inspection shall be conducted according to this process standard, and the Acceptance Record of Civil Handover of Elevator Installation shall be filled in Schedule A. ..
3.2.2 Before elevator installation, the elevator equipment shall be accepted according to this process standard, and the Acceptance Record of Elevator Installation Engineering Equipment shall be filled in Schedule B. ..
3.2.3 Each subdivisional work of elevator installation shall be subject to quality control according to this process standard, and each subdivisional work shall have self-inspection records.
3.3 The quality acceptance of elevator installation project shall meet the following requirements:
3.3. 1 The personnel involved in installation construction and quality acceptance shall have corresponding qualifications.
3.3.2 Units undertaking safety performance testing must have corresponding qualifications. Instruments and equipment shall meet the accuracy requirements and be within the validity period of verification.
3.3.3 The quality acceptance of subdivisional work shall be carried out on the basis that the elevator installation unit has passed the self-inspection.
3.3.4 The quality of subdivisional work shall be inspected and accepted respectively according to the master control project and general project.
3.3.5 Concealed works shall be inspected and accepted by the elevator installation unit before concealment, and acceptance documents shall be formed.
4 General provisions
4. 1 computer room (if any) shall also meet the following requirements:
4. 1. 1
The computer room should be equipped with fixed electrical lighting, and the ground illumination should not be less than 200lx. One or more power sockets shall be set in the computer room. Switches or similar devices should be installed at an appropriate height near the entrance of the machine room to control the lighting power supply of the machine room.
4. 1.2 The machine room shall be ventilated, and stale air inhaled from other parts of the building shall not be discharged into the machine room.
4. 1.3 Provide the access and handling space required for equipment entry according to the requirements of product suppliers.
4. 1.4 elevator workers should be able to enter the machine room or pulley room conveniently without using other auxiliary facilities for the time being.
4. 1.5 The machine room shall be made of durable materials that are not easy to generate dust, and the ground of the machine room shall be made of non-slip materials.
Note: This project can be accepted after elevator installation.
4. 1.6
In a computer room, when there are more than two working platforms with different planes, and the height difference between adjacent platforms is more than 0.5m, stairs or steps should be set up, and safety protective railings with a height of not less than 0.9m should be set up. When there is a pit on the ground of the computer room or a pit with a depth greater than 0.5m, it should be covered. The personnel activity space and the clear height above the workbench should not be less than1.8m.
4. 1.7 There should be no less than 0.8m×0.8m unblocked passage for personnel to enter and exit the trap door, and it should be kept open after the door is in place. After the trapdoor is closed, it should be able to support the weight of two people (each person should be calculated by the force acting on any 0.2m×0.2m area of the door at 1000N), and there should be no permanent deformation.
4. 1.8 doors or access doors shall be equipped with key locks, which shall be opened from the machine room without keys. Trapdoors used only for transportation equipment can only be locked in the computer room.
4. 1.9 Power neutral line and grounding line should be separated. The grounding resistance of the grounding device in the machine room should not be greater than 4Ω.
4. 1. 10 machine room should have good seepage prevention and water leakage protection.
4.2 The shaft shall also meet the following requirements:
4.2. 1 Shaft size refers to the minimum clearance size of the shaft measured by the projection of the shaft section perpendicular to the design and operation direction of the elevator, which shall meet the requirements of civil layout, and the allowable deviation shall meet the following requirements:
When the elevator stroke height is less than or equal to 30m, 1 is 0 ~+25mm;;
2 0 ~+35mm; when the elevator stroke height is more than 30m and less than 60m;
3 when the elevator stroke height is greater than 60m and less than or equal to 90m, it is 0 ~+50mm;;
4 When the elevator stroke height is greater than 90m, the allowable deviation should meet the requirements of civil engineering layout.
4.2.2 Fully closed or partially closed hoistway, isolation protection of hoistway, hoistway wall, bottom surface and pit top plate should have sufficient strength to install elevator components, and non-combustible materials should be used, and it is not easy to generate dust.
4.2.3 When the pit depth is more than 2.5m and the building layout allows, the pit entrance meeting the requirements of the safety door shall be set; When there is no other access to the pit, a permanent device should be installed to enter the pit from the landing door, and the device should not extend into the elevator operation space.
4.2.4 The hoistway shall be dedicated to the elevator, and no equipment and cables unrelated to the elevator shall be installed in the hoistway. Heating equipment can be installed in the shaft, but steam and water should not be used as heat sources, and the control and adjustment device of heating equipment should be installed outside the shaft.
4.2.5 The shaft shall be provided with permanent electric lighting, and the illumination in the shaft shall be no less than 50lx. Install lamps and lanterns within 0.5m of the highest and lowest points of the shaft, install intermediate lights, and set control switches in the machine room and the pit respectively.
4.2.6 In a hoistway equipped with multiple elevators, guardrails should be set between the bottom pits of the elevators, with the lowest point not exceeding 0.3m from the ground of the bottom pit and at least extending to a height of 2.5m above the ground of the lowest floor. The gap between the guardrails and the hoistway wall in the width direction of the guardrails should not be greater than 150mm.
When the horizontal distance between the top edge of the car and the moving parts (car, counterweight or counterweight) of the adjacent elevator is less than 0.5m, the guardrail shall extend to the height of the whole hoistway. The width of guardrail shall not be less than the width of protected moving parts (or parts thereof) plus 0. 1m on each side.
4.2.7 Anti-seepage and water leakage should be well done in the pit, and there should be no accumulated water in the pit.
4.2.8 Each layer shall be marked with a horizontal datum.
5 Construction preparation
5. 1 Requirements for the entry acceptance and re-inspection of materials, finished products, semi-finished products and parts
5. 1. 1 Wood formwork shall be knotless, dry, tough and undeformed wood. And shave it off.
5. 1.2 According to different lifting heights, the formwork section is not small, and the values listed in Table 5. 1.2 are not small.
See table 5. 1.2 for the sample section requirements.
Lifting height (m), thickness (mm) and width (mm)
≤20 20~60 >6040
50 6080 100
100
Note: The required dimensions in the table are the net dimensions after processing.
5. 1.3 wood square (formwork erection), angle steel, M 16 expansion bolt, U-clamp, nail, piano steel wire, 8# lead wire, etc. After processing, the cross section shall not be less than100×100 mm.
5.2 Requirements for construction machines, equipment and construction site
5.2. 1 Main machine tools:
Electric hammer, hammer, spirit level, square ruler, steel ruler, box ruler, wire pendant, Mo Dou.
Operating conditions:
1 The scaffold of the shaft has been completed, which meets the requirements of the Operating Rules for Scaffolding Safety Technology in Construction and Installation Engineering and the drawings provided by the installation department.
2. The highest point of the scaffold platform is located under the roof of the shaft: 1.5 ~ 1.7m, so as to stably place the formwork. It is best to use four short pipes for the riser of the top scaffold. After the short pipe is removed, the vertex of the remaining riser should be 500mm below the support of the highest floor to facilitate the installation of the car (Figure 5.2.2.2).
3 The span of scaffold pipe layout should be1.4 ~1.7m. To facilitate installation, a horizontal pipe should be set 200 ~ 400 mm below each layer of support, and a horizontal pipe should be installed between two horizontal pipes to facilitate climbing up and down. Scaffolding should be supplemented with at least 2/3 scaffolding boards at each step, and each floor should be staggered to reduce the risk of falling (Figure 5.2: At both ends of scaffolding, exhaust pipes 150 ~ 200mm are fastened with 8# lead wires (Figure 5.2.3.b).
Scaffolding must be checked and accepted by the safety technology department before it can be used.
5. The electricity used for site construction and lighting must meet the requirements of the national standard "Technical Specification for Safety of Temporary Electricity Use in Construction Sites".
6 doors at all levels must be equipped with good protective doors; Doors at all levels and scaffolding at every step should be kept clean and free of sundries.
7 The actual measurement of the height of the top floor and the depth of the bottom pit should be consistent with the drawings, and check whether it can meet the requirements of climbing the ladder without crossing.
6 construction technology
6. 1 process flow:
Erecting formwork frame → determining datum line by measuring axis → hanging datum line when formwork is in place.
6. 1. 1 Installation of sample rack:
1 angle steel is horizontally and firmly fixed on the shaft wall about 1.2m below the roof of the shaft with expansion bolts.
2 If the shaft wall is a brick wall, a hole should be dug in the horizontal direction about 1. 1m below the shaft roof, and the formwork wooden support should be placed firmly and fixed at both ends. 3. The square end of the sample holder shall be leveled, and the levelness error shall not be greater than 3/ 1000.
6. 1.2 Measure the axis and determine the standard line.
1 Pre-put two floor entrance line survey shafts. Generally, the distance between two lines is the net opening of the door.
2 according to the shaft measurement results to determine the baseline, should pay attention to the problem:
(1) Do the components installed in the hoistway, such as speed limiter steel wire rope, layer selector steel belt, limit switch, neutral box, cable hanger, etc., cause obstacles to the car operation? At the same time, the distance between the slide and sill on the car door and the distance between the counterweight and the wall should be considered. It is necessary to ensure that the clear distance between the moving parts of the car and counterweight and the static parts and building structures in the hoistway is not less than 30mm when running up and down.
(2) When determining the position of the trolley track line, the installation position should be considered according to the height requirements of the track frame.
(3) When determining the center line of the counterweight track, the counterweight width (including the counterweight block and the most prominent part) should be considered, and the clearance with the wall and the car should not be less than 50 mm ..
(4) For elevators with front and rear doors (through doors), the depth of the hoistway should be ≥ the width of the landing sill ×2+ the gap between the landing sill and the car sill ×2+ the car depth. And should consider whether the vertical condition of the shaft wall meets the installation requirements.
(5) Determine the threshold position of each floor, and measure the distance between each bracket and the line according to the door line of each floor. If you plan well, you must take care of the majority. It is necessary to consider less brackets or walls, and to stabilize the windowsill farthest from the wall. The gap between the doorpost and the upper wall is less than 30 mm ..
(6) For the elevator with marble door cover and decorative wall on the floor door building, the construction of door cover and decorative wall should be considered in addition to the consideration in (5) above when determining the floor door baseline.
(7) When installing two or more parallel elevators, attention should be paid to whether the center distance of each elevator is consistent with the architectural drawings. According to the construction situation of the shaft, the position of all landing door indicator lights and button boxes should be considered comprehensively, so that their heights are consistent, coordinated with the building and beautiful.
(8) When determining the baseline of several elevators that are relatively parallel, in addition to the above precautions, the width of the elevator waiting hall on both sides should be consistent according to the building and the door cover, and the doors of two elevator floors should be relatively consistent to ensure the aesthetic requirements of elevator door cover construction or civil marble door cover construction.
(9) When determining the baseline, the layout of the computer room should also be reviewed. Whether there is any problem in the layout of electrical equipment such as traction machine, I-beam, speed limiter, generator, limit switch and layer selector, and whether it is convenient for maintenance, make necessary adjustments.
6. 1.3 template in place, hang the baseline:
1 template processing and manufacturing. The wooden strips of the sample should be planed and straightened on all sides, assembled according to the requirements of the drawings, and the sample should be firmly fixed in place with glue.
In order to simplify the construction, the method of nailing battens directly on the wood square can be adopted instead of hanging the baseline with the whole template. However, the materials used must meet the requirements of the first section of this chapter.
2 No matter whether the formwork method or the straight nailing method is adopted, the center line of the elevator shaft, the center line of the car frame and the center line of the counterweight shall be determined after overall consideration according to the requirements of Article 6. 1.2 (Figure 6. 1.3. 1), and then the setting-off points of each reference vertical line shall be determined. When crossing a line, check whether it is correct with a thin pencil, and then recheck each diagonal line. The levelness of the battens on the formwork or wood square in the whole plane shall not be greater than 3mm.
3 At the formwork, hang the lighter objects at one end of the steel wire and slowly lower them into the pit in sequence. The middle of the vertical line cannot touch scaffolding or other objects, nor can the steel wire have a knot.
4 At the pay-off point, vertically saw or draw a small V-shaped groove with a saw blade or an electrician's knife, so that the apex of the V-shaped groove is the pay-off point, and pay-off is carried out to prevent errors caused by the displacement of the baseline, and the name of the line is marked at the pay-off point, and the tail line is firmly tied on the fixing nail.
5. After the line into the pit, replace the hanging object when paying off with a line pendant, and let it stand vertically naturally. If the trip is high or the wind is strong, it is difficult for the steel wire pendant to rest. You can put a bucket in the pit and put the steel wire pendant in water or engine oil to increase its swing resistance and let the steel wire pendant rest as soon as possible.
6 Fix the lower formwork with wood square support at 600 ~ 1000 mm of the pit, fix the line on the formwork wood with U-shaped nails after the baseline is fixed, and then check the size and diagonal of each setting-out fixed point on the formwork. After confirmation, proceed to the next process.
7 quality standards
7. 1 determination of baseline
When determining the baseline, we should consider the dimensions of all parties in the shaft, try to avoid planing, and ensure that the spacing between the moving parts and the wall meets the requirements;
7.2 Stability and Verification of Reference Lines
When there is no wind, the baseline should be stable, and the baseline can be stable only when it is naturally static. In order to ensure its accuracy, the baseline spacing and diagonal baseline size should be checked after stabilization, and then checked again with laser pay-off.
7.3. 1 The baseline size must conform to the drawings, and the deviation of each line should not be greater than 0.3 mm.
Inspection method: ruler measurement.
7.3.2 The datum line must be vertical.
Inspection method: messenger wire and ruler.
7.4. The horizontal deviation of1formwork support shall not be greater than 3/ 1000.
7.4.2 The center deviation of parallel elevators and landing doors shall not exceed 20mm.
7.4.3 The deviation between the center line of the elevator and the landing door shall not exceed 20mm.
8 construction test plan
After template installation and baseline hanging are completed, check and record the setting-out size.
9 site safety production and civilized construction requirements
9. 1 Prevent falling objects from injuring people during operation.
9.2 The door bars of each floor shall be kept intact.
9.3 When entering the shaft construction, protection should be done to prevent falling.
9.4 Dust-proof measures should be taken when digging holes in the floor display box and call box at the inner wall of the shaft and the landing door, and the garbage should be cleaned up in time.
10 finished product protection
10. 1 The gate fences at all levels shall be kept intact to prevent non-working personnel from entering and leaving at will.
10.2 during operation, prevent objects from falling and avoid breaking samples.
10.3 When entering and leaving the tunnel, be careful not to touch the floor entrance line; Pay attention to the datum line when working in the well, especially when welding.
1 1 project quality acceptance
After the formwork installation and baseline hanging are completed, the inspection and acceptance records shall be made according to the "Seven Quality Standards" of this process, and the records shall be made according to Schedule C. ..
12 prevention and treatment of common quality problems in engineering
12. 1 When determining the reference line of car guide rail, check whether the drawing dimensions are consistent. Inconsistencies should be based on physical dimensions. And passed the verification of relevant departments.
12.2 before each operation, the baseline shall be rechecked to confirm that there is no displacement and no contact with other objects before operation.
12.3 When holes are dug in the inner wall of the shaft and the floor display box and calling box at the door of the floor, protective measures should be taken, and scaffolding boards should be cleaned in time to prevent the samples from being broken.
Code for acceptance of engineering quality-Provisions on inspection and evaluation records of construction units and supervision (construction) units
record of acceptance
The master control project 1, the interior of the machine room and the civil (steel structure) layout of the hoistway must meet the requirements of the civil layout of the elevator.
2 Article 4.2.2 Main power switch
Article 4.2.3 of Axis 3
The general project 1 computer room shall also comply with the provisions of Article 4.2.4.
2. The provisions of article 4.2.5, mine should also comply with.
Elevator installation engineering equipment entry quality acceptance record table b
The provisions of the acceptance specification for the engineering quality inspection and evaluation records of the construction unit and the acceptance records of the supervision (construction) unit.
Article 5. 1. 1
(2) Product factory certificate
(3) Copy of type test certificate of door lock device, reducer, safety gear and buffer.
The accompanying documents of the general item 1 shall also include (1) Article 4. 1.2 of the packing list.
Article 5.65438 +0.2
(2) Installation, use and maintenance instructions
(3) Electrical schematic diagram of power supply and safety circuit
(4) Schematic diagram of hydraulic system
2 Equipment parts and components are in conformity with the packing list.
3. The appearance of the equipment is not obviously damaged.
- Related articles
- What has Gannan Prefecture of Gansu Province done to improve the environment?
- Yulin Inn in Yulin Fort
- The effect of establishing grass-roots omnipotent king
- 202 1 What is the theme of the 5th Conference of the Parties to the Convention on Biological Diversity?
- A man drives a Siberian tiger in Hunchun, Lu Yu. What should he do in this case?
- 2020 New Year’s Eve drama—Ghosn’s “Harry Houdini-style” escape
- The candy taster introduced it in English.
- Handwriting the second half-price pop poster-How to rewind pop?
- How to apply for Sichuan Pass online?
- How to write a handwritten newspaper about the most glorious content of labor