What are the materials for application for commencement of construction?
Before the project starts, the construction unit needs to submit the following information to the supervision unit:
1. Construction license; bid winning notice and construction contract
2. Construction unit Business license, production safety license, enterprise qualifications
3. Project organizational structure, personnel list and special work certificates (see originals, keep copies)
4. Report on on-site equipment use Review (with qualified test report)
5. Construction organization design, emergency plan and special plan
6. Construction progress plan
7. Terrain retest Reports, measurement and setting out data
8. Inspection of entry equipment and entry materials
9. Application for commencement of construction, commencement of construction report
"Construction Project Supervision Specifications"
Article 5
Approval of the construction permit by the competent government department is one of the important conditions for starting construction.
"Construction Law of the People's Republic of China"
Article 64
Anyone who constructs without obtaining a construction permit shall bear legal responsibility .
Extended information:
Irregular behaviors in reporting for construction start-up:
(1) The owner started construction in violation of regulations.
The owner is motivated by economic interests and pursues the progress of the project, or for other reasons, hastily decides on construction before the construction permit is obtained. The construction unit and supervisors also considered their own interests or had no choice but to prevent the owners from violating regulations. Although some resisted, they failed to stop it, and some even acquiesced to start construction.
(2) The supervision procedure is chaotic.
Because the supervisors are afraid of taking responsibility, they deliberately postpone or delay the normal supervision work, and fail to witness and sign in time for the review and inspection of materials and processes during the construction phase, resulting in distortion of supervision data and loss of control of construction quality.
Reference material: Baidu Encyclopedia of Construction Law of the People's Republic of China - Construction Project Supervision Code
- Related articles
- Doesn't the postal bank card time deposit SMS show the balance?
- I can't understand what message China Telecom sent me to inquire about the usage of telephone charges.
- A short message in the middle of the night is eight words.
- How to set up Apple X breathing light How to set up Apple X breathing light
- How to set up the voice broadcast of the warehouse outgoing instrument
- Which female character in anime is your favorite?
- How to download CRBT from Unicom 3G card?
- If a girl doesn't like a boy, she will send a holiday greeting message to the boy and ask her best friend if the boy likes her.
- What's the relationship between your wife calling another man's husband in a text message?
- What does it mean for your legend to apply for activation in other places?