Joke Collection Website - Blessing messages - The order of decoration is very important. When will furniture and home appliances enter the market?

The order of decoration is very important. When will furniture and home appliances enter the market?

In the process of decoration, we have encountered such a situation: we have to connect water and electricity, but even the equipment is still struggling with which brand ... The bricklayer is in place, and the tiles are still being processed in the distant fields ...

This is because we didn't consider the time for the main materials to enter the site in advance, which delayed a lot of construction period. Similarly, when furniture and household appliances enter the market in the later period, the order of customization and entry also has corresponding time periods.

Although the entry of furniture and household appliances is after the hard installation, it is too late to decide after the hard installation is completed! Household appliances, in particular, must be prepared in advance, and they should also be prepared when they are hard-loaded. So what do you need to order at which nodes? Let's have a look.

First, it is difficult to install before water and electricity

1. Determine the equipment to be used at home: whether central air conditioner, air conditioner cabinet, air conditioner hanging machine, fresh air system or household water purification system are needed. These all involve the question of how to get to the circuit waterway.

Details are as follows:

A. If the central air conditioning/fresh air system is adopted, it is necessary to determine and reserve the position of the switch and determine the position of the air conditioning drain pipe when taking the circuit.

If cabinets and air conditioners are used, the positions should be determined in advance, and the positions of high and low sockets and air conditioner openings should be reserved. ?

B. If there is demand for household water purification systems (pre-filtration, water purifier and water softener), especially for families that need to install water softeners, the location must be set in advance, and special power supply, floor drain and launching need to be reserved.

2. Be sure to find a good cabinet manufacturer in advance and conduct the first on-site measurement before the hydropower starts;

A. First communicate with the cabinet designer about the types of household appliances needed in the kitchen, so that the cabinet designer can make a preliminary plan;

B. According to the determined types of household appliances, help the owner to determine the scheme of kitchen water and electricity transformation, involving which household appliances are needed for cabinets and the placement of specific positions in combination with cabinet design;

C. The kitchen water and electricity shall be implemented according to the corresponding scheme issued by the cabinet designer.

3. Determine the location of various household appliances and bulky furniture, such as the location of reserved wires for TV sets, the location of sockets near sofas/cabinets, and the location of switch panels, so as to avoid the situation that placing household appliances and furniture in the later stage will affect the use of switch panels, or the reserved sockets cannot be used.

On the whole, the water and electricity part mainly involves the advance reservation of equipment (air conditioning, purified water and soft water) and cabinets (kitchen appliances), the water and electricity reservation of lamps, kitchen utensils and sanitary ware, and the position reservation of switches and sockets. The water circuit is a concealed installation project, and it is troublesome to modify it later, so it needs careful examination and approval in the early stage, so that the water circuit modification in the early stage can be put in place at one time.

Second, before the carpenter comes into play.

It is necessary to determine the depth position of furniture that needs ceiling in advance, such as custom cabinets (mostly hanging cabinets) and tatami. In order to facilitate carpenters to match and combine with later customized furniture when making ceiling.

3. After the bricklayer's work is completed

1. The reserved cabinet designer came to the door again. On the basis of the completion of the wall and floor, the specific dimensions will be determined again, and the specific cabinet design scheme will be worked out (at this time, the owner will also cooperate with the cabinet designer to put forward the details of the cabinet design, such as the types, brands and sizes of kitchen appliances that have been scheduled before), and start to arrange the door-to-door installation of the cabinet.

2, bricklayer's completion refers to the indoor ceiling (carpentry) ground (bricklayer) has been completed, the general appearance of the room has been presented. After determining the style and color of the whole house, you can start ordering the finished furniture in advance, determining the custom furniture manufacturer and measuring it at home (here, pay attention to whether the door of the kitchen and bathroom is a door cover, if not, the side wall of the door opening needs to be bricked; If the door cover is made, there is no need to stick bricks on the side wall of the door opening. The width and height of the door will become smaller after the side wall of the door cover is bricked, which needs the owner to decide in advance and notify the bricklayer.

Fourth, the painter comes into play.

Before the painter starts construction, the owner needs to inform the workers whether there are window covers, stones on the windowsill and dumb covers at the entrance. Where there are no window covers, stone materials and dumb mouth covers, workers need to use gypsum powder and putty powder for leveling; where there are window covers, stone materials and dumb mouth covers, there is no need to deal with them.

After the painter finishes, start the installation of finished products. Here, we need to pay attention to several orders:

1, the kitchen ceiling must be completed before the cabinet is installed (it is best to install the range hood after the cabinet is installed)

2, wooden floor must be completed before the skirting board installation.

3, windowsill stone must be completed before installing the window cover.

Furniture and home appliances will enter the market after hard installation.

After the completion of hard installation, the ceiling and floor have been completed, and the skirting line of door and window covers including doors has been basically installed during hard installation. At this time, customized furniture and finished furniture can enter the market according to the scheduled time.

The order of furniture entering the market is that the large pieces that will not move in the future, such as custom cabinets and tatami, can then move into the furniture such as beds and sofas that have been set before, and finally the home appliances enter the market, supplemented by soft assembly ornaments. Wait until the smell passes, and you can stay in your new home!

Finally, mention:

1, furniture and household appliances must pay attention to the protection of floors and walls during transportation and installation! Don't leave scratches when carrying furniture, and it is more troublesome to repair it locally later (it is easy to have problems such as color difference);

2. When booking and buying household appliances, be sure to determine the size of furniture and household appliances, and the corresponding relationship between furniture and wall modeling (size, color, etc.). );

Generally speaking, although the order of furniture and household appliances entering the market seems simple on the surface, what is really time-consuming and laborious is the scheduled stage before entering the market, which is an important stage related to whether the whole process is smooth, not delayed and not reworked, but after hard work, it means that you are only one step away from liberation!

(This article is only for exchange and sharing, the picture is from the network, and it is invaded and deleted.)

The above content was shared by the designer of Xi 'an, Mouton, Shanghai. He is a good user. I hope I can help you ~